Waste Management Bethel LFGTE

100 North Park Lane, Hampton, VA 23666

Plant Summary Information

Waste Management Bethel LFGTE is ranked #7 out of 17 landfill gas power plants in Virginia in terms of total annual net electricity generation.

Waste Management Bethel LFGTE is comprised of 6 generators and generated 8.3 GWh during the 3-month period between September 2024 to December 2024.

Plant NameWaste Management Bethel LFGTE
Utility NameWM Renewable Energy LLC
LocationHampton city, VA
Initial Operation DateFebruary 2008
Last Update Dec 2024
Annual Generation 36.5 GWh
Annual Consumption 472.4 k MMBtu
Ranked #4,394 out of 12,288 Power Plants Nationwide
Ranked #64 out of 292 Landfill Gas Power Plants Nationwide
Ranked #108 out of 227 Virginia Power Plants
Ranked #7 out of 17 Virginia Landfill Gas Power Plants
Fuel Types Landfill Gas

Map of Waste Management Bethel LFGTE

Full Screen Map
Use Ctrl + scroll to zoom the map
Use two fingers to move the map

Register Now for Comprehensive Access

Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Waste Management Bethel LFGTE.

Create Your Account Today

Monthly Net Generation for Waste Management Bethel LFGTE

5k5k4k4k3k3k2k2k900900002008200820092009201020102011201120122012201320132014201420152015201620162017201720182018201920192020202020212021202220222023202320242024
Download SVG
Download PNG
Download CSV

Waste Management Bethel LFGTE Details

Summary Information
Plant NameWaste Management Bethel LFGTE (56531)
Plant Address100 North Park Lane, Hampton, VA 23666
UtilityWM Renewable Energy LLC (54842)
Latitude, Longitude37.07635, -76.44437
Generation Dates on FileFeb 2008 to Dec 2024
Initial Operation DateFebruary 2008
Annual Generation 36.5 GWh
Fuel Types Landfill Gas
 
Federal Energy Regulatory Commission (FERC) Information
FERC Cogeneration StatusNo
FERC Small Power Producer StatusYes
FERC Small Power Producer Docket Number07-71
FERC Exempt Wholesale Generator StatusNo
Regulatory Information
Regulatory StatusNon-Regulated
NERC RegionSERC
Balancing AuthorityPJM Interconnection, LLC (PJM)
NAICS CodeUtilities (22)
Sector IPP Non-CHP (2)
Water Source
Ash Impoundment No
Transmission / Distribution OwnerVirginia Electric & Power Co (19876) VA
Grid Voltage 35.00 kV
Energy StorageNo

Generator GEN1 Details Operating February 2008

TechnologyLandfill Gas
Prime MoverInternal Combustion Engine
OwnershipSingle Owner
RTO ISO LMP Node Designation53049067
RTO ISO Location Designation For Reporting Wholesale Sales Data53049067
Nameplate Capacity0.8 MW
Nameplate Power Factor0.98
Summer Capacity0.8 MW
Winter Capacity0.8 MW
Minimum Load0.5 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateFebruary 2008
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceLandfill Gas
Time From Cold Shutdown To Full Load1H
Multiple FuelsNo
Cofire FuelsNo
Switch Between Oil And Natural GasNo

Generator GEN2 Details Operating February 2008

TechnologyLandfill Gas
Prime MoverInternal Combustion Engine
OwnershipSingle Owner
RTO ISO LMP Node Designation53049067
RTO ISO Location Designation For Reporting Wholesale Sales Data53049067
Nameplate Capacity0.8 MW
Nameplate Power Factor0.98
Summer Capacity0.8 MW
Winter Capacity0.8 MW
Minimum Load0.5 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateFebruary 2008
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceLandfill Gas
Time From Cold Shutdown To Full Load1H
Multiple FuelsNo
Cofire FuelsNo
Switch Between Oil And Natural GasNo

Generator GEN3 Details Operating February 2008

TechnologyLandfill Gas
Prime MoverInternal Combustion Engine
OwnershipSingle Owner
RTO ISO LMP Node Designation53049067
RTO ISO Location Designation For Reporting Wholesale Sales Data53049067
Nameplate Capacity0.8 MW
Nameplate Power Factor0.98
Summer Capacity0.8 MW
Winter Capacity0.8 MW
Minimum Load0.5 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateFebruary 2008
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceLandfill Gas
Time From Cold Shutdown To Full Load1H
Multiple FuelsNo
Cofire FuelsNo
Switch Between Oil And Natural GasNo

Generator GEN4 Details Operating February 2008

TechnologyLandfill Gas
Prime MoverInternal Combustion Engine
OwnershipSingle Owner
RTO ISO LMP Node Designation53049067
RTO ISO Location Designation For Reporting Wholesale Sales Data53049067
Nameplate Capacity0.8 MW
Nameplate Power Factor0.98
Summer Capacity0.8 MW
Winter Capacity0.8 MW
Minimum Load0.5 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateFebruary 2008
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceLandfill Gas
Time From Cold Shutdown To Full Load1H
Multiple FuelsNo
Cofire FuelsNo
Switch Between Oil And Natural GasNo

Generator GEN5 Details Operating February 2008

TechnologyLandfill Gas
Prime MoverInternal Combustion Engine
OwnershipSingle Owner
RTO ISO LMP Node Designation53049067
RTO ISO Location Designation For Reporting Wholesale Sales Data53049067
Nameplate Capacity0.8 MW
Nameplate Power Factor0.98
Summer Capacity0.8 MW
Winter Capacity0.8 MW
Minimum Load0.5 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateFebruary 2008
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceLandfill Gas
Time From Cold Shutdown To Full Load1H
Multiple FuelsNo
Cofire FuelsNo
Switch Between Oil And Natural GasNo

Generator GEN6 Details Operating February 2008

TechnologyLandfill Gas
Prime MoverInternal Combustion Engine
OwnershipSingle Owner
RTO ISO LMP Node Designation53049067
RTO ISO Location Designation For Reporting Wholesale Sales Data53049067
Nameplate Capacity0.8 MW
Nameplate Power Factor0.98
Summer Capacity0.8 MW
Winter Capacity0.8 MW
Minimum Load0.5 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateFebruary 2008
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceLandfill Gas
Time From Cold Shutdown To Full Load1H
Multiple FuelsNo
Cofire FuelsNo
Switch Between Oil And Natural GasNo

Waste Management Bethel LFGTE Plant Owners

Owner NameAddressGeneratorOwnership
We couldn't locate any owners for this plant

Power Plants with Similar Net Generation

Power plants with a similar annual net generation from Landfill Gas.

RankPlant NamePlant LocationAnnual Generation
#54Coffin ButteCorvallis, OR38.4 GWh
#55West CamdenCamden, TN38.1 GWh
#56Lakeview Gas RecoveryErie, PA37.7 GWh
#57BrevardCocoa, FL37.2 GWh
#58UNH 7.9 MW PlantDurham, NH49.5 GWh
#59Georgia LFG Pine Ridge PlantGriffin, GA37.1 GWh
#60Deertrack Park Gas RecoveryWatertown, WI37.0 GWh
#61Metro Gas RecoveryFranklin, WI37.0 GWh
#62CoopersvilleCoopersville, MI36.9 GWh
#63Trans-Jordan Generating StationSouth Jordan, UT36.5 GWh
#65Calabasas Gas to Energy FacilityAgoura, CA36.3 GWh
#66RidgeviewWhitelaw, WI35.6 GWh
#67Springhill Gas Recovery PlantCampbellton, FL35.3 GWh
#68Zimmerman EnergyArgos, IN34.7 GWh
#69Richmond EnergyHenrico, VA33.4 GWh
#70TaylorMauk, GA33.4 GWh
#71Hyland LFGTE FacilityAngelica, NY33.3 GWh
#72Fitchburg Gas RecoveryWestminster, MA32.3 GWh
#73Modern Innovative Energy LLCYoungstown, NY32.3 GWh
#74Ameresco Vasco RoadLivermore, CA32.3 GWh

Nearby Power Plants

Below are closest 20 power plants surrounding Waste Management Bethel LFGTE.

Plant NamePlant LocationAnnual GenerationDistance
Cavalier SolarSmithfield, VA253.8 GWh16.6 mi
Cavalier Solar A2Smithfield, VA41.8 GWh16.6 mi
ChesapeakeChesapeake, VA186.0 MWh22.5 mi
Colonial Trail WestSpring Grove, VA278.8 GWh25.6 mi
Elizabeth River Power StationChesapeake, VA109.2 GWh22.1 mi
Gloucester SolarGloucester, VA37.9 GWh25.8 mi
Gravel NeckSurry, VA115.4 GWh14.7 mi
IKEA Norfolk Rooftop PV SystemNorfolk, VA1.4 GWh19.3 mi
Norge Solar FarmWilliamsburg, VA38.8 GWh27 mi
Pleasant Hill SolarSuffolk, VA40.2 GWh27.6 mi
Rochambeau SolarWilliamsburg, VA37.6 GWh25.7 mi
Solidago SolarWindsor, VA38.3 GWh19.5 mi
Spring Grove ISpring Grove, VA161.2 GWh27 mi
SurrySurry, VA12.9 TWh15.3 mi
TWE Myrtle Solar Farm, LLCSuffolk, VA24.7 GWh23.4 mi
Virginia BeachVirginia Beach, VA3.2 GWh24.1 mi
Western Branch High SchoolChesapeake, VA979.0 MWh15.9 mi
Wheelabrator PortsmouthPortsmouth, VA35.6 GWh20.1 mi
Winterberry SolarGloucester, VA41.1 GWh20.2 mi
Woodland Solar FarmSmithfield, VA32.2 GWh15.8 mi