Cimarron Bend III
407 County Road 7, Minneola, KS 67865Plant Summary Information
Cimarron Bend III is ranked #26 out of 176 power plants in Kansas in terms of total annual net electricity generation.
Cimarron Bend III generated 187.5 GWh during the 3-month period between May 2026 to August 2026.
| Plant Name | Cimarron Bend III |
|---|---|
| Utility Name | Enel Kansas, LLC |
| Location | Clark County, KS |
| Initial Operation Date | December 2020 |
| Last Update | Aug 2026 |
| Annual Generation | 725.4 GWh |
| Annual Consumption | 2.6 M MMBtu |
| Ranked #995 out of 13,301 Power Plants Nationwide | |
| Ranked #203 out of 1,377 Wind Power Plants Nationwide | |
| Ranked #26 out of 176 Kansas Power Plants | |
| Ranked #19 out of 52 Kansas Wind Power Plants | |
| Fuel Types | Wind |
Map of Cimarron Bend III
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Cimarron Bend III.
Monthly Net Generation for Cimarron Bend III
Monthly Plant Fuel Consumption for Cimarron Bend III
Cimarron Bend III Details
| Summary Information | |
|---|---|
| Plant Name | Cimarron Bend III (64074) |
| Plant Address | 407 County Road 7, Minneola, KS 67865 |
| Utility | Enel Kansas, LLC (61372) |
| Latitude, Longitude | 37.371, -99.994 |
| Generation Dates on File | Nov 2020 to Aug 2026 |
| Initial Operation Date | December 2020 |
| Annual Generation | 725.4 GWh |
| Fuel Types | Wind |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | MRO |
| Balancing Authority | Southwest Power Pool (SWPP) |
| NAICS Code | Utilities (22) |
| Sector | IPP Non-CHP (2) |
| Water Source | |
| Ash Impoundment | |
| Transmission / Distribution Owner | ITC Great Plains, LLC (56526) |
| Grid Voltage | 345.00 kV |
| Energy Storage | No |
Generator 3 Details Operating December 2020
| Technology | Onshore Wind Turbine |
|---|---|
| Prime Mover | Wind Turbine, Onshore |
| Ownership | Single Owner |
| Nameplate Capacity | 198.8 MW |
| Summer Capacity | 198.8 MW |
| Winter Capacity | 198.8 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | December 2020 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Wind |
| Turbines/Hydrokinetic Buoys | 74 |
| Turbine Details | |
| Number Of Turbines | 74 |
|---|---|
| Predominant Turbine Manufacturer | GE |
| Predominant Turbine Model Number | 2.82-127 |
| Design Wind Speed | 22 MPH |
| Wind Quality Class | 2 - Medium Wind |
| Turbine Hub Height Feet | 374 |
Cimarron Bend III Plant Owners
| Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #193 | Whispering Willow North | Latimer, IA | 739.1 GWh |
| #194 | Diversion Wind Energy LLC | Seymour, TX | 738.1 GWh |
| #195 | South Plains Wind Phase I | Floydada, TX | 737.3 GWh |
| #196 | Tucannon River Wind Farm | Dayton, WA | 736.8 GWh |
| #197 | West Raymond Wind Farm LLC | Lyford, TX | 735.1 GWh |
| #198 | Klondike Windpower III | Wasco, OR | 733.2 GWh |
| #199 | White Rock East Wind Project | Anadarko, OK | 730.2 GWh |
| #200 | Cross Winds Energy Park | Unionville, MI | 728.2 GWh |
| #201 | Rattlesnake Den | Garden City, TX | 726.4 GWh |
| #202 | Harvest Ridge Wind Farm | Newman, IL | 725.7 GWh |
| #204 | Great Pathfinder Wind | Stratford, IA | 724.2 GWh |
| #205 | Jayhawk Wind Energy Center | Hepler, KS | 720.4 GWh |
| #206 | Broadview Energy JN, LLC | Texico, NM | 719.3 GWh |
| #207 | Spinning Spur Wind III | Adrian, TX | 718.6 GWh |
| #208 | Upstream Wind Energy LLC | Neligh, NE | 714.4 GWh |
| #209 | Bishop Hill Energy LLC | Cambridge, IL | 713.3 GWh |
| #210 | Grandview Wind Farm, LLC | Panhandle, TX | 709.0 GWh |
| #211 | Pryor Mountain Wind | Bridger, MT | 709.0 GWh |
| #212 | Javelina Wind Energy, LLC | Mirando City, TX | 708.9 GWh |
| #213 | King Creek Wind Farm 2, LLC | Throckmorton, TX | 707.5 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Cimarron Bend III.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Ashland | Ashland, KS | 32.0 MWh | 17.6 mi |
| Bloom Wind | Minneola, KS | 640.3 GWh | 8.8 mi |
| Boot Hill Solar | Dodge City, KS | 171.6 GWh | 22.3 mi |
| Cimarron Bend Wind Project I, LLC | Minneola, KS | 759.8 GWh | 1.1 mi |
| Cimarron Bend Wind Project II, LLC | Minneola, KS | 772.3 GWh | 1.1 mi |
| Cimarron Wind Energy LLC | Cimmaron, KS | 340.2 GWh | 38.1 mi |
| Cimarron Windpower II | Cimarron, KS | 437.0 GWh | 42.1 mi |
| CMS-Coldwater | Coldwater, KS | 3.4 GWh | 35.1 mi |
| Ensign Wind LLC | Montezuma, KS | 400.0 GWh | 22.9 mi |
| Fort Dodge | Dodge City, KS | 41.6 GWh | 25.1 mi |
| Gray County Wind Energy | Montezuma, KS | 237.3 GWh | 26.9 mi |
| Greensburg | Greensburg, KS | 7.7 GWh | 37.7 mi |
| Greensburg Solar | Greensburg, KS | 1.7 GWh | 39.5 mi |
| Iron Star Wind Project | Dodge City, KS | 1.3 TWh | 19.2 mi |
| Ironwood Wind | Spearville, KS | 476.3 GWh | 33.1 mi |
| Meade | Meade, KS | 73.0 MWh | 19.5 mi |
| Shooting Star | Mullinville, KS | 164.5 GWh | 31.7 mi |
| Spearville | Ford, KS | 128.1 GWh | 36.5 mi |
| Spearville 3 LLC | Spearville, KS | 170.5 GWh | 34.3 mi |
| Western Plains Wind Farm | Spearville, KS | 1.1 TWh | 37.6 mi |