Lennon Generating
9536 E. Lennon Road, Lennon, MI 48849Plant Summary Information
Lennon Generating is ranked #7 out of 23 landfill gas power plants in Michigan in terms of total annual net electricity generation.
Lennon Generating is comprised of 4 generators and generated 7.0 GWh during the 3-month period between September 2024 to December 2024.
Plant Name | Lennon Generating |
---|---|
Utility Name | North American Natural Res |
Location | Shiawassee County, MI |
Initial Operation Date | February 2001 |
Last Update | Dec 2024 |
Annual Generation | 29.9 GWh |
Annual Consumption | 358.9 k MMBtu |
Ranked #4,716 out of 12,530 Power Plants Nationwide | |
Ranked #88 out of 293 Landfill Gas Power Plants Nationwide | |
Ranked #125 out of 263 Michigan Power Plants | |
Ranked #7 out of 23 Michigan Landfill Gas Power Plants | |
Fuel Types | Landfill Gas |
Map of Lennon Generating
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Lennon Generating.
Monthly Net Generation for Lennon Generating
Lennon Generating Details
Summary Information | |
---|---|
Plant Name | Lennon Generating (59436) |
Plant Address | 9536 E. Lennon Road, Lennon, MI 48849 |
Utility | North American Natural Res (13559) |
Latitude, Longitude | 42.98167, -83.97944 |
Generation Dates on File | Jan 2014 to Dec 2024 |
Initial Operation Date | February 2001 |
Annual Generation | 29.9 GWh |
Fuel Types | Landfill Gas |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | RFC |
Balancing Authority | Midcontinent Independent Transmission System Operator, Inc.. (MISO) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | No |
Transmission / Distribution Owner | Consumers Energy Co (4254) MI |
Grid Voltage | 46.00 kV |
Energy Storage | No |
Generator 10 Details Operating September 2012
Technology | Landfill Gas |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
Nameplate Capacity | 1.6 MW |
Nameplate Power Factor | 0.96 |
Summer Capacity | 1.5 MW |
Winter Capacity | 1.5 MW |
Minimum Load | 1.4 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | September 2012 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Landfill Gas |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Generator 9 Details Operating September 2012
Technology | Landfill Gas |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
Nameplate Capacity | 1.6 MW |
Nameplate Power Factor | 0.96 |
Summer Capacity | 1.5 MW |
Winter Capacity | 1.5 MW |
Minimum Load | 1.4 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | September 2012 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Landfill Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Generator 7 Details Operating May 2014
Technology | Landfill Gas |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
Nameplate Capacity | 1.6 MW |
Nameplate Power Factor | 0.96 |
Summer Capacity | 1.5 MW |
Winter Capacity | 1.5 MW |
Minimum Load | 1.4 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | May 2014 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Landfill Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Generator 8 Details Operating May 2014
Technology | Landfill Gas |
---|---|
Prime Mover | Internal Combustion Engine |
Ownership | Single Owner |
Nameplate Capacity | 1.6 MW |
Nameplate Power Factor | 0.96 |
Summer Capacity | 1.5 MW |
Winter Capacity | 1.5 MW |
Minimum Load | 1.4 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | May 2014 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Landfill Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Lennon Generating Plant Owners
Owner Name | Address | Generator | Ownership |
---|---|---|---|
We couldn't locate any owners for this plant |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Landfill Gas.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#78 | Ameresco Forward | Manteca, CA | 31.8 GWh |
#79 | Chestnut Ridge Gas Recovery | Heiskell, TN | 31.1 GWh |
#80 | MM West Covina | West Covina, CA | 31.0 GWh |
#81 | Ameresco San Joaquin | Linden, CA | 30.7 GWh |
#82 | Prairie View I & II LFGTE | Wyatt, IN | 30.5 GWh |
#83 | Pecan Row Landfill To Electric Facility | Valdosta, GA | 30.5 GWh |
#84 | Model City Energy Facility | Youngstown, NY | 30.1 GWh |
#85 | Stanton Energy Center | Orlando, FL | 4.9 TWh |
#86 | Georgia LFG Oak Grove Plant | Winder, GA | 38.7 GWh |
#87 | Sarasota County LFGTE Facility | Nokomis, FL | 30.0 GWh |
#89 | Apple Campus 2 Fuel Cell | Cupertino, CA | 29.6 GWh |
#90 | Lincoln Landfill | Lincoln, CA | 29.5 GWh |
#91 | G2 Energy Ostrom Road LLC | Wheatland, CA | 29.0 GWh |
#92 | Bavarian LFGTE | Walton, KY | 28.7 GWh |
#93 | Bryon Center | Byron Center, MI | 28.6 GWh |
#94 | Watervliet | Watervliet, MI | 28.2 GWh |
#95 | Nanticoke LFG | Binghamton, NY | 28.2 GWh |
#96 | Suburban Landfill Gas Recovery | Glenford, OH | 28.2 GWh |
#97 | Brown County LFGTE Power Station | Georgetown, OH | 28.2 GWh |
#98 | Riverbend Landfill | McMinnville, OR | 28.1 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Lennon Generating.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Assembly Solar II LLC | Lennon, MI | 229.8 GWh | 4.4 mi |
Assembly Solar III | Lennon, MI | 163.8 GWh | 3.4 mi |
Assembly Solar Project | Venice Township, MI | 104.0 GWh | 3.3 mi |
Bingham Solar, LLC | St. Johns, MI | 41.0 GWh | 27.8 mi |
Blue Elk VII Solar, LLC | Flint, MI | 21.7 GWh | 22 mi |
Brent Run Generating Station | Montrose, MI | 51.2 GWh | 15 mi |
Captain Solar, LLC | Mt. Morris, MI | 3.7 GWh | 12.9 mi |
Coldwater Solar, LLC | Flint, MI | 3.6 GWh | 12.8 mi |
Geddes 2 Solar, LLC | Saginaw, MI | 2.9 GWh | 31.6 mi |
Genesee Power Station LP | Flint, MI | 96.5 GWh | 17.2 mi |
Grand Blanc Generating Station | Grand Blanc, MI | 51.6 GWh | 13.8 mi |
Interchange Solar, LLC | Mt. Morris, MI | 3.9 GWh | 13.3 mi |
Jack Francis Solar, LLC | Clio, MI | 3.9 GWh | 19.1 mi |
Lyons Road | Owosso, MI | 40.5 GWh | 8.3 mi |
May Shannon Solar, LLC | Clio, MI | 4.1 GWh | 18.7 mi |
Midcontinent Solar, LLC | Owosso, MI | 36.8 GWh | 9.1 mi |
Peoples Generating Station | Ann Arbor, MI | 17.1 GWh | 21.4 mi |
Spartan PV 1, LLC | East Lansing, MI | 12.0 GWh | 31.4 mi |
T B Simon Power Plant | East Lansing, MI | 251.3 GWh | 31.4 mi |
Venice Resources Gas Recovery | Lennon, MI | 10.6 GWh | 0.3 mi |