El Campo Wind
5309 FM 1756 East, Truscott, TX 79227Plant Summary Information
El Campo Wind is ranked #60 out of 217 wind farms in Texas in terms of total annual net electricity generation.
El Campo Wind generated 247.0 GWh during the 3-month period between November 2023 to February 2024.
Plant Name | El Campo Wind |
---|---|
Utility Name | Longroad Energy Services LLC |
Location | Knox County, TX |
Initial Operation Date | December 2020 |
Last Update | Feb 2024 |
Annual Generation | 773.5 GWh |
Annual Consumption | 2.6 M MMBtu |
Ranked #946 out of 11,455 Power Plants Nationwide | |
Ranked #184 out of 1,337 Wind Power Plants Nationwide | |
Ranked #163 out of 726 Texas Power Plants | |
Ranked #60 out of 217 Texas Wind Power Plants | |
Fuel Types | Wind |
Map of El Campo Wind
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for El Campo Wind.
Monthly Net Generation for El Campo Wind
El Campo Wind Details
Summary Information | |
---|---|
Plant Name | El Campo Wind (62765) |
Plant Address | 5309 FM 1756 East Truscott, TX 79227 |
Utility | Longroad Energy Services LLC (61219) |
Latitude, Longitude | 33.73218, -99.72639 |
Generation Dates on File | Dec 2020 to Feb 2024 |
Initial Operation Date | December 2020 |
Annual Generation | 773.5 GWh |
Fuel Types | Wind |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | TRE |
Balancing Authority | Electric Reliability Council of Texas, Inc. (ERCO) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | |
Transmission / Distribution Owner | Electric Transmission Texas LLC (50174) |
Grid Voltage | 345.00 kV |
Energy Storage | No |
Generator CAMPO Details Operating December 2020
Technology | Onshore Wind Turbine |
---|---|
Prime Mover | Wind Turbine, Onshore |
Ownership | Single Owner |
Nameplate Capacity | 242.8 MW |
Summer Capacity | 242.8 MW |
Winter Capacity | 242.8 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | December 2020 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Wind |
Turbines/Hydrokinetic Buoys | 67 |
Turbine Details | |
Number Of Turbines | 67 |
---|---|
Predominant Turbine Manufacturer | Vestas |
Predominant Turbine Model Number | V150-4.2 |
Design Wind Speed | 16.8 MPH |
Wind Quality Class | 3 - Low Wind |
Turbine Hub Height Feet | 344 |
El Campo Wind Plant Owners
Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#174 | Buckeye Wind Energy Center | Hays, KS | 791.6 GWh |
#175 | Limestone Wind Project | Coolidge, TX | 787.3 GWh |
#176 | BMP Wind (TX) | Baird, TX | 786.2 GWh |
#177 | Pryor Mountain Wind | Bridger, MT | 783.6 GWh |
#178 | FPL Energy Crystal Lake Wind II LLC | Britt, IA | 783.4 GWh |
#179 | Isabella Wind Park | Rosebush, MI | 780.4 GWh |
#180 | Panther Creek Wind Farm Three | Big Spring, TX | 780.3 GWh |
#181 | East Fork Wind Project, LLC | Colby, KS | 778.9 GWh |
#182 | Golden West Power Partners LLC | Calhan, CO | 776.8 GWh |
#183 | Whispering Willow North | Latimer, IA | 776.7 GWh |
#185 | Nobles Wind Project | Reading, MN | 771.9 GWh |
#186 | Bison 4 Wind Energy Center | New Salem, ND | 771.6 GWh |
#187 | Courtenay Wind Farm | Courtenay, ND | 770.5 GWh |
#188 | Minonk Wind Farm | Minonk, IL | 768.4 GWh |
#189 | Caddo Wind | Apache, OK | 766.7 GWh |
#190 | Lower Snake River Wind Energy Project | Pomeroy, WA | 766.2 GWh |
#191 | TX Hereford Wind | Hereford, TX | 766.0 GWh |
#192 | Harvest Ridge Wind Farm | Newman, IL | 765.9 GWh |
#193 | Blue Summit III Wind | Chilicothe, TX | 764.5 GWh |
#194 | Niyol Wind, LLC | Fleming, CO | 759.9 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding El Campo Wind.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Azure Sky Wind Project, LLC Hybrid | Town of Throckmorton, TX | 991.1 GWh | 46.1 mi |
Blue Summit II Wind, LLC | Vernon, TX | 393.0 GWh | 37 mi |
Blue Summit III Wind | Chilicothe, TX | 764.5 GWh | 31.7 mi |
Blue Summit Wind LLC | Vernon, TX | 462.4 GWh | 43.9 mi |
Electra Wind Farm | Oklaunion, TX | 995.5 GWh | 43.2 mi |
Foard City Wind | Crowell, TX | 1.2 TWh | 12.7 mi |
Green Pastures Wind I | Seymour, TX | 234.5 GWh | 19.5 mi |
Green Pastures Wind II | Seymour, TX | 283.4 GWh | 12.6 mi |
Griffin Trail Wind | E Seymour, TX | 820.5 GWh | 11.9 mi |
Horse Creek Wind Farm | Weinert, TX | 956.2 GWh | 28.5 mi |
Inertia Wind Project | Haskell, TX | 1.3 TWh | 38.4 mi |
King Creek Wind Farm 1, LLC | Throckmorton, TX | 583.3 GWh | 35.4 mi |
King Creek Wind Farm 2, LLC | Throckmorton, TX | 677.8 GWh | 42.6 mi |
Lockett Windfarm | Vernon, TX | 795.9 GWh | 35.4 mi |
Misae Solar | Childress, TX | 546.6 GWh | 49.6 mi |
OCI Alamo 7 LLC | Haskell, TX | 269.9 GWh | 48.9 mi |
Seymour Hills Wind Project, LLC | Seymour, TX | 142.8 GWh | 32.5 mi |
TG East | Truscott, TX | 1.1 TWh | 3.6 mi |
Western Trail Wind, LLC | Electra, TX | 915.4 GWh | 38.9 mi |
Willow Springs Wind Farm | Weinert, TX | 948.4 GWh | 27.4 mi |