Seven Mile Hill
2681 US HWY 30, Hanna, WY 82327Plant Summary Information
Seven Mile Hill is ranked #24 out of 69 power plants in Wyoming in terms of total annual net electricity generation.
Seven Mile Hill generated 162.2 GWh during the 3-month period between September 2025 to December 2025.
| Plant Name | Seven Mile Hill |
|---|---|
| Utility Name | PacifiCorp |
| Location | Carbon County, WY |
| Initial Operation Date | December 2008 |
| Last Update | Dec 2025 |
| Annual Generation | 458.3 GWh |
| Annual Consumption | 1.8 M MMBtu |
| Ranked #1,487 out of 13,301 Power Plants Nationwide | |
| Ranked #426 out of 1,377 Wind Power Plants Nationwide | |
| Ranked #24 out of 69 Wyoming Power Plants | |
| Ranked #13 out of 27 Wyoming Wind Power Plants | |
| Fuel Types | Wind |
Map of Seven Mile Hill
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Seven Mile Hill.
Monthly Net Generation for Seven Mile Hill
Monthly Plant Fuel Consumption for Seven Mile Hill
Seven Mile Hill Details
| Summary Information | |
|---|---|
| Plant Name | Seven Mile Hill (56843) |
| Plant Address | 2681 US HWY 30, Hanna, WY 82327 |
| Utility | PacifiCorp (14354) |
| Latitude, Longitude | 41.9203, -106.3758 |
| Generation Dates on File | Dec 2008 to Dec 2025 |
| Initial Operation Date | December 2008 |
| Annual Generation | 458.3 GWh |
| Fuel Types | Wind |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Regulated |
| NERC Region | WECC |
| Balancing Authority | PacifiCorp - East (PACE) |
| NAICS Code | Utilities (22) |
| Sector | Electric Utility (1) |
| Water Source | |
| Ash Impoundment | |
| Transmission / Distribution Owner | PacifiCorp (14354) WY |
| Grid Voltage | 230.00 kV |
| Energy Storage | No |
Generator 1 Details Operating December 2008
| Technology | Onshore Wind Turbine |
|---|---|
| Prime Mover | Wind Turbine, Onshore |
| Ownership | Single Owner |
| Nameplate Capacity | 122.1 MW |
| Summer Capacity | 99 MW |
| Winter Capacity | 99 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | December 2008 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Wind |
| Turbines/Hydrokinetic Buoys | 66 |
| Multiple Fuels | No |
| Turbine Details | |
| Number Of Turbines | 66 |
|---|---|
| Predominant Turbine Manufacturer | GE |
| Predominant Turbine Model Number | 1.85-87 |
| Design Wind Speed | 19 MPH |
| Wind Quality Class | 2 - Medium Wind |
| Turbine Hub Height Feet | 262 |
Generator 2 Details Operating December 2008
| Technology | Onshore Wind Turbine |
|---|---|
| Prime Mover | Wind Turbine, Onshore |
| Ownership | Single Owner |
| Nameplate Capacity | 24.1 MW |
| Summer Capacity | 19.5 MW |
| Winter Capacity | 19.5 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | December 2008 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Wind |
| Turbines/Hydrokinetic Buoys | 13 |
| Multiple Fuels | No |
| Turbine Details | |
| Number Of Turbines | 13 |
|---|---|
| Predominant Turbine Manufacturer | GE |
| Predominant Turbine Model Number | 1.85-87 |
| Design Wind Speed | 19 MPH |
| Wind Quality Class | 2 - Medium Wind |
| Turbine Hub Height Feet | 262 |
Seven Mile Hill Plant Owners
| Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #416 | Glenrock | Glenrock, WY | 469.2 GWh |
| #417 | Cranell Wind Farm LLC | TBD, TX | 469.2 GWh |
| #418 | Scioto Ridge Wind Farm | Belle Center, OH | 468.2 GWh |
| #419 | La Chalupa, LLC | Rio Hondo, TX | 466.8 GWh |
| #420 | Heartland Farms | Middleton, MI | 464.8 GWh |
| #421 | Pleasant Valley Wind Farm | Dexter, MN | 463.6 GWh |
| #422 | 1370 Shannon | Windhorst, TX | 463.5 GWh |
| #423 | Adams Wind | Lenox, IA | 460.4 GWh |
| #424 | Polaris Wind Park | North Star Township, MI | 459.4 GWh |
| #425 | Walleye Wind | Beaver Creek, MN | 459.1 GWh |
| #427 | Limon Wind II | Limon, CO | 458.1 GWh |
| #428 | Otter Creek Wind Farm LLC | Ransom, IL | 457.7 GWh |
| #429 | Prairie Rose Wind Farm | Hardwick, MN | 457.5 GWh |
| #430 | Ranchland Wind Project I | Cisco, TX | 455.4 GWh |
| #431 | Wildhorse Mountain Wind Facility | Clayton, OK | 454.1 GWh |
| #432 | Seiling Wind I | Seiling, OK | 454.1 GWh |
| #433 | West Camp Wind Farm | Heber, AZ | 453.2 GWh |
| #434 | Prairie Queen Wind Farm | Moran, KS | 452.7 GWh |
| #435 | Salt Creek Wind | Traer, IA | 452.0 GWh |
| #436 | Minco Wind III, LLC | Minco, OK | 449.3 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Seven Mile Hill.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Alcova | Alcova, WY | 107.2 GWh | 46.8 mi |
| Boswell Wind | Rock River, WY | 1.2 TWh | 26.1 mi |
| Campbell Hill Windpower | Glenrock, WY | 265.8 GWh | 78 mi |
| Dave Johnston | Glen Rock, WY | 2.7 TWh | 70.4 mi |
| Dunlap | Medicine Bow, WY | 416.7 GWh | 14 mi |
| Ekola Flats | Medicine Bow, WY | 792.8 GWh | 1.2 mi |
| Foote Creek Rim | McFadden, WY | 618.0 GWh | 22.1 mi |
| Fremont Canyon | Alcova, WY | 233.5 GWh | 44 mi |
| Glenrock | Glenrock, WY | 469.2 GWh | 80.7 mi |
| High Plains | Rock River, WY | 341.2 GWh | 25.3 mi |
| Kortes | Sinclair, WY | 105.7 GWh | 31.3 mi |
| Laramie River Station | Wheatland, WY | 8.2 TWh | 77.8 mi |
| McFadden Ridge | Rock River, WY | 104.8 GWh | 24 mi |
| Pioneer Wind Park, LLC | Glenrock, WY | 252.6 GWh | 61.6 mi |
| Rock Creek Wind | McFadden, WY | 623.6 GWh | 27.9 mi |
| Seminoe | Sinclair, WY | 84.5 GWh | 31.8 mi |
| Sinclair Oil Refinery | Sinclair, WY | 5.9 GWh | 39 mi |
| TB Flats | Medicine Bow, WY | 1.4 TWh | 19.2 mi |
| Top of the World Windpower Project | Glenrock, WY | 541.1 GWh | 75.7 mi |