Seymour Hills Wind Project, LLC
TBD, Seymour, TX 76380Plant Summary Information
Seymour Hills Wind Project, LLC is ranked #203 out of 228 wind farms in Texas in terms of total annual net electricity generation.
Seymour Hills Wind Project, LLC generated 36.2 GWh during the 3-month period between March 2026 to June 2026.
| Plant Name | Seymour Hills Wind Project, LLC |
|---|---|
| Utility Name | Engie North America |
| Location | Baylor County, TX |
| Initial Operation Date | May 2019 |
| Last Update | Jun 2026 |
| Annual Generation | 135.0 GWh |
| Annual Consumption | 502.1 k MMBtu |
| Ranked #3,136 out of 13,094 Power Plants Nationwide | |
| Ranked #856 out of 1,369 Wind Power Plants Nationwide | |
| Ranked #501 out of 858 Texas Power Plants | |
| Ranked #203 out of 228 Texas Wind Power Plants | |
| Fuel Types | Wind |
Map of Seymour Hills Wind Project, LLC
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Seymour Hills Wind Project, LLC.
Monthly Net Generation for Seymour Hills Wind Project, LLC
Monthly Plant Fuel Consumption for Seymour Hills Wind Project, LLC
Seymour Hills Wind Project, LLC Details
| Summary Information | |
|---|---|
| Plant Name | Seymour Hills Wind Project, LLC (62227) |
| Plant Address | TBD, Seymour, TX 76380 |
| Utility | Engie North America (56201) |
| Latitude, Longitude | 33.57824, -99.1921 |
| Generation Dates on File | Jun 2019 to Jun 2026 |
| Initial Operation Date | May 2019 |
| Annual Generation | 135.0 GWh |
| Fuel Types | Wind |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | TRE |
| Balancing Authority | Electric Reliability Council of Texas, Inc. (ERCO) |
| NAICS Code | Utilities (22) |
| Sector | IPP Non-CHP (2) |
| Water Source | |
| Ash Impoundment | No |
| Transmission / Distribution Owner | Brazos Electric Power Coop Inc (2172) |
| Grid Voltage | 69.00 kV |
| Energy Storage | No |
Generator WTGS Details Operating May 2019
| Technology | Onshore Wind Turbine |
|---|---|
| Prime Mover | Wind Turbine, Onshore |
| Ownership | Wholly Owned by Other Entity |
| Nameplate Capacity | 30.2 MW |
| Nameplate Power Factor | 0.95 |
| Summer Capacity | 30.2 MW |
| Winter Capacity | 30.2 MW |
| Minimum Load | 2.5 MW |
| Uprate/Derate Completed | No |
|---|---|
| Status | Operating |
| First Operation Date | May 2019 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Wind |
| Turbines/Hydrokinetic Buoys | 12 |
| Multiple Fuels | No |
| Turbine Details | |
| Number Of Turbines | 12 |
|---|---|
| Predominant Turbine Manufacturer | GE |
| Predominant Turbine Model Number | 2.5-120 |
| Design Wind Speed | 18.8 MPH |
| Wind Quality Class | 2 - Medium Wind |
| Turbine Hub Height Feet | 292 |
Seymour Hills Wind Project, LLC Plant Owners
| Owner Name | Address | Ownership |
|---|---|---|
| Seymour Hills Wind Project, LLC | 1990 Post Oak BLVD., Suite 1900, Houston, TX 77056 | 100.00% |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #846 | Oklahoma Wind Energy Center | Woodward, OK | 140.6 GWh |
| #847 | Woodward Mountain I | Girvin, TX | 140.1 GWh |
| #848 | Smoky Hills Wind Project Phase I | Lincoln, KS | 139.8 GWh |
| #849 | Dillon Wind LLC | North Palm Springs, CA | 138.3 GWh |
| #850 | Sweetwater Wind 1 LLC | Sweetwater, TX | 138.2 GWh |
| #851 | Beech Ridge II Wind Energy Center | Rupert, WV | 138.2 GWh |
| #852 | Butler Ridge | Mayville, WI | 137.5 GWh |
| #853 | Eurus Combine Hills Turbine Ranch 2 | Milton Freewater, OR | 137.0 GWh |
| #854 | Prairie Breeze III | Elgin, NE | 136.3 GWh |
| #855 | Passadumkeag Windpark LLC | Greenbush, ME | 135.5 GWh |
| #857 | Providence Heights Wind LLC | Tiskilwa, IL | 134.8 GWh |
| #858 | Northern Iowa Windpower II | Kensett, IA | 134.3 GWh |
| #859 | Howard Wind Farm | Hornell, NY | 133.5 GWh |
| #860 | Woodward Mountain II | Girvin, TX | 132.5 GWh |
| #861 | Sunray Wind I | Sunray, TX | 131.4 GWh |
| #862 | Sandy Ridge Wind Farm | Tyrone, PA | 131.1 GWh |
| #863 | Golden Hills North Wind Energy Center | Livermore, CA | 130.8 GWh |
| #864 | Kumeyaay Wind | Campo, CA | 130.5 GWh |
| #865 | Palmer's Creek Wind Farm, LLC | Granite Falls, MN | 130.5 GWh |
| #866 | Forest Creek Wind Farm LLC | Big Springs, TX | 128.4 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Seymour Hills Wind Project, LLC.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Azure Sky Wind Project, LLC Hybrid | Throckmorton, TX | 1.2 TWh | 28.6 mi |
| Bobcat Bluff Wind Project LLC | Archer, TX | 484.8 GWh | 35.6 mi |
| Diversion Wind Energy LLC | Seymour, TX | 738.1 GWh | 13.8 mi |
| El Campo Wind | Truscott, TX | 850.5 GWh | 32.5 mi |
| Electra Wind Farm | Oklaunion, TX | 812.1 GWh | 36.5 mi |
| Green Pastures Wind I | Seymour, TX | 255.6 GWh | 13.1 mi |
| Green Pastures Wind II | Seymour, TX | 298.1 GWh | 20.2 mi |
| Griffin Trail Wind | E Seymour, TX | 738.8 GWh | 22.6 mi |
| Horse Creek Wind Farm | Weinert, TX | 820.0 GWh | 25.5 mi |
| Inertia Wind Project | Haskell, TX | 1.3 TWh | 35.7 mi |
| King Creek Wind Farm 1, LLC | Throckmorton, TX | 605.2 GWh | 26.7 mi |
| King Creek Wind Farm 2, LLC | Throckmorton, TX | 694.7 GWh | 29.6 mi |
| Lockett Windfarm | Vernon, TX | 661.8 GWh | 34.4 mi |
| Millers Branch Solar | Haskell, TX | 233.6 GWh | 33.6 mi |
| Montgomery Ranch Wind Farm, LLC | Crowell, TX | 633.6 GWh | 32.4 mi |
| TG East | Truscott, TX | 1.0 TWh | 29.6 mi |
| Trinity Hills | Olney, TX | 818.5 GWh | 30.8 mi |
| Western Trail Wind, LLC | Electra, TX | 1.1 TWh | 20.3 mi |
| Willow Springs Wind Farm | Weinert, TX | 869.8 GWh | 29.7 mi |
| Young Wind | Graham, TX | 1.6 TWh | 37.3 mi |