Clearwater Wind III
245 Rock Spring Road East, Miles City, MT 59301Plant Summary Information
Clearwater Wind III is ranked #20 out of 71 power plants in Montana in terms of total annual net electricity generation.
Clearwater Wind III generated 101.4 GWh during the 3-month period between November 2025 to February 2026.
| Plant Name | Clearwater Wind III |
|---|---|
| Utility Name | Clearwater Wind III, LLC |
| Location | Rosebud County, MT |
| Initial Operation Date | September 2024 |
| Last Update | Feb 2026 |
| Annual Generation | 365.7 GWh |
| Annual Consumption | 1.4 M MMBtu |
| Ranked #1,730 out of 12,637 Power Plants Nationwide | |
| Ranked #506 out of 1,376 Wind Power Plants Nationwide | |
| Ranked #20 out of 71 Montana Power Plants | |
| Ranked #7 out of 23 Montana Wind Power Plants | |
| Fuel Types | Wind |
Map of Clearwater Wind III
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Clearwater Wind III.
Monthly Net Generation for Clearwater Wind III
Monthly Plant Fuel Consumption for Clearwater Wind III
Clearwater Wind III Details
| Summary Information | |
|---|---|
| Plant Name | Clearwater Wind III (66811) |
| Plant Address | 245 Rock Spring Road East, Miles City, MT 59301 |
| Utility | Clearwater Wind III, LLC (65780) |
| Latitude, Longitude | 46.81883, -106.19458 |
| Generation Dates on File | Sep 2024 to Feb 2026 |
| Initial Operation Date | September 2024 |
| Annual Generation | 365.7 GWh |
| Fuel Types | Wind |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | WECC |
| Balancing Authority | Avista Corporation (AVA) |
| NAICS Code | Utilities (22) |
| Sector | IPP Non-CHP (2) |
| Water Source | NA |
| Ash Impoundment | No |
| Transmission / Distribution Owner | NorthWestern Energy LLC - (MT) (12825) MT |
| Grid Voltage | 500.00 kV |
| Energy Storage | No |
Generator CW3 Details Operating September 2024
| Technology | Onshore Wind Turbine |
|---|---|
| Prime Mover | Wind Turbine, Onshore |
| Ownership | Single Owner |
| Nameplate Capacity | 100 MW |
| Nameplate Power Factor | 0.9 |
| Summer Capacity | 100 MW |
| Winter Capacity | 100 MW |
| Uprate/Derate Completed | No |
|---|---|
| Status | Operating |
| First Operation Date | September 2024 |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Wind |
| Turbines/Hydrokinetic Buoys | 36 |
| Turbine Details | |
| Number Of Turbines | 36 |
|---|---|
| Predominant Turbine Manufacturer | GE |
| Predominant Turbine Model Number | 2.82-127 |
| Design Wind Speed | 10.1 MPH |
| Wind Quality Class | 3 - Low Wind |
| Turbine Hub Height Feet | 374 |
Clearwater Wind III Plant Owners
| Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #496 | Hoopeston Wind LLC | Rossville, IL | 371.3 GWh |
| #497 | FPL Energy Vansycle LLC (WA) | Touchet, WA | 370.3 GWh |
| #498 | Rock Creek Wind | McFadden, WY | 369.7 GWh |
| #499 | White Rock West Wind Project | Anadarko, OK | 369.5 GWh |
| #500 | Goshen Phase II | Idaho Falls, ID | 369.2 GWh |
| #501 | Willow Creek Wind Power LLC | Newell, SD | 369.1 GWh |
| #502 | Crescent Wind Park | Hillsdale, MI | 367.9 GWh |
| #503 | New Frontier Wind | Ruso, ND | 367.6 GWh |
| #504 | Cottonwood Wind Energy Center | Blue Hill, NE | 366.6 GWh |
| #505 | Dunlap | Medicine Bow, WY | 366.5 GWh |
| #507 | Majestic 1 Wind Farm | Panhandle, TX | 365.1 GWh |
| #508 | Voyager Wind I | Mojave, CA | 364.8 GWh |
| #509 | Alta Wind Energy Center II | Mojave, CA | 364.6 GWh |
| #510 | Steele Flats Wind Project LLC | Diller, NE | 364.0 GWh |
| #511 | McAdoo Wind Energy LLC | McAdoo, TX | 363.6 GWh |
| #512 | Buckthorn Wind | Mingus, TX | 363.6 GWh |
| #513 | Oliver Wind III, LLC | Mandan, ND | 363.5 GWh |
| #514 | Alta Wind Energy Center III | Mojave, CA | 363.2 GWh |
| #515 | Stoneray Power Partners, LLC | Woodstock, MN | 362.9 GWh |
| #516 | Minco Wind III, LLC | Minco, OK | 362.5 GWh |
Nearby Power Plants
Below are closest 14 power plants surrounding Clearwater Wind III.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Clearwater Wind East | Miles City, MT | 792.3 GWh | 9.3 mi |
| Clearwater Wind I | Miles City, MT | 1.3 TWh | 8.7 mi |
| Clearwater Wind II | Miles City, MT | 389.7 GWh | 0 mi |
| Colstrip | Colstrip, MT | 8.7 TWh | 67.7 mi |
| Colstrip Energy LP | Colstrip, MT | 287.5 GWh | 62.3 mi |
| Culbertson Generation Station | Culbertson, MT | 251.2 GWh | 127.7 mi |
| Fort Peck | Fort Peck, MT | 751.6 GWh | 83.1 mi |
| Glendive GT | Glendive, MT | 2.6 GWh | 70.5 mi |
| Hardin Generator Project | Hardin, MT | 481.0 GWh | 99.4 mi |
| Miles City GT | Miles City, MT | 331.0 MWh | 33.9 mi |
| OREG 1 Inc | Culbertson, MT | 130.7 GWh | 127.8 mi |
| OREG 2 Inc | Culbertson, MT | 128.1 GWh | 127.8 mi |
| South Mills Solar, LLC | Hardin, MT | 5.0 GWh | 101.9 mi |
| Yellowtail | Hardin, MT | 798.4 GWh | 134.3 mi |