Blue Cloud Wind Energy LLC
1901 County Road 227, Sudan, TX 79371Plant Summary Information
Blue Cloud Wind Energy LLC is ranked #103 out of 231 wind farms in Texas in terms of total annual net electricity generation.
Blue Cloud Wind Energy LLC generated 133.9 GWh during the 3-month period between May 2026 to August 2026.
| Plant Name | Blue Cloud Wind Energy LLC |
|---|---|
| Utility Name | TC Energy |
| Location | Bailey County, TX |
| Initial Operation Date | December 2018 |
| Last Update | Aug 2026 |
| Annual Generation | 578.5 GWh |
| Annual Consumption | 2.1 M MMBtu |
| Ranked #1,211 out of 13,301 Power Plants Nationwide | |
| Ranked #316 out of 1,377 Wind Power Plants Nationwide | |
| Ranked #245 out of 861 Texas Power Plants | |
| Ranked #103 out of 231 Texas Wind Power Plants | |
| Fuel Types | Wind |
| Previous Operators |
Tri Global Energy, LLC (2015 to 2017) Blue Cloud Wind Energy (2018 to 2018) RWE Renewables Americas LLC (2019 to 2021) RWE Renewables Americas, LLC (2022 to 2023) TC Energy (2024 to 2025) |
Map of Blue Cloud Wind Energy LLC
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Blue Cloud Wind Energy LLC.
Monthly Net Generation for Blue Cloud Wind Energy LLC
Monthly Plant Fuel Consumption for Blue Cloud Wind Energy LLC
Blue Cloud Wind Energy LLC Details
| Summary Information | |
|---|---|
| Plant Name | Blue Cloud Wind Energy LLC (60270) |
| Plant Address | 1901 County Road 227, Sudan, TX 79371 |
| Utility | TC Energy (67080) |
| Latitude, Longitude | 34.03821, -102.66524 |
| Generation Dates on File | Dec 2018 to Aug 2026 |
| Initial Operation Date | December 2018 |
| Annual Generation | 578.5 GWh |
| Fuel Types | Wind |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | Yes |
| FERC Exempt Wholesale Generator Docket Number | 18-121 |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | MRO |
| Balancing Authority | Southwest Power Pool (SWPP) |
| NAICS Code | Utilities (22) |
| Sector | IPP Non-CHP (2) |
| Water Source | |
| Ash Impoundment | No |
| Transmission / Distribution Owner | Southwestern Public Service Co (17718) TX |
| Grid Voltage | 230.00 kV |
| Energy Storage | No |
Generator WT1 Details Operating December 2018
| Technology | Onshore Wind Turbine |
|---|---|
| Prime Mover | Wind Turbine, Onshore |
| Ownership | Wholly Owned by Other Entity |
| Nameplate Capacity | 148.4 MW |
| Summer Capacity | 148.4 MW |
| Winter Capacity | 148.4 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | December 2018 |
| Combined Heat & Power | No |
|---|---|
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Wind |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Turbines/Hydrokinetic Buoys | 43 |
| Other Planned Modifications | No |
| Multiple Fuels | No |
| Cofire Fuels | No |
| Turbine Details | |
| Number Of Turbines | 43 |
|---|---|
| Predominant Turbine Manufacturer | Vestas |
| Predominant Turbine Model Number | V126-3.45 |
| Design Wind Speed | 18 MPH |
| Wind Quality Class | 2 - Medium Wind |
| Turbine Hub Height Feet | 285 |
Blue Cloud Wind Energy LLC Plant Owners
| Owner Name | Address | Ownership |
|---|---|---|
| Blue Cloud Wind Energy LLC | 700 Louisiana Street Suite 1300, Houston, TX 77002 | 100.00% |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #306 | Pilot Hill Wind Farm | Herscher, IL | 588.6 GWh |
| #307 | Minco Wind IV, LLC | Hinton, OK | 587.9 GWh |
| #308 | Panorama Wind, LLC | Grover, CO | 587.3 GWh |
| #309 | Old Settler Wind | Floydada, TX | 585.1 GWh |
| #310 | Moraine Sands Wind Power | Mason City, IL | 583.8 GWh |
| #311 | FPL Energy Ashtabula Wind LLC | Luverne, ND | 583.0 GWh |
| #312 | Sugar Creek Wind One LLC | TBD, IL | 582.9 GWh |
| #313 | Reloj del Sol Wind Farm | San Ygnacio, TX | 582.9 GWh |
| #314 | NaturEner Rim Rock Energy | Kevin, MT | 581.4 GWh |
| #315 | FPL Energy Crystal Lake Wind LLC | Britt, IA | 579.8 GWh |
| #317 | Jumbo Hill Wind Project | Andrews, TX | 578.3 GWh |
| #318 | Headwaters Wind Farm II LLC | Losanville, IN | 578.2 GWh |
| #319 | Pattern Panhandle Wind 2 LLC | Panhandle, TX | 577.3 GWh |
| #320 | Cedar Creek II | New Raymer, CO | 577.2 GWh |
| #321 | Stella Wind Farm | Armstrong, TX | 574.6 GWh |
| #322 | Broadview Energy KW, LLC | Texico, NM | 574.6 GWh |
| #323 | Chevelon Butte Wind Farm | Winslow, AZ | 573.2 GWh |
| #324 | Bison 4 Wind Energy Center | New Salem, ND | 572.9 GWh |
| #325 | Old Trail Wind Farm | Ellsworth, IL | 569.1 GWh |
| #326 | FPL Energy Story Wind LLC | Zearing, IA | 568.7 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Blue Cloud Wind Energy LLC.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Antelope Station | Abernathy, TX | 296.6 GWh | 48.6 mi |
| BESSP1, LLC. | Shallowater, TX | 8.9 GWh | 46.3 mi |
| Bethel Wind Farm LLC | Dimmitt, TX | 1.1 TWh | 38.7 mi |
| Elk Station | Abernathy, TX | 890.9 GWh | 48.6 mi |
| GE-Lubbock | Lubbock, TX | 1.7 GWh | 46.6 mi |
| Hale Community Wind Farm | Plainview, TX | 2.1 TWh | 53.4 mi |
| Hart Wind | Hart, TX | 804.6 GWh | 42.1 mi |
| Hornet Solar (TX) | Tulia, TX | 1.6 TWh | 50.2 mi |
| Lazbuddie Wind Energy LLC | Muleshoe, TX | 87.0 GWh | 36 mi |
| Mariah del Norte | Friona, TX | 840.8 GWh | 43.8 mi |
| Milo Wind Project LLC | Portales, NM | 183.5 GWh | 40.2 mi |
| Plant X | Earth, TX | 585.8 GWh | 17 mi |
| Plant X Solar | Earth, TX | 218.4 GWh | 17.3 mi |
| Pluma - Curry Road North | Clovis, NM | 186.0 MWh | 40.1 mi |
| Roosevelt County | Portales, NM | 750.8 GWh | 49.1 mi |
| Sagamore Wind | Rogers, NM | 2.2 TWh | 30.5 mi |
| SoCore Clovis 1 | Clovis, NM | 4.6 GWh | 42.9 mi |
| Tolk | Muleshoe, TX | 2.7 TWh | 11.6 mi |
| TX Jumbo Road Wind | Hereford, TX | 568.6 GWh | 52.6 mi |
| Wildcat Ranch Wind Project | Morton, TX | 669.6 GWh | 39.1 mi |