Foote Creek Rim
180 Ex 373 N 2 Mile Rte 13, McFadden, WY 82083Plant Summary Information
Foote Creek Rim is ranked #31 out of 73 power plants in Wyoming in terms of total annual net electricity generation.
Foote Creek Rim generated 191.3 GWh during the 3-month period between December 2024 to March 2025.
Plant Name | Foote Creek Rim |
---|---|
Utility Name | PacifiCorp |
Location | Carbon County, WY |
Initial Operation Date | December 2024 |
Last Update | Mar 2025 |
Annual Generation | 256.3 GWh |
Annual Consumption | 874.6 k MMBtu |
Ranked #2,099 out of 12,288 Power Plants Nationwide | |
Ranked #650 out of 1,353 Wind Power Plants Nationwide | |
Ranked #31 out of 73 Wyoming Power Plants | |
Ranked #17 out of 31 Wyoming Wind Power Plants | |
Fuel Types | Wind |
Map of Foote Creek Rim
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Foote Creek Rim.
Monthly Net Generation for Foote Creek Rim
Foote Creek Rim Details
Summary Information | |
---|---|
Plant Name | Foote Creek Rim (67916) |
Plant Address | 180 Ex 373 N 2 Mile Rte 13, McFadden, WY 82083 |
Utility | PacifiCorp (14354) |
Latitude, Longitude | 41.6283, -106.2013 |
Generation Dates on File | Dec 2024 to Mar 2025 |
Initial Operation Date | December 2024 |
Annual Generation | 256.3 GWh |
Fuel Types | Wind |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Regulated |
NERC Region | WECC |
Balancing Authority | PacifiCorp - East (PACE) |
NAICS Code | Utilities (22) |
Sector | Electric Utility (1) |
Water Source | |
Ash Impoundment | No |
Transmission / Distribution Owner | PacifiCorp (14354) WY |
Grid Voltage | 135.00 kV |
Energy Storage | No |
Generator 1 Details Operating December 2024
Technology | Onshore Wind Turbine |
---|---|
Prime Mover | Wind Turbine, Onshore |
Ownership | Single Owner |
Nameplate Capacity | 134.8 MW |
Nameplate Power Factor | 0.95 |
Summer Capacity | 134.8 MW |
Winter Capacity | 134.8 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | December 2024 |
Sector Name | Electric Utility (1) |
Energy Source | Wind |
Turbines/Hydrokinetic Buoys | 43 |
Turbine Details | |
Number Of Turbines | 43 |
---|---|
Predominant Turbine Manufacturer | Vestas |
Predominant Turbine Model Number | V136-4.2 |
Design Wind Speed | 17 MPH |
Wind Quality Class | 1 - High Wind |
Turbine Hub Height Feet | 136 |
Foote Creek Rim Plant Owners
Owner Name | Address | Ownership | |
---|---|---|---|
We couldn't locate any owners for this plant |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#640 | Rocky Ridge Wind Project | Hobart, OK | 259.5 GWh |
#641 | South Peak Wind | Geyser, MT | 258.8 GWh |
#642 | Criterion | Oakland, MD | 258.5 GWh |
#643 | EcoGrove Wind LLC | Lena, IL | 258.0 GWh |
#644 | Borderlands Wind, LLC | Quemado, NM | 257.8 GWh |
#645 | Sendero | Hebbronville, TX | 257.7 GWh |
#646 | Sigel Wind Park | Harbor Beach, MI | 257.4 GWh |
#647 | FPL Energy Vansycle LLC (OR) | Touchet, OR | 257.0 GWh |
#648 | Juniper Canyon I Wind Project | Bickleton, WA | 256.8 GWh |
#649 | Copenhagen Wind Farm | Copenhagen, NY | 256.7 GWh |
#651 | Brookfield | Pigeon, MI | 254.6 GWh |
#652 | Crystal Lake 3 LLC | Britt, IA | 254.3 GWh |
#653 | Stanton Wind Energy LLC | Lenorah, TX | 253.9 GWh |
#654 | Cimarron Windpower II | Cimarron, KS | 253.9 GWh |
#655 | South Trent Wind Farm | Sweetwater, TX | 252.5 GWh |
#656 | Minco Wind II, LLC | Minco, OK | 251.0 GWh |
#657 | Smoky Hills Wind Project Phase I | Lincoln, KS | 250.8 GWh |
#658 | Rockland Wind Farm | American Falls, ID | 250.6 GWh |
#659 | Blackstone Wind Farm LLC | Ransom, IL | 250.1 GWh |
#660 | Los Vientos Wind 1B | Sebastian, TX | 249.4 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Foote Creek Rim.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Alcova | Alcova, WY | 119.2 GWh | 68.9 mi |
Boswell Wind | Rock River, WY | 395.5 GWh | 26.4 mi |
Dunlap | Medicine Bow, WY | 366.5 GWh | 28.8 mi |
Ekola Flats | Hanna, WY | 776.6 GWh | 22.5 mi |
Foote Creek I | McFadden, WY | 215.5 GWh | 0 mi |
Foote Creek III | McFadden, WY | 14.6 GWh | 2.8 mi |
Foote Creek IV | Rock River, WY | 11.6 GWh | 3.4 mi |
Fremont Canyon | Alcova, WY | 227.7 GWh | 66.1 mi |
Happy Jack Windpower Project | Cheyenne, WY | 62.4 GWh | 70.9 mi |
High Plains | Rock River, WY | 274.1 GWh | 10.3 mi |
Kortes | Sinclair, WY | 155.4 GWh | 51.4 mi |
McFadden Ridge | Rock River, WY | 84.1 GWh | 12.7 mi |
Medicine Bow | Medicine Bow, WY | 11.1 GWh | 14.5 mi |
Roundhouse Wind Energy Project | Cheyenne, WY | 847.3 GWh | 67.6 mi |
Seminoe | Sinclair, WY | 137.0 GWh | 51.5 mi |
Seven Mile Hill | Medicine Bow, WY | 399.8 GWh | 22.1 mi |
Silver Sage Windpower | Cheyenne, WY | 115.1 GWh | 70.1 mi |
Sinclair Oil Refinery | Sinclair, WY | 7.6 GWh | 48 mi |
TB Flats | Medicine Bow, WY | 1.5 TWh | 38 mi |
Whiskey Hill Solar | Walden, CO | 2.3 GWh | 56.6 mi |