PCA, Filer City Mill
2246 Udell St, Filer City, MI 49634Plant Summary Information
PCA, Filer City Mill is ranked #29 out of 73 natural gas power plants in Michigan in terms of total annual net electricity generation.
PCA, Filer City Mill is comprised of 2 generators and generated 21.3 GWh during the 3-month period between June 2025 to September 2025.
| Plant Name | PCA, Filer City Mill |
|---|---|
| Utility Name | PCA, Filer City Mill |
| Location | Manistee County, MI |
| Initial Operation Date | January 1950 |
| Last Update | Sep 2025 |
| Annual Generation | 91.5 GWh |
| Annual Consumption | 3.0 M MMBtu |
| Ranked #3,483 out of 12,539 Power Plants Nationwide | |
| Ranked #927 out of 2,243 Natural Gas Power Plants Nationwide | |
| Ranked #84 out of 263 Michigan Power Plants | |
| Ranked #29 out of 73 Michigan Natural Gas Power Plants | |
| Fuel Types | Natural Gas |
Map of PCA, Filer City Mill
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for PCA, Filer City Mill.
Monthly Net Generation for PCA, Filer City Mill
PCA, Filer City Mill Details
| Summary Information | |
|---|---|
| Plant Name | PCA, Filer City Mill (58066) |
| Plant Address | 2246 Udell St, Filer City, MI 49634 |
| Utility | PCA, Filer City Mill (57442) |
| Latitude, Longitude | 44.21333, -86.28667 |
| Generation Dates on File | Jan 2012 to Sep 2025 |
| Initial Operation Date | January 1950 |
| Annual Generation | 91.5 GWh |
| Fuel Types | Natural Gas |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | RFC |
| Balancing Authority | Midcontinent Independent Transmission System Operator, Inc.. (MISO) |
| NAICS Code | Paper Manufacturing (322) |
| Sector | Industrial CHP (7) |
| Water Source | Lake Manistee |
| Ash Impoundment | No |
| Transmission / Distribution Owner | Consumers Energy Co (4254) MI |
| Grid Voltage | 138.00 kV |
| Energy Storage | No |
| Natural Gas Information | |
| Pipeline Name |
DTE GAS COMPANY Other - Please explain in pipeline notes below. |
| Pipeline Notes | DTE and Michicon distribute to PCA Filer. |
| Natural Gas Storage | No |
Generator TG2 Details Operating January 1950
| Technology | Natural Gas Steam Turbine |
|---|---|
| Prime Mover | Steam Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 8 MW |
| Nameplate Power Factor | 0.8 |
| Summer Capacity | 8 MW |
| Winter Capacity | 8 MW |
| Minimum Load | 0.5 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | January 1950 |
| Combined Heat & Power | Yes |
| Sector Name | Industrial CHP (7) |
|---|---|
| Topping Or Bottoming | T |
| Energy Source | Natural Gas / Purchased Steam / Other Biomass Gas / Wood/Wood Waste Solids / Sludge Waste / Tire-derived Fuels |
| Startup Source | Natural Gas |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 12H |
| Pulverized Coal Technology | No |
| Subcritical Technology | No |
| Multiple Fuels | Yes |
| Cofire Fuels | Yes |
| Switch Between Oil And Natural Gas | No |
| Multifuel Details | |
| Cofire Energy Source | NG / OBG |
|---|---|
Generator TG3 Details Operating January 1950
| Technology | Natural Gas Steam Turbine |
|---|---|
| Prime Mover | Steam Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 11.5 MW |
| Nameplate Power Factor | 0.8 |
| Summer Capacity | 11.5 MW |
| Winter Capacity | 11.5 MW |
| Minimum Load | 2 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | January 1950 |
| Combined Heat & Power | Yes |
| Sector Name | Industrial CHP (7) |
|---|---|
| Topping Or Bottoming | T |
| Energy Source | Natural Gas / Purchased Steam / Other Biomass Gas / Wood/Wood Waste Solids / Sludge Waste / Tire-derived Fuels |
| Startup Source | Natural Gas |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 12H |
| Pulverized Coal Technology | No |
| Subcritical Technology | No |
| Multiple Fuels | Yes |
| Cofire Fuels | Yes |
| Switch Between Oil And Natural Gas | No |
| Multifuel Details | |
| Cofire Energy Source | NG / OBG |
|---|---|
PCA, Filer City Mill Plant Owners
| Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #917 | Duke Energy CHP at Clemson University | Clemson, SC | 95.0 GWh |
| #918 | International Paper Texarkana Mill | Queen City, TX | 336.7 GWh |
| #919 | Central Utility Plant - Texas A&M | College Station, TX | 94.1 GWh |
| #920 | Calcasieu | Sulphur, LA | 94.1 GWh |
| #921 | Central Utility Plant at White Oak | Silver Spring, MD | 94.1 GWh |
| #922 | Stony Brook | Ludlow, MA | 125.4 GWh |
| #923 | Centrahoma West | Centrahoma, OK | 93.1 GWh |
| #924 | Goodman Energy Center | Hays, KS | 92.9 GWh |
| #925 | Selkirk Cogen | Selkirk, NY | 92.4 GWh |
| #926 | 491 E 48th Street | Holland, MI | 92.2 GWh |
| #928 | Spiritwood Station | Spiritwood, ND | 154.3 GWh |
| #929 | Delray | Detroit, MI | 91.1 GWh |
| #930 | Tenaska Georgia Generation Facility | Franklin, GA | 94.0 GWh |
| #931 | Pea Ridge | Pace, FL | 88.2 GWh |
| #932 | University of Notre Dame | Notre Dame, IN | 88.5 GWh |
| #933 | Wallingford Energy | Wallingford, CT | 87.8 GWh |
| #934 | Centrahoma East | Centrahoma, OK | 87.0 GWh |
| #935 | Castleton Energy Center | Castleton, NY | 87.1 GWh |
| #936 | MJMEUC Generating Station #1 | Laddonia, MO | 86.7 GWh |
| #937 | John Twitty Energy Center | Springfield, MO | 2.1 TWh |
Nearby Power Plants
Below are closest 20 power plants surrounding PCA, Filer City Mill.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| C W Tippy | Wellston, MI | 54.2 GWh | 17.5 mi |
| Cadillac Renewable Energy | Cadillac, MI | 135.7 GWh | 42.3 mi |
| Cargill Salt Hersey | Hersey, MI | 318.2 MWh | 53.1 mi |
| Fremont Community Digester, LLC | Newaygo, MI | 375.0 MWh | 54.3 mi |
| George Johnson | Hersey, MI | 34.0 GWh | 50 mi |
| Green Lake Solar | Interlochen, MI | 1.3 GWh | 48.7 mi |
| Hardy | Newaygo, MI | 71.6 GWh | 59.9 mi |
| Hodenpyl | Mesick, MI | 39.6 GWh | 25.3 mi |
| Lake City | Lake City, MI | 59.0 MWh | 53.3 mi |
| Lake Winds Energy Park | Ludington, MI | 262.1 GWh | 23.7 mi |
| M72 West Solar | Traverse City, MI | 2.5 GWh | 48.5 mi |
| Macbeth Solar | Montague, MI | 38.9 GWh | 53.7 mi |
| Michigan Power LP | Ludington, MI | 1.1 TWh | 20.3 mi |
| Morey Road | Lake City, MI | 71.0 MWh | 53.6 mi |
| National Energy of McBain | McBain, MI | 122.2 GWh | 52.8 mi |
| Rogers | Big Rapids, MI | 16.4 GWh | 57.7 mi |
| Stoney Corners Wind Farm | McBain, MI | 126.7 GWh | 49 mi |
| TCLP Solar Phase 1 | Traverse City, MI | 1.5 GWh | 48.7 mi |
| TES Filer City Station | Filer City, MI | 316.0 GWh | 0.3 mi |
| Workman Road Solar Farm, LLC | Lake City, MI | 3.8 GWh | 53.4 mi |