Trans-Jordan Generating Station
10873 S Highway 111, South Jordan, UT 84095Plant Summary Information
Trans-Jordan Generating Station is ranked #1 out of 3 landfill gas power plants in Utah in terms of total annual net electricity generation.
Trans-Jordan Generating Station is comprised of 3 generators and generated 8.9 GWh during the 3-month period between September 2025 to December 2025.
| Plant Name | Trans-Jordan Generating Station |
|---|---|
| Utility Name | Energy Developments, Inc d/b/a EDL |
| Location | Salt Lake County, UT |
| Initial Operation Date | March 2009 |
| Last Update | Dec 2025 |
| Annual Generation | 35.2 GWh |
| Annual Consumption | 448.8 k MMBtu |
| Ranked #4,639 out of 13,081 Power Plants Nationwide | |
| Ranked #56 out of 281 Landfill Gas Power Plants Nationwide | |
| Ranked #56 out of 120 Utah Power Plants | |
| Ranked #1 out of 3 Utah Landfill Gas Power Plants | |
| Fuel Types | Landfill Gas |
| Previous Operators |
Granger Electric Co (2013 to 2016) Energy Developments, Inc II (2017 to 2017) EDL Inc (2018 to 2023) Energy Developments, Inc d/b/a EDL (2024 to 2025) |
Map of Trans-Jordan Generating Station
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Trans-Jordan Generating Station.
Monthly Net Generation for Trans-Jordan Generating Station
Monthly Plant Fuel Consumption for Trans-Jordan Generating Station
Trans-Jordan Generating Station Details
| Summary Information | |
|---|---|
| Plant Name | Trans-Jordan Generating Station (56853) |
| Plant Address | 10873 S Highway 111, South Jordan, UT 84095 |
| Utility | Energy Developments, Inc d/b/a EDL (55858) |
| Latitude, Longitude | 40.55, -112.0631 |
| Generation Dates on File | Mar 2009 to Dec 2025 |
| Initial Operation Date | March 2009 |
| Annual Generation | 35.2 GWh |
| Fuel Types | Landfill Gas |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | WECC |
| Balancing Authority | PacifiCorp - East (PACE) |
| NAICS Code | Utilities (22) |
| Sector | IPP Non-CHP (2) |
| Water Source | |
| Ash Impoundment | No |
| Transmission / Distribution Owner | PacifiCorp (14354) UT |
| Grid Voltage | 46.00 kV |
| Energy Storage | No |
Generator 1 Details Operating March 2009
| Technology | Landfill Gas |
|---|---|
| Prime Mover | Internal Combustion Engine |
| Ownership | Single Owner |
| Nameplate Capacity | 1.6 MW |
| Nameplate Power Factor | 1 |
| Summer Capacity | 1.5 MW |
| Winter Capacity | 1.5 MW |
| Minimum Load | 1.2 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | March 2009 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Landfill Gas |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | No |
Generator 2 Details Operating March 2009
| Technology | Landfill Gas |
|---|---|
| Prime Mover | Internal Combustion Engine |
| Ownership | Single Owner |
| Nameplate Capacity | 1.6 MW |
| Nameplate Power Factor | 1 |
| Summer Capacity | 1.5 MW |
| Winter Capacity | 1.5 MW |
| Minimum Load | 1.2 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | March 2009 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Landfill Gas |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | No |
Generator 3 Details Operating March 2009
| Technology | Landfill Gas |
|---|---|
| Prime Mover | Internal Combustion Engine |
| Ownership | Single Owner |
| Nameplate Capacity | 1.6 MW |
| Nameplate Power Factor | 1 |
| Summer Capacity | 1.5 MW |
| Winter Capacity | 1.5 MW |
| Minimum Load | 1.2 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | March 2009 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Landfill Gas |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | No |
Trans-Jordan Generating Station Plant Owners
| Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Landfill Gas.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #46 | Turnkey Landfill Gas Recovery | Rochester, NH | 38.5 GWh |
| #47 | Pioneer Crossing Energy, LLC | Birdsboro, PA | 38.0 GWh |
| #48 | Charles City | Providence Forge, VA | 40.4 GWh |
| #49 | Coopersville | Coopersville, MI | 37.9 GWh |
| #50 | Chaffee Gas Recovery | Chaffee, NY | 37.4 GWh |
| #51 | Waste Management Bethel LFGTE | Hampton, VA | 37.3 GWh |
| #52 | Ridgeview | Whitelaw, WI | 37.3 GWh |
| #53 | JED Solid Waste Mgmt Renewable Energy | St. Cloud, FL | 37.1 GWh |
| #54 | Waste Management Arden LFGTE | Washington, PA | 36.4 GWh |
| #55 | MM San Diego-Miramar | San Diego, CA | 39.6 GWh |
| #57 | Sarasota County LFGTE Facility | Nokomis, FL | 35.0 GWh |
| #58 | Kiefer Landfill | Sloughhouse, CA | 34.6 GWh |
| #59 | Chestnut Ridge Gas Recovery | Heiskell, TN | 34.0 GWh |
| #60 | West Camden | Camden, TN | 33.6 GWh |
| #61 | LRI LFGTE Facility | Graham, WA | 33.2 GWh |
| #62 | Suburban Landfill Gas Recovery | Glenford, OH | 32.9 GWh |
| #63 | Seneca Energy | Seneca Falls, NY | 32.9 GWh |
| #64 | Hyland LFGTE Facility | Angelica, NY | 32.8 GWh |
| #65 | Ameresco Vasco Road | Livermore, CA | 32.7 GWh |
| #66 | Modern Innovative Energy LLC | Youngstown, NY | 32.7 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Trans-Jordan Generating Station.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Bountiful City | Bountiful, UT | 31.3 GWh | 25.1 mi |
| BYU Central Heating Plant | Provo, UT | 115.9 GWh | 30.3 mi |
| Copperton Solar Plant No. 1 | Bingham Canyon, UT | 7.3 GWh | 2.2 mi |
| Deer Creek (UT) | Heber, UT | 22.2 GWh | 29.8 mi |
| Faraday Solar | Fairfield, UT | 1.0 TWh | 31.6 mi |
| Gadsby | Salt Lake City, UT | 191.3 GWh | 16.7 mi |
| Granite | Salt lake City, UT | 4.2 GWh | 15.5 mi |
| HTW Plant 303 COGEN | Salt Lake City, UT | 48.2 GWh | 18.7 mi |
| Kennecott Power Plant | Magna, UT | 135.6 GWh | 11.6 mi |
| Lake Side Power Plant | Vineyard, UT | 6.3 TWh | 22.2 mi |
| Little Cottonwood | Sandy, UT | 8.6 GWh | 14 mi |
| Murray Turbine | Murray, UT | 220.0 MWh | 12.3 mi |
| Provo Power Plant | Provo, UT | 4.4 GWh | 29.9 mi |
| Salt Lake Energy Systems | Salt Lake City, UT | 12.7 GWh | 13.6 mi |
| Salt Palace Solar Gen Plant | Salt Lake City, UT | 1.1 GWh | 17.4 mi |
| Snake Creek | Midway, UT | 3.8 GWh | 29.4 mi |
| Snowbird Power Plant | Snowbird, UT | 14.6 GWh | 21.6 mi |
| Stairs | Salt Lake City, UT | 4.1 GWh | 17 mi |
| Tesoro SLC Cogeneration Plant | Salt Lake City, UT | 199.9 GWh | 18.8 mi |
| West Valley Generation Project | West Valley City, UT | 383.2 GWh | 8.2 mi |