UC Merced Solar Hybrid
5200 Lake Rd, Merced, CA 92350Plant Summary Information
UC Merced Solar Hybrid is ranked #379 out of 849 solar farms in California in terms of total annual net electricity generation.
UC Merced Solar Hybrid generated 1.1 GWh during the 3-month period between September 2024 to December 2024.
| Plant Name | UC Merced Solar Hybrid |
|---|---|
| Utility Name | MN8 Energy LLC |
| Location | Merced County, CA |
| Initial Operation Date | December 2018 |
| Last Update | Dec 2024 |
| Annual Generation | 6.5 GWh |
| Annual Consumption | 23.5 k MMBtu |
| Ranked #7,415 out of 12,539 Power Plants Nationwide | |
| Ranked #2,747 out of 6,400 Solar Power Plants Nationwide | |
| Ranked #1,008 out of 1,600 California Power Plants | |
| Ranked #379 out of 849 California Solar Power Plants | |
| Fuel Types | Solar |
| Previous Operators |
Solar University, LLC (2018 to 2019) Goldman Sachs Renewable Power Group (2020 to 2020) Goldman Sachs Renewable Power LLC (2021 to 2021) MN8 Energy LLC (2022 to 2024) |
Map of UC Merced Solar Hybrid
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for UC Merced Solar Hybrid.
Monthly Net Generation for UC Merced Solar Hybrid
UC Merced Solar Hybrid Details
| Summary Information | |
|---|---|
| Plant Name | UC Merced Solar Hybrid (61995) |
| Plant Address | 5200 Lake Rd, Merced, CA 92350 |
| Utility | MN8 Energy LLC (61944) |
| Latitude, Longitude | 37.36569, -120.43223 |
| Generation Dates on File | Dec 2018 to Dec 2024 |
| Initial Operation Date | December 2018 |
| Annual Generation | 6.5 GWh |
| Fuel Types | Solar |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | Yes |
| FERC Small Power Producer Docket Number | 19-592 |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | WECC |
| Balancing Authority | California Independent System Operator (CISO) |
| NAICS Code | Utilities (22) |
| Sector | IPP Non-CHP (2) |
| Water Source | |
| Ash Impoundment | |
| Transmission / Distribution Owner | Pacific Gas & Electric Co. (14328) CA |
| Grid Voltage | 15.00 kV / 12.47 kV / 0.48 kV |
| Energy Storage | Yes |
Generator UCMBA Details Operating December 2018
| Technology | Batteries |
|---|---|
| Prime Mover | Battery |
| Ownership | Single Owner |
| Nameplate Capacity | 0.5 MW |
| Summer Capacity | 0.5 MW |
| Winter Capacity | 0.5 MW |
| Minimum Load | 0.5 MW |
| Uprate/Derate Completed | No |
|---|---|
| Status | Operating |
| First Operation Date | December 2018 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Electricity used for energy storage |
| Time From Cold Shutdown To Full Load | 10M |
| Energy Storage Details | |
| Nameplate Energy Capacity MWH | 0.9 |
|---|---|
| Maximum Charge Rate | 0.5 MW |
| Maximum Discharge Rate | 0.5 MW |
| Storage Technology | LIB |
| Nameplate Reactive Power Rating | 0.5 |
| Storage Enclosure Type | CS |
| System Peak Shaving | Yes |
| Excess Wind And Solar Generation | P |
| Ac Coupled | Yes |
| Direct Support Of Another Unit | Yes |
| Direct Support Plant Id | 61995 |
| Direct Support Gen Id | UCMPV |
| Support T D Asset | No |
Generator UCMPV Details Operating December 2018
| Technology | Solar Photovoltaic |
|---|---|
| Prime Mover | Photovoltaic |
| Ownership | Single Owner |
| Nameplate Capacity | 4.5 MW |
| Summer Capacity | 4.3 MW |
| Winter Capacity | 1.8 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | December 2018 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Solar |
| Multiple Fuels | No |
| Solar Details | |
| Fixed Tilt | Yes |
|---|---|
| Azimuth Angle | 48 |
| Tilt Angle | 10 |
| DC Net Capacity | 5.4 MW |
| Crystalline Silicon | Yes |
| Net Metering Agreement | Yes |
| Net Metering DC Capacity | 4.3 MW |
| Virtual Net Metering Agreement | No |
UC Merced Solar Hybrid Plant Owners
| Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #2737 | Quichapa 1 | Cedar City, UT | 6.6 GWh |
| #2738 | Highway 56 Solar | Sherman, TX | 6.6 GWh |
| #2739 | Watervliet PV | Watervliet, MI | 6.6 GWh |
| #2740 | Tift Fletcher | Tifton, GA | 6.6 GWh |
| #2741 | Aloha Solar Energy Fund 1 PK1 | Waianae, HI | 6.6 GWh |
| #2742 | State Route 5 | Vernon, NY | 6.6 GWh |
| #2743 | Currin Solar, LLC | Oxford, NC | 6.6 GWh |
| #2744 | Bluewater CDEC 1 | Bluewater, NM | 6.6 GWh |
| #2745 | Kearsarge Westerly | Westerly, RI | 6.6 GWh |
| #2746 | Greene Durham | Union Point, GA | 6.6 GWh |
| #2748 | Outback Solar At Christmas Valley | Christmas Valley, OR | 6.6 GWh |
| #2749 | Brattleboro (Windham Landfill) | Brattleboro, VT | 6.6 GWh |
| #2750 | Farmersville | Farmersville, CA | 6.5 GWh |
| #2751 | Phoenix Solar South Farms LLC Solar Farm | Champaign, IL | 6.5 GWh |
| #2752 | Upson County GA S1 LLC | Thomaston, GA | 6.5 GWh |
| #2753 | ASA DeKalb NY Solar I LLC | DeKalb, NY | 6.5 GWh |
| #2754 | Polk County GA S1, LLC | Cedartown, GA | 6.5 GWh |
| #2755 | Canal Road Solar | Franklin, NJ | 6.5 GWh |
| #2756 | Chisago Community Solar | Taylor Falls, MN | 6.5 GWh |
| #2757 | Mantisi | Brockport, NY | 6.5 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding UC Merced Solar Hybrid.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| 2097 Helton Solar Project | Merced, CA | 1.6 GWh | 4.2 mi |
| Adera Solar | Chowchilla, CA | 17.3 GWh | 17.9 mi |
| Avenue 26 Solar | Chowchilla, CA | 4.5 GWh | 21.7 mi |
| Broadway 3 - UC Merced 1 | Merced, CA | 901.0 MWh | 0.1 mi |
| Chowchilla II | Chowchilla, CA | 16.5 GWh | 20.5 mi |
| DGS Valley State Prison | Chowchilla, CA | 3.9 GWh | 23.9 mi |
| Diamond H Dairy Power | Chowchilla, CA | 11.9 GWh | 24.4 mi |
| Don Pedro | La Grange, CA | 277.5 GWh | 22.8 mi |
| Exchequer | Snelling, CA | 267.9 GWh | 17.6 mi |
| Five H Farms Solar Array | Merced, CA | 1.3 GWh | 18.6 mi |
| Henry Miller RD | Dos Palos, CA | 3.2 GWh | 24.2 mi |
| La Grange | La Grange, CA | 4.4 GWh | 21 mi |
| McSwain | Snelling, CA | 31.8 GWh | 12.7 mi |
| Merced Falls | Snelling, CA | 9.4 GWh | 12.2 mi |
| Merced Solar LLC | Merced, CA | 3.8 GWh | 7.3 mi |
| Mission Solar LLC | Merced, CA | 3.8 GWh | 7.3 mi |
| Parker | Snelling, CA | 5.5 GWh | 7.8 mi |
| Turlock Lake | Hickman, CA | 7.0 GWh | 19.2 mi |
| Upper Dawson | La Grange, CA | 10.7 GWh | 19.8 mi |
| West Tambo Clean Power II | Livingston, CA | 877.0 MWh | 15.8 mi |