Indeck Silver Springs Energy Center
1 Indeck Drive, Silver Springs, NY 14550Plant Summary Information
Indeck Silver Springs Energy Center is ranked #47 out of 111 natural gas power plants in New York in terms of total annual net electricity generation.
Indeck Silver Springs Energy Center is comprised of 2 generators and generated 21.2 GWh during the 3-month period between September 2024 to December 2024.
Plant Name | Indeck Silver Springs Energy Center |
---|---|
Utility Name | Indeck-Energy Serv Silver Spg |
Location | Wyoming County, NY |
Initial Operation Date | May 1991 |
Last Update | Dec 2024 |
Annual Generation | 60.5 GWh |
Annual Consumption | 596.4 k MMBtu |
Ranked #3,764 out of 12,288 Power Plants Nationwide | |
Ranked #1,032 out of 2,221 Natural Gas Power Plants Nationwide | |
Ranked #115 out of 912 New York Power Plants | |
Ranked #47 out of 111 New York Natural Gas Power Plants | |
Fuel Types | Natural Gas |
Map of Indeck Silver Springs Energy Center
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Indeck Silver Springs Energy Center.
Monthly Net Generation for Indeck Silver Springs Energy Center
Indeck Silver Springs Energy Center Details
Summary Information | |
---|---|
Plant Name | Indeck Silver Springs Energy Center (50449) |
Plant Address | 1 Indeck Drive, Silver Springs, NY 14550 |
Utility | Indeck-Energy Serv Silver Spg (9245) |
Latitude, Longitude | 42.6544, -78.0772 |
Generation Dates on File | Mar 2001 to Dec 2024 |
Initial Operation Date | May 1991 |
Annual Generation | 60.5 GWh |
Fuel Types | Natural Gas |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | Yes |
FERC Cogeneration Docket Number | 88-4-000 |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | Yes |
FERC Exempt Wholesale Generator Docket Number | 06-40-000 |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | NPCC |
Balancing Authority | New York Independent System Operator (NYIS) |
NAICS Code | Utilities (22) |
Sector | IPP CHP (3) |
Water Source | Wells |
Ash Impoundment | No |
Transmission / Distribution Owner | New York State Elec & Gas Corp (13511) NY |
Grid Voltage | 115.00 kV |
Energy Storage | No |
Natural Gas Information | |
Pipeline Name | DOMINION TRANSMISSION INCORPORATED |
Natural Gas Storage | No |
Generator GEN1 Details Operating May 1991
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Combustion Turbine Part |
Unit Code | G722 |
Ownership | Single Owner |
Can Bypass Heat Recovery Steam Generator | No |
RTO ISO LMP Node Designation | PTID 23768 |
RTO ISO Location Designation For Reporting Wholesale Sales Data | PTID 23768 |
Nameplate Capacity | 39.4 MW |
Nameplate Power Factor | 0.9 |
Summer Capacity | 34.7 MW |
Winter Capacity | 45.1 MW |
Minimum Load | 34 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | May 1991 |
Combined Heat & Power | Yes |
Sector Name | IPP CHP (3) |
Topping Or Bottoming | T |
Energy Source | Natural Gas / Distillate Fuel Oil |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | Yes |
Cofire Fuels | Yes |
Switch Between Oil And Natural Gas | Yes |
Multifuel Details | |
Cofire Energy Source | NG / DFO |
---|---|
Switch When Operating | Yes |
Net Summer Capacity With Natural Gas | 34.7 MW |
Net Winter Capacity With Natural Gas | 45.1 MW |
Net Summer Capacity With Oil | 34.7 MW |
Net Winter Capacity With Oil | 45.1 MW |
Time To Switch From Gas To Oil | 1H |
Time To Switch From Oil To Gas | 1H |
Factors That Limit Switching | Yes |
Storage Limits | Yes |
Air Permit Limits | Yes |
Generator GEN2 Details Operating May 1991
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Steam Part |
Unit Code | G722 |
Ownership | Single Owner |
Duct Burners | Yes |
RTO ISO LMP Node Designation | PTID 23768 |
RTO ISO Location Designation For Reporting Wholesale Sales Data | PTID 23768 |
Nameplate Capacity | 17.2 MW |
Nameplate Power Factor | 0.9 |
Summer Capacity | 17.2 MW |
Winter Capacity | 17.2 MW |
Minimum Load | 10 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | May 1991 |
Combined Heat & Power | Yes |
Sector Name | IPP CHP (3) |
Topping Or Bottoming | T |
Energy Source | Natural Gas / Distillate Fuel Oil |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | Yes |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | Yes |
Multifuel Details | |
Switch When Operating | Yes |
---|---|
Net Summer Capacity With Natural Gas | 17.2 MW |
Net Winter Capacity With Natural Gas | 17.2 MW |
Net Summer Capacity With Oil | 17.2 MW |
Net Winter Capacity With Oil | 17.2 MW |
Time To Switch From Gas To Oil | 1H |
Time To Switch From Oil To Gas | 1H |
Factors That Limit Switching | Yes |
Storage Limits | Yes |
Air Permit Limits | Yes |
Indeck Silver Springs Energy Center Plant Owners
Owner Name | Address | Generator | Ownership |
---|---|---|---|
We couldn't locate any owners for this plant |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#1022 | Dartmouth Power Associates LP | Dartmouth, MA | 63.0 GWh |
#1023 | Essex | Essex, MO | 62.6 GWh |
#1024 | Clayville | Vineland, NJ | 62.4 GWh |
#1025 | MRP Elgin LLC | Elgin, IL | 62.2 GWh |
#1026 | Grant Town Power Plant | Grant Town, WV | 614.8 GWh |
#1027 | Loma Linda University Cogen | Loma Linda, CA | 61.6 GWh |
#1028 | CityCenter Central Plant Cogen Units | Las Vegas, NV | 61.4 GWh |
#1029 | Hopewell Mill | Hopewell, VA | 280.9 GWh |
#1030 | R M Schahfer | Wheatfield, IN | 1.8 TWh |
#1031 | Tres Port Power, LLC | Victoria, TX | 60.8 GWh |
#1033 | Paddys Run | Louisville, KY | 60.5 GWh |
#1034 | Powerlane Plant | Greenville, TX | 62.4 GWh |
#1035 | Gillette SBMC | Boston, MA | 60.0 GWh |
#1036 | Cumberland (NJ) | Millville, NJ | 59.9 GWh |
#1037 | Cymric 36W Cogen | McKittrick, CA | 59.2 GWh |
#1038 | DTE Atlantic, LLC | Atlantic City, NJ | 59.1 GWh |
#1039 | Spruance Operating Services LLC | Richmond, VA | 59.1 GWh |
#1040 | Osawatomie | Miami, KS | 58.8 GWh |
#1041 | California Institute of Technology | Pasadena, CA | 58.7 GWh |
#1042 | Dan E Karn | Essexville, MI | 63.7 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Indeck Silver Springs Energy Center.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Allegany Cogen | Fillmore, NY | 15.5 GWh | 10.5 mi |
Bliss | Bliss, NY | 170.7 GWh | 14.1 mi |
Bright Field Solar LLC(CSG) | Burns, NY | 5.7 GWh | 21.9 mi |
Chaffee Gas Recovery | Chaffee, NY | 48.4 GWh | 21.4 mi |
Geneseo Solar | Geneseo, NY | 7.7 GWh | 21.5 mi |
High Sheldon Wind Farm | Strykersville, NY | 201.4 GWh | 19.7 mi |
Houghton | Houghton, NY | 2.0 GWh | 16.2 mi |
Letchworth Solar Project | Gainesville, NY | 1.8 GWh | 5.7 mi |
Morris Ridge Solar | Mount Morris, NY | 64.2 GWh | 9.5 mi |
NY Geneseo 3240 W Lake Rd Solar | Geneseo, NY | 5.7 GWh | 22.6 mi |
NY70 Solar | Hunt, NY | 8.1 GWh | 9 mi |
OYA Main Street | York, NY | 8.1 GWh | 18.3 mi |
Podunque Road CSG | Rushford, NY | 7.6 GWh | 18.4 mi |
Route 19 #1 Community Solar Farm | Pike, NY | 3.9 GWh | 9.1 mi |
Route 19 #2 Community Solar Farm | Pike, NY | 8.6 GWh | 9.2 mi |
Stony Creek Wind Farm NY | Strykersville, NY | 232.9 GWh | 18.9 mi |
Synergy Biogas | Wyoming, NY | 3.8 GWh | 12.1 mi |
Telegraph Rd #1 Community Solar Farm | Pike, NY | 5.5 GWh | 8.3 mi |
Telegraph Rd #2 Community Solar Farm | Pike, NY | 3.3 GWh | 8.4 mi |
Wethersfield | Gainsville, NY | 218.5 GWh | 7.7 mi |