Ameresco San Joaquin

6484 North Waverly Road, Linden, CA 95326

Plant Summary Information

Ameresco San Joaquin is ranked #14 out of 35 landfill gas power plants in California in terms of total annual net electricity generation.

Ameresco San Joaquin is comprised of 2 generators and generated 7.7 GWh during the 3-month period between September 2024 to December 2024.

Plant NameAmeresco San Joaquin
Utility NameAmeresco San Joaquin, LLC
LocationSan Joaquin County, CA
Initial Operation DateApril 2014
Last Update Dec 2024
Annual Generation 30.7 GWh
Annual Consumption 332.6 k MMBtu
Ranked #4,717 out of 12,539 Power Plants Nationwide
Ranked #81 out of 293 Landfill Gas Power Plants Nationwide
Ranked #610 out of 1,600 California Power Plants
Ranked #14 out of 35 California Landfill Gas Power Plants
Fuel Types Landfill Gas

Map of Ameresco San Joaquin

Full Screen Map

Register Now for Comprehensive Access

Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Ameresco San Joaquin.

Create Your Account Today

Monthly Net Generation for Ameresco San Joaquin

Ameresco San Joaquin Details

Summary Information
Plant NameAmeresco San Joaquin (58436)
Plant Address6484 North Waverly Road, Linden, CA 95326
UtilityAmeresco San Joaquin, LLC (58432)
Latitude, Longitude38.02972, -120.92972
Generation Dates on FileApr 2014 to Dec 2024
Initial Operation DateApril 2014
Annual Generation 30.7 GWh
Fuel Types Landfill Gas
 
Federal Energy Regulatory Commission (FERC) Information
FERC Cogeneration StatusNo
FERC Small Power Producer StatusYes
FERC Small Power Producer Docket Number12-295-000
FERC Exempt Wholesale Generator StatusNo
Regulatory Information
Regulatory StatusNon-Regulated
NERC RegionWECC
Balancing AuthorityCalifornia Independent System Operator (CISO)
NAICS CodeUtilities (22)
Sector IPP Non-CHP (2)
Water Source
Ash Impoundment No
Transmission / Distribution OwnerPacific Gas & Electric Co (14328) CA
Grid Voltage 12.47 kV
Energy StorageNo

Generator ENG1 Details Operating April 2014

TechnologyLandfill Gas
Prime MoverInternal Combustion Engine
OwnershipSingle Owner
Nameplate Capacity2.2 MW
Nameplate Power Factor1
Summer Capacity2.1 MW
Winter Capacity2.1 MW
Minimum Load0.5 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateApril 2014
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceLandfill Gas
Solid Fuel Gasification No
Carbon Capture TechnologyNo
Time From Cold Shutdown To Full Load10M
Multiple FuelsNo
Cofire FuelsNo
Switch Between Oil And Natural GasNo

Generator ENG2 Details Operating April 2014

TechnologyLandfill Gas
Prime MoverInternal Combustion Engine
OwnershipSingle Owner
Nameplate Capacity2.2 MW
Nameplate Power Factor1
Summer Capacity2.1 MW
Winter Capacity2.1 MW
Minimum Load0.5 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateApril 2014
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceLandfill Gas
Solid Fuel Gasification No
Carbon Capture TechnologyNo
Time From Cold Shutdown To Full Load10M
Multiple FuelsNo
Cofire FuelsNo
Switch Between Oil And Natural GasNo

Ameresco San Joaquin Plant Owners

Owner NameAddressGeneratorOwnership
We couldn't locate any owners for this plant

Power Plants with Similar Net Generation

Power plants with a similar annual net generation from Landfill Gas.

RankPlant NamePlant LocationAnnual Generation
#71Fitchburg Gas RecoveryWestminster, MA32.3 GWh
#72Modern Innovative Energy LLCYoungstown, NY32.3 GWh
#73Ameresco Vasco RoadLivermore, CA32.3 GWh
#74Austin Gas RecoveryAustin, TX32.2 GWh
#75Uwharrie Mountain RenewableMt. Gilead, NC32.1 GWh
#76LRI LFGTE FacilityGraham, WA32.1 GWh
#77AmeliaJetersville, VA33.9 GWh
#78Ameresco ForwardManteca, CA31.8 GWh
#79Chestnut Ridge Gas RecoveryHeiskell, TN31.1 GWh
#80MM West CovinaWest Covina, CA31.0 GWh
#82Prairie View I & II LFGTEWyatt, IN30.5 GWh
#83Pecan Row Landfill To Electric FacilityValdosta, GA30.5 GWh
#84Model City Energy FacilityYoungstown, NY30.1 GWh
#85Georgia LFG Oak Grove PlantWinder, GA38.7 GWh
#86Sarasota County LFGTE FacilityNokomis, FL30.0 GWh
#87Lennon GeneratingLennon, MI29.9 GWh
#88Apple Campus 2 Fuel CellCupertino, CA29.6 GWh
#89Lincoln LandfillLincoln, CA29.5 GWh
#90Stanton Energy CenterOrlando, FL5.3 TWh
#91G2 Energy Ostrom Road LLCWheatland, CA29.0 GWh

Nearby Power Plants

Below are closest 20 power plants surrounding Ameresco San Joaquin.

Plant NamePlant LocationAnnual GenerationDistance
Amazon - Stockton - Roof (SCK1) - (CA)Stockton, CA3.6 GWh16.8 mi
Ameresco ForwardManteca, CA31.8 GWh17.2 mi
AngelsAngels Camp, CA6.3 GWh21.4 mi
Axium Modesto SolarModesto, CA47.4 GWh20.7 mi
Bear Creek Solar (CA)Lodi, CA4.0 GWh14 mi
CA Manteca 730 Spreckels AveManteca, CA323.0 MWh22 mi
CamancheClements & Wallace, CA31.7 GWh14.6 mi
Donaghy-StocktonStockton, CA2.2 GWh16.7 mi
Frankenheimer Power PlantOakdale, CA12.6 GWh15.3 mi
Kettleman Solar ProjectLodi, CA2.6 GWh13.1 mi
LodiLodi, CA2.8 GWh21.7 mi
Manteca Land PVManteca, CA1.6 GWh20.4 mi
New Hogan Power PlantValley Springs, CA8.8 GWh10.4 mi
New MelonesJamestown, CA275.9 GWh22.6 mi
Niagara Bottling StocktonStockton, CA870.0 MWh19.7 mi
PardeeValley Springs, CA117.8 GWh16.3 mi
Robert O Schulz Solar FarmOakdale, CA2.1 GWh12 mi
Stockton BiomassStockton, CA343.1 GWh22.6 mi
TullochJamestown, CA103.6 GWh20.6 mi
University of the PacificStockton, CA6.5 GWh21.1 mi