Sunray Wind I
6701 FM119, Sunray, TX 79086Plant Summary Information
Sunray Wind I is ranked #203 out of 227 wind farms in Texas in terms of total annual net electricity generation.
Sunray Wind I generated 39.1 GWh during the 3-month period between September 2024 to December 2024.
| Plant Name | Sunray Wind I |
|---|---|
| Utility Name | Diamond Shamrock Refining Company LP |
| Location | Moore County, TX |
| Initial Operation Date | September 2009 |
| Last Update | Dec 2024 |
| Annual Generation | 129.7 GWh |
| Annual Consumption | 442.6 k MMBtu |
| Ranked #3,124 out of 12,613 Power Plants Nationwide | |
| Ranked #855 out of 1,374 Wind Power Plants Nationwide | |
| Ranked #479 out of 816 Texas Power Plants | |
| Ranked #203 out of 227 Texas Wind Power Plants | |
| Fuel Types | Wind |
Map of Sunray Wind I
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Sunray Wind I.
Monthly Net Generation for Sunray Wind I
Monthly Plant Fuel Consumption for Sunray Wind I
Sunray Wind I Details
| Summary Information | |
|---|---|
| Plant Name | Sunray Wind I (57326) |
| Plant Address | 6701 FM119, Sunray, TX 79086 |
| Utility | Diamond Shamrock Refining Company LP (56680) |
| Latitude, Longitude | 35.9454, -101.9005 |
| Generation Dates on File | Jan 2010 to Dec 2024 |
| Initial Operation Date | September 2009 |
| Annual Generation | 129.7 GWh |
| Fuel Types | Wind |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | TRE |
| Balancing Authority | Southwest Power Pool (SWPP) |
| NAICS Code | Utilities (22) |
| Sector | IPP Non-CHP (2) |
| Water Source | N/A |
| Ash Impoundment | No |
| Transmission / Distribution Owner | Southwestern Public Service Co (17718) TX |
| Grid Voltage | 12.47 kV |
| Energy Storage | No |
Generator WND1 Details Operating September 2009
| Technology | Onshore Wind Turbine |
|---|---|
| Prime Mover | Wind Turbine, Onshore |
| Ownership | Single Owner |
| Nameplate Capacity | 49.5 MW |
| Nameplate Power Factor | 1 |
| Summer Capacity | 49.5 MW |
| Winter Capacity | 49.5 MW |
| Minimum Load | 3 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | September 2009 |
|---|---|
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Wind |
| Solid Fuel Gasification | No |
| Turbines/Hydrokinetic Buoys | 33 |
| Supercritical Technology | No |
| Ultrasupercritical Technology | No |
| Multiple Fuels | No |
| Turbine Details | |
| Number Of Turbines | 33 |
|---|---|
| Predominant Turbine Manufacturer | GE |
| Predominant Turbine Model Number | 1.5 SLE |
| Design Wind Speed | 16.5 MPH |
| Wind Quality Class | 2 - Medium Wind |
| Turbine Hub Height Feet | 270 |
Sunray Wind I Plant Owners
| Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #845 | Palmer's Creek Wind Farm, LLC | Granite Falls, MN | 135.3 GWh |
| #846 | Forward Wind Energy Center | Brownsville, WI | 134.6 GWh |
| #847 | Panther Creek Wind Project | Pittsfield, IL | 134.2 GWh |
| #848 | Spearville | Ford, KS | 133.6 GWh |
| #849 | Voyager Wind III | Mojave, CA | 133.4 GWh |
| #850 | Mojave 3/4/5 | Mojave, CA | 132.8 GWh |
| #851 | Community Wind South | Rushmore, MN | 132.3 GWh |
| #852 | Stony Creek Wind Farm LLC | Berlin, PA | 132.0 GWh |
| #853 | Macho Springs Power I | Deming, NM | 130.2 GWh |
| #854 | Northern Iowa Windpower II | Kensett, IA | 130.2 GWh |
| #856 | Whitewater Hill Wind Partners | North Palm Springs, CA | 128.3 GWh |
| #857 | Beech Ridge II Wind Energy Center | Rupert, WV | 127.3 GWh |
| #858 | Kumeyaay Wind | Campo, CA | 127.2 GWh |
| #859 | Beebe 1B | Ithaca, MI | 127.0 GWh |
| #860 | Willow Creek Wind (OK) | Morrison, OK | 126.8 GWh |
| #861 | Stoney Corners Wind Farm | McBain, MI | 126.7 GWh |
| #862 | Cambria Wind LLC | Sidman, PA | 126.1 GWh |
| #863 | San Gorgonio Westwinds II LLC | North Palm Springs, CA | 124.4 GWh |
| #864 | Mesa Wind Power LLC | North Palm Springs, CA | 122.8 GWh |
| #865 | Laurel Hill Wind | Roaring Branch, PA | 122.7 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Sunray Wind I.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Black Hawk Station | Borger, TX | 1.4 TWh | 34.9 mi |
| Borger Plant | Borger, TX | 46.6 GWh | 32.5 mi |
| Brisket Wind (8) LLC | Sunray, TX | 5.9 GWh | 4.8 mi |
| Engineered Carbons Borger Cogen | Borger, TX | 80.2 GWh | 32.5 mi |
| Filet Wind (5) LLC | Stratford, TX | 3.3 GWh | 34.6 mi |
| Flat Iron Wind (7) LLC | Sunray, TX | 4.9 GWh | 5.6 mi |
| Goodwell Wind Project LLC | Goodwell, OK | 701.0 GWh | 45.2 mi |
| Great Plains Windpark LLC | Spearman, TX | 107.1 GWh | 47.5 mi |
| Great Prairie Wind | Gruver, TX | 4.1 TWh | 32.4 mi |
| Harrington | Amarillo, TX | 2.0 TWh | 45.5 mi |
| Majestic 1 Wind Farm | Panhandle, TX | 365.1 GWh | 43.5 mi |
| Majestic II Wind | Panhandle, TX | 157.4 GWh | 42.7 mi |
| Nichols | Amarillo, TX | 1.7 TWh | 46.6 mi |
| Pantex | Amarillo, TX | 15.7 GWh | 47.7 mi |
| Pattern Panhandle Wind 2 LLC | Panhandle, TX | 614.0 GWh | 45.6 mi |
| Porterhouse Wind (4) LLC | Gruver, TX | 8.7 GWh | 43.3 mi |
| Ribeye Wind (11) LLC | Dumas, TX | 5.9 GWh | 10.2 mi |
| T-Bone Wind (10) LLC | Dumas, TX | 5.3 GWh | 11 mi |
| Tenderloin Wind (6) LLC | Texhoma, TX | 4.4 GWh | 36.3 mi |
| Tri-Tip Wind (9) LLC | Sunray, TX | 6.3 GWh | 5.5 mi |