Trans-Jordan Generating Station
10873 S Highway 111, South Jordan, UT 84095Plant Summary Information
Trans-Jordan Generating Station is ranked #1 out of 3 landfill gas power plants in Utah in terms of total annual net electricity generation.
Trans-Jordan Generating Station is comprised of 3 generators and generated 9.1 GWh during the 3-month period between September 2024 to December 2024.
Plant Name | Trans-Jordan Generating Station |
---|---|
Utility Name | Energy Developments, Inc d/b/a EDL |
Location | Salt Lake County, UT |
Initial Operation Date | March 2009 |
Last Update | Dec 2024 |
Annual Generation | 36.5 GWh |
Annual Consumption | 468.3 k MMBtu |
Ranked #4,414 out of 12,299 Power Plants Nationwide | |
Ranked #63 out of 292 Landfill Gas Power Plants Nationwide | |
Ranked #55 out of 120 Utah Power Plants | |
Ranked #1 out of 3 Utah Landfill Gas Power Plants | |
Fuel Types | Landfill Gas |
Previous Operators |
Granger Electric Co (2013 to 2016) Energy Developments, Inc II (2017 to 2017) EDL Inc (2018 to 2023) Energy Developments, Inc d/b/a EDL (2024 to 2024) |
Map of Trans-Jordan Generating Station
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Trans-Jordan Generating Station.
Monthly Net Generation for Trans-Jordan Generating Station
Trans-Jordan Generating Station Details
Summary Information | |
---|---|
Plant Name | Trans-Jordan Generating Station (56853) |
Plant Address | 10873 S Highway 111, South Jordan, UT 84095 |
Utility | Energy Developments, Inc d/b/a EDL (55858) |
Latitude, Longitude | 40.55, -112.0631 |
Generation Dates on File | Mar 2009 to Dec 2024 |
Initial Operation Date | March 2009 |
Annual Generation | 36.5 GWh |
Fuel Types | Landfill Gas |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | WECC |
Balancing Authority | PacifiCorp - East (PACE) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | No |
Transmission / Distribution Owner | PacifiCorp (14354) UT |
Grid Voltage | 46.00 kV |
Energy Storage | No |
Generator 1 Details Operating March 2009
Technology | Landfill Gas |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
Nameplate Capacity | 1.6 MW |
Nameplate Power Factor | 1 |
Summer Capacity | 1.5 MW |
Winter Capacity | 1.5 MW |
Minimum Load | 1.2 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | March 2009 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Landfill Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Generator 2 Details Operating March 2009
Technology | Landfill Gas |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
Nameplate Capacity | 1.6 MW |
Nameplate Power Factor | 1 |
Summer Capacity | 1.5 MW |
Winter Capacity | 1.5 MW |
Minimum Load | 1.2 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | March 2009 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Landfill Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Generator 3 Details Operating March 2009
Technology | Landfill Gas |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
Nameplate Capacity | 1.6 MW |
Nameplate Power Factor | 1 |
Summer Capacity | 1.5 MW |
Winter Capacity | 1.5 MW |
Minimum Load | 1.2 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | March 2009 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Landfill Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Trans-Jordan Generating Station Plant Owners
Owner Name | Address | Generator | Ownership |
---|---|---|---|
We couldn't locate any owners for this plant |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Landfill Gas.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#53 | Waste Management Arden LFGTE | Washington, PA | 38.5 GWh |
#54 | Coffin Butte | Corvallis, OR | 38.4 GWh |
#55 | West Camden | Camden, TN | 38.1 GWh |
#56 | Lakeview Gas Recovery | Erie, PA | 37.7 GWh |
#57 | UNH 7.9 MW Plant | Durham, NH | 50.2 GWh |
#58 | Brevard | Cocoa, FL | 37.2 GWh |
#59 | Georgia LFG Pine Ridge Plant | Griffin, GA | 37.1 GWh |
#60 | Deertrack Park Gas Recovery | Watertown, WI | 37.0 GWh |
#61 | Metro Gas Recovery | Franklin, WI | 37.0 GWh |
#62 | Coopersville | Coopersville, MI | 36.9 GWh |
#64 | Waste Management Bethel LFGTE | Hampton, VA | 36.5 GWh |
#65 | Calabasas Gas to Energy Facility | Agoura, CA | 36.3 GWh |
#66 | Ridgeview | Whitelaw, WI | 35.6 GWh |
#67 | Springhill Gas Recovery Plant | Campbellton, FL | 35.3 GWh |
#68 | Zimmerman Energy | Argos, IN | 34.8 GWh |
#69 | Richmond Energy | Henrico, VA | 33.4 GWh |
#70 | Taylor | Mauk, GA | 33.4 GWh |
#71 | Hyland LFGTE Facility | Angelica, NY | 33.3 GWh |
#72 | Fitchburg Gas Recovery | Westminster, MA | 32.3 GWh |
#73 | Modern Innovative Energy LLC | Youngstown, NY | 32.3 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Trans-Jordan Generating Station.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Bountiful City | Bountiful, UT | 28.4 GWh | 25.1 mi |
BYU Central Heating Plant | Provo, UT | 115.6 GWh | 30.3 mi |
Copperton Solar Plant No. 1 | Bingham Canyon, UT | 648.0 MWh | 2.2 mi |
Deer Creek (UT) | Heber, UT | 23.3 GWh | 29.8 mi |
Gadsby | Salt Lake City, UT | 320.0 GWh | 16.7 mi |
Granite | Salt lake City, UT | 5.2 GWh | 15.5 mi |
Heber City | Heber City, UT | 27.6 GWh | 33.7 mi |
HTW Plant 303 COGEN | Salt Lake City, UT | 44.9 GWh | 18.7 mi |
Kennecott Power Plant | Magna, UT | 170.2 GWh | 11.6 mi |
Lake Side Power Plant | Vineyard, UT | 5.9 TWh | 22.2 mi |
Little Cottonwood | Sandy, UT | 10.3 GWh | 14 mi |
Murray Turbine | Murray, UT | 37.3 GWh | 12.3 mi |
Provo Power Plant | Provo, UT | 4.9 GWh | 29.9 mi |
Salt Lake Energy Systems | Salt Lake City, UT | 24.3 GWh | 13.6 mi |
Salt Palace Solar Gen Plant | Salt Lake City, UT | 2.0 GWh | 17.4 mi |
Snake Creek | Midway, UT | 5.6 GWh | 29.4 mi |
Snowbird Power Plant | Snowbird, UT | 14.7 GWh | 21.6 mi |
Stairs | Salt Lake City, UT | 3.2 GWh | 17 mi |
Tesoro SLC Cogeneration Plant | Salt Lake City, UT | 188.4 GWh | 18.8 mi |
West Valley Generation Project | West Valley City, UT | 589.0 GWh | 8.2 mi |