Grady Wind Energy Center, LLC
410 SR 19, Clovis, NM 88101Plant Summary Information
Grady Wind Energy Center, LLC is ranked #12 out of 152 power plants in New Mexico in terms of total annual net electricity generation.
Grady Wind Energy Center, LLC generated 257.7 GWh during the 3-month period between February 2026 to May 2026.
| Plant Name | Grady Wind Energy Center, LLC |
|---|---|
| Utility Name | Pattern Operators LP |
| Location | Curry County, NM |
| Initial Operation Date | August 2019 |
| Last Update | May 2026 |
| Annual Generation | 861.4 GWh |
| Annual Consumption | 3.1 M MMBtu |
| Ranked #836 out of 13,081 Power Plants Nationwide | |
| Ranked #102 out of 1,366 Wind Power Plants Nationwide | |
| Ranked #12 out of 152 New Mexico Power Plants | |
| Ranked #7 out of 30 New Mexico Wind Power Plants | |
| Fuel Types | Wind |
Map of Grady Wind Energy Center, LLC
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Grady Wind Energy Center, LLC.
Monthly Net Generation for Grady Wind Energy Center, LLC
Monthly Plant Fuel Consumption for Grady Wind Energy Center, LLC
Grady Wind Energy Center, LLC Details
| Summary Information | |
|---|---|
| Plant Name | Grady Wind Energy Center, LLC (60317) |
| Plant Address | 410 SR 19, Clovis, NM 88101 |
| Utility | Pattern Operators LP (56545) |
| Latitude, Longitude | 34.73414, -103.09223 |
| Generation Dates on File | Jul 2019 to May 2026 |
| Initial Operation Date | August 2019 |
| Annual Generation | 861.4 GWh |
| Fuel Types | Wind |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | WECC |
| Balancing Authority | Public Service Company of New Mexico (PNM) |
| NAICS Code | Utilities (22) |
| Sector | IPP Non-CHP (2) |
| Water Source | |
| Ash Impoundment | No |
| Transmission / Distribution Owner | Public Service Co of NM (15473) NM |
| Grid Voltage | 34.50 kV |
| Energy Storage | No |
Generator 1 Details Operating August 2019
| Technology | Onshore Wind Turbine |
|---|---|
| Prime Mover | Wind Turbine, Onshore |
| Ownership | Wholly Owned by Other Entity |
| Nameplate Capacity | 220.5 MW |
| Summer Capacity | 220.5 MW |
| Winter Capacity | 220.5 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | August 2019 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Wind |
| Turbines/Hydrokinetic Buoys | 96 |
| Turbine Details | |
| Number Of Turbines | 96 |
|---|---|
| Predominant Turbine Manufacturer | Siemens |
| Predominant Turbine Model Number | SWT-2.3-108 |
| Design Wind Speed | 19 MPH |
| Wind Quality Class | 2 - Medium Wind |
| Turbine Hub Height Feet | 80 |
Grady Wind Energy Center, LLC Plant Owners
| Owner Name | Address | Ownership |
|---|---|---|
| Grady Wind Energy Center, LLC | 410 SR 19, Clovis, NM 88101 | 100.00% |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #92 | Pyron Wind Farm LLC Hybrid | Hermleigh, TX | 896.2 GWh |
| #93 | Little Blue Wind Project, LLC | Blue Hill, NE | 894.3 GWh |
| #94 | Roundhouse Wind Energy Project | Cheyenne, WY | 894.0 GWh |
| #95 | Kingfisher Wind LLC | Kingfisher, OK | 885.0 GWh |
| #96 | Dermott Wind | Snyder, TX | 879.7 GWh |
| #97 | Red Dirt Wind Project | Hennessy, OK | 874.4 GWh |
| #98 | Tecolote Wind LLC | Duran, NM | 865.6 GWh |
| #99 | Willow Springs Wind Farm | Weinert, TX | 864.7 GWh |
| #100 | Stephens Ranch Wind Energy LLC | O'Donnell, TX | 863.3 GWh |
| #101 | Persimmon Creek Wind Farm 1, LLC | Vici, OK | 863.3 GWh |
| #103 | La Joya NM | Encino, NM | 860.9 GWh |
| #104 | Karankawa Wind LLC | Mathis, TX | 859.6 GWh |
| #105 | Shamrock Wind | TBD, TX | 841.1 GWh |
| #106 | Diamond Trail Wind Farm | Ladora, IA | 854.7 GWh |
| #107 | North Bend Wind Project, LLC | Highmore, SD | 853.6 GWh |
| #108 | Hubbard Wind | Mt Calm, TX | 853.4 GWh |
| #109 | Diamond Spring, LLC | Sulphur, OK | 852.3 GWh |
| #110 | Haystack Wind Project, LLC | Carroll, NE | 852.3 GWh |
| #111 | O'Brien Wind | Primghar, IA | 851.2 GWh |
| #112 | Blooming Grove Wind Energy Center | Chenoa, IL | 850.2 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Grady Wind Energy Center, LLC.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Bethel Wind Farm LLC | Dimmitt, TX | 1.1 TWh | 36.8 mi |
| Blue Cloud Wind Energy LLC | Sudan, TX | 565.3 GWh | 53.9 mi |
| Broadview Energy JN, LLC | Texico, NM | 684.2 GWh | 0.9 mi |
| Broadview Energy KW, LLC | Texico, NM | 545.1 GWh | 4.3 mi |
| Broadview Energy Prime | Grady, NM | 12.9 GWh | 13.2 mi |
| Broadview Energy Prime 2 | Grady, NM | 9.8 GWh | 12.1 mi |
| Canadian Breaks, LLC | Vega, TX | 792.9 GWh | 54.5 mi |
| Caprock Solar 1 LLC | San Jon, NM | 57.5 GWh | 23.6 mi |
| Caprock Wind Farm | San Jon, NM | 378.7 GWh | 22.6 mi |
| Casa Mesa Wind Energy Center Hybrid | House, NM | 179.6 GWh | 50.5 mi |
| Mariah del Norte | Friona, TX | 840.8 GWh | 29.6 mi |
| New Mexico Wind Energy Center | House, NM | 523.4 GWh | 54.7 mi |
| Plant X | Earth, TX | 815.7 GWh | 55.2 mi |
| Quay County | Tucumcari, NM | 42.0 MWh | 47.6 mi |
| SoCore Clovis 1 | Clovis, NM | 4.6 GWh | 23.4 mi |
| Spinning Spur Wind II | Adrian, TX | 381.2 GWh | 44.1 mi |
| Spinning Spur Wind III | Adrian, TX | 718.6 GWh | 44.1 mi |
| Tolk | Muleshoe, TX | 3.1 TWh | 48.1 mi |
| TX Hereford Wind | Hereford, TX | 587.2 GWh | 52.1 mi |
| TX Jumbo Road Wind | Hereford, TX | 545.7 GWh | 47.6 mi |