Fillmore County Solar Project

14868 140th St, Spring Valley, MN 55975

Plant Summary Information

Fillmore County Solar Project is ranked #7 out of 537 solar farms in Minnesota in terms of total annual net electricity generation.

Fillmore County Solar Project generated 31.0 GWh during the 3-month period between May 2026 to August 2026.

Plant NameFillmore County Solar Project
Utility NameGeronimo Power
LocationFillmore County, MN
Initial Operation DateDecember 2024
Last Update Aug 2026
Annual Generation 81.0 GWh
Annual Consumption 310.1 k MMBtu
Ranked #3,795 out of 13,301 Power Plants Nationwide
Ranked #1,035 out of 7,209 Solar Power Plants Nationwide
Ranked #73 out of 784 Minnesota Power Plants
Ranked #7 out of 537 Minnesota Solar Power Plants
Fuel Types Solar
Previous Operator National Grid Renewables (2023 to 2024)
Geronimo Power (2025 to 2025)

Map of Fillmore County Solar Project

Full Screen Map

Register Now for Comprehensive Access

Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Fillmore County Solar Project.

Create Your Account Today

Monthly Net Generation for Fillmore County Solar Project

Monthly Plant Fuel Consumption for Fillmore County Solar Project

Fillmore County Solar Project Details

Summary Information
Plant NameFillmore County Solar Project (67168)
Plant Address14868 140th St, Spring Valley, MN 55975
UtilityGeronimo Power (62759)
Latitude, Longitude43.552, -92.357
Generation Dates on FileDec 2024 to Aug 2026
Initial Operation DateDecember 2024
Annual Generation 81.0 GWh
Fuel Types Solar
 
Federal Energy Regulatory Commission (FERC) Information
FERC Cogeneration StatusNo
FERC Small Power Producer StatusNo
FERC Exempt Wholesale Generator StatusYes
FERC Exempt Wholesale Generator Docket Number24-196-000
Regulatory Information
Regulatory StatusNon-Regulated
NERC RegionMRO
Balancing AuthorityMidcontinent Independent Transmission System Operator, Inc.. (MISO)
NAICS CodeUtilities (22)
Sector IPP Non-CHP (2)
Water Source
Ash Impoundment
Transmission / Distribution OwnerDairyland Power Coop (4716)
Grid Voltage 69.00 kV
Energy StorageNo

Generator FILCO Details Operating December 2024

TechnologySolar Photovoltaic
Prime MoverPhotovoltaic
OwnershipSingle Owner
Nameplate Capacity45 MW
Summer Capacity45 MW
Winter Capacity45 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateDecember 2024
Sector NameIPP Non-CHP (2)
Energy SourceSolar
Solar Details
Single Axis TrackingYes
Azimuth Angle180
DC Net Capacity58.5 MW
Thin Film CDTEYes
Net Metering AgreementNo
Virtual Net Metering AgreementNo

Fillmore County Solar Project Plant Owners

Owner NameAddressOwnership
We couldn't locate any owners for this plant

Power Plants with Similar Net Generation

Power plants with a similar annual net generation from Solar.

RankPlant NamePlant LocationAnnual Generation
#1025Edwards Sanborn S3Mojave, CA80.0 GWh
#1026Wolfskin SolarArnoldsville, GA84.1 GWh
#1027Sycamore SolarGretna, VA83.7 GWh
#1028BT JungmannBuckholts, TX82.6 GWh
#1029Long Branch SolarParrish, FL82.5 GWh
#1030Clover FLFort Pierce, FL82.4 GWh
#1031Gulf Coast Solar Center IINavarre, FL82.2 GWh
#1032Beacon Solar Plant Site 5Cantil, CA81.9 GWh
#1033Spectrum Solar PV Power ProjectLas Vegas, NV81.8 GWh
#1034Innovative Solar 42Fayetteville, NC81.4 GWh
#1036Five Points Solar ParkFive Points, CA80.7 GWh
#1037Virginia Line Solar, LLCManson, NC80.4 GWh
#1038Eden Solar LLCEllerbe, NC79.9 GWh
#1039Hale Kuawehi Solar HybridWaimea, HI77.8 GWh
#1040Lockhart Solar PV IV, LLCHinkley, CA78.9 GWh
#1041Bluestone SolarChase City, VA78.5 GWh
#1042Sea GrapeFt. Pierce, FL78.3 GWh
#1043Seville 2Ocotillo Wells, CA78.3 GWh
#1044SR Millington IIMillington, TN78.0 GWh
#1045OCI Alamo Solar I HybridSan Antonio, TX77.8 GWh

Nearby Power Plants

Below are closest 20 power plants surrounding Fillmore County Solar Project.

Plant NamePlant LocationAnnual GenerationDistance
Adams Wind FarmAdams, MN10.2 GWh18.4 mi
Alliant SBD 9206 DonaldsonCresco, IA6.9 MWh16.6 mi
Buffalo Center Wind LLCLittle Cedar, IA4.0 GWh23.2 mi
Crane Creek Wind Energy CenterRiceville, IA284.0 GWh12.2 mi
Douglas (IA)Riceville, IA804.0 MWh17.9 mi
FountainFountain, MN6.2 GWh17.6 mi
Grand MeadowDexter, MN378.7 GWh20.9 mi
Grand Meadow (PV)Grand Meadow, MN425.0 MWh13.3 mi
LanesboroLanesboro, MN140.0 MWh22.2 mi
Little CedarLittle Cedar, IA65.0 MWh22.2 mi
Louise SolarTaopi, MN91.3 GWh16.3 mi
Mower County Wind Energy CenterGrand Meadow, MN334.0 GWh12.8 mi
Pioneer Prairie Wind FarmMcIntire, IA841.7 GWh13.7 mi
Pleasant Valley (MN)Dexter, MN156.8 GWh23.6 mi
Prairie Star Wind FarmGrand Meadow, MN303.3 GWh16.4 mi
Preston (MN)Preston, MN78.0 MWh15.8 mi
Saratoga Wind FarmLime Springs, IA255.3 GWh8.1 mi
Spring ValleySpring Valley, MN227.4 MWh9.5 mi
Turtle Creek Wind Farm LLCSt. Ansgar, IA693.6 GWh25.6 mi
Wapsipinicon Wind ProjectDexter, MN268.1 GWh23.6 mi