Wilton Wind II LLC
5120 279th Ave NE, Wilton, ND 58579Plant Summary Information
Wilton Wind II LLC is ranked #37 out of 59 power plants in North Dakota in terms of total annual net electricity generation.
Wilton Wind II LLC generated 57.0 GWh during the 3-month period between September 2025 to December 2025.
| Plant Name | Wilton Wind II LLC |
|---|---|
| Utility Name | Wilton Wind II LLC |
| Location | Burleigh County, ND |
| Initial Operation Date | November 2009 |
| Last Update | Dec 2025 |
| Annual Generation | 201.1 GWh |
| Annual Consumption | 747.7 k MMBtu |
| Ranked #2,524 out of 13,081 Power Plants Nationwide | |
| Ranked #749 out of 1,366 Wind Power Plants Nationwide | |
| Ranked #37 out of 59 North Dakota Power Plants | |
| Ranked #28 out of 42 North Dakota Wind Power Plants | |
| Fuel Types | Wind |
Map of Wilton Wind II LLC
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Wilton Wind II LLC.
Monthly Net Generation for Wilton Wind II LLC
Monthly Plant Fuel Consumption for Wilton Wind II LLC
Wilton Wind II LLC Details
| Summary Information | |
|---|---|
| Plant Name | Wilton Wind II LLC (57120) |
| Plant Address | 5120 279th Ave NE, Wilton, ND 58579 |
| Utility | Wilton Wind II LLC (56415) |
| Latitude, Longitude | 47.1333, -100.7011 |
| Generation Dates on File | Nov 2009 to Dec 2025 |
| Initial Operation Date | November 2009 |
| Annual Generation | 201.1 GWh |
| Fuel Types | Wind |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | MRO |
| Balancing Authority | Midcontinent Independent Transmission System Operator, Inc.. (MISO) |
| NAICS Code | Utilities (22) |
| Sector | IPP Non-CHP (2) |
| Water Source | |
| Ash Impoundment | No |
| Transmission / Distribution Owner | Central Power Elec Coop, Inc (3279) |
| Grid Voltage | 230.00 kV |
| Energy Storage | No |
Generator 1 Details Operating November 2009
| Technology | Onshore Wind Turbine |
|---|---|
| Prime Mover | Wind Turbine, Onshore |
| Ownership | Single Owner |
| Nameplate Capacity | 49.5 MW |
| Summer Capacity | 49.5 MW |
| Winter Capacity | 49.5 MW |
| Minimum Load | 2.5 MW |
| Uprate/Derate Completed | No |
|---|---|
| Status | Operating |
| First Operation Date | November 2009 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Wind |
| Turbines/Hydrokinetic Buoys | 33 |
| Turbine Details | |
| Number Of Turbines | 33 |
|---|---|
| Predominant Turbine Manufacturer | GE |
| Predominant Turbine Model Number | 1.5 XLE |
| Design Wind Speed | 16.8 MPH |
| Wind Quality Class | 3 - Low Wind |
| Turbine Hub Height Feet | 262.5 |
Wilton Wind II LLC Plant Owners
| Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #739 | NaturEner Glacier Wind Energy 2 | Ethridge, MT | 205.6 GWh |
| #740 | NaturEner Glacier Wind Energy 1 | Ethridge, MT | 205.5 GWh |
| #741 | Cohocton Wind Project | Cohocton, NY | 205.5 GWh |
| #742 | Silver Star I Wind Power Project | Dublin, TX | 204.9 GWh |
| #743 | Independence Wind Farm | Manchester, IA | 204.7 GWh |
| #744 | Pinyon Pine II | Mojave, CA | 204.3 GWh |
| #745 | Flat Water Wind Farm LLC | Du Bois, NE | 203.9 GWh |
| #746 | Star Point Wind Project LLC | Wasco, OR | 201.3 GWh |
| #747 | North Allegheny Windpower Project | Lilly, PA | 201.3 GWh |
| #748 | Coachella Hills Wind | Palm Springs, CA | 201.2 GWh |
| #750 | Chateaugay | Chateaugay, NY | 200.8 GWh |
| #751 | Bluegrass Ridge | King City, MO | 199.7 GWh |
| #752 | Arlington Wind Power Project | Arlington, OR | 199.4 GWh |
| #753 | Crescent Ridge | Tiskilwa, IL | 199.2 GWh |
| #754 | Harvest 2 | Elkton, MI | 199.0 GWh |
| #755 | Locust Ridge II LLC | Shenandoah, PA | 198.7 GWh |
| #756 | Wheat Field Wind Power Project | Arlington, OR | 197.5 GWh |
| #757 | Golden Spread Panhandle Wnd Rch | Wilderado, TX | 196.8 GWh |
| #758 | Bison I Wind Energy Center | New Salem, ND | 196.5 GWh |
| #759 | Jeffers Wind 20 LLC | Jeffers, MN | 196.5 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Wilton Wind II LLC.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Baldwin Wind LLC | Wilton, ND | 384.1 GWh | 1.4 mi |
| Bison 2 Wind Energy Center | New Salem, ND | 269.8 GWh | 41.6 mi |
| Bison 3 Wind Energy Center | New Salem, ND | 267.9 GWh | 41.6 mi |
| Bison 4 Wind Energy Center | New Salem, ND | 572.9 GWh | 41.6 mi |
| Bison I Wind Energy Center | New Salem, ND | 196.5 GWh | 41.6 mi |
| Coal Creek | Underwood, ND | 8.0 TWh | 27.2 mi |
| Coyote | Beulah, ND | 2.5 TWh | 52.7 mi |
| FPL Energy Burleigh County Wind | Wilton, ND | 180.2 GWh | 1.9 mi |
| FPL Energy Oliver Wind I LLC | Center, ND | 181.6 GWh | 23.4 mi |
| FPL Energy Oliver Wind II LLC | Center, ND | 189.5 GWh | 23.4 mi |
| Garrison | Riverside, ND | 2.0 TWh | 41.6 mi |
| Glen Ullin Energy Center | Glen Ullin, ND | 423.3 GWh | 53.8 mi |
| Glen Ullin Station 6 | Glen Ullin, ND | 32.3 GWh | 54.2 mi |
| Leland Olds | Stanton, ND | 2.9 TWh | 30.8 mi |
| Milton R Young | Center, ND | 3.9 TWh | 24.5 mi |
| New Frontier Wind | Ruso, ND | 368.6 GWh | 51.6 mi |
| Oliver Wind III, LLC | Mandan, ND | 365.7 GWh | 25.1 mi |
| Oliver Wind IV | Hannover, ND | 805.9 GWh | 42.8 mi |
| R M Heskett | Mandan, ND | 61.8 GWh | 20.3 mi |
| Tesoro Mandan Cogeneration Plant | Mandan, ND | 50.4 GWh | 21.4 mi |