Noblesville
21225 Riverwood Ave, Noblesville, IN 46060Plant Summary Information
Noblesville is ranked #16 out of 218 power plants in Indiana in terms of total annual net electricity generation.
Noblesville is comprised of 5 generators and generated 478.4 GWh during the 3-month period between September 2025 to December 2025.
| Plant Name | Noblesville |
|---|---|
| Utility Name | Duke Energy Indiana, LLC |
| Location | Hamilton County, IN |
| Initial Operation Date | September 1950 |
| Last Update | Dec 2025 |
| Annual Generation | 1.7 TWh |
| Annual Consumption | 15.2 M MMBtu |
| Ranked #555 out of 13,081 Power Plants Nationwide | |
| Ranked #349 out of 2,206 Natural Gas Power Plants Nationwide | |
| Ranked #16 out of 218 Indiana Power Plants | |
| Ranked #7 out of 46 Indiana Natural Gas Power Plants | |
| Fuel Types | Natural Gas |
| Previous Operator |
Duke Energy Indiana Inc (2013 to 2014) Duke Energy Indiana, LLC (2015 to 2025) |
Map of Noblesville
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Noblesville.
Monthly Net Generation for Noblesville
Monthly Plant Fuel Consumption for Noblesville
Noblesville Details
| Summary Information | |
|---|---|
| Plant Name | Noblesville (1007) |
| Plant Address | 21225 Riverwood Ave, Noblesville, IN 46060 |
| Utility | Duke Energy Indiana, LLC (15470) |
| Latitude, Longitude | 40.0969, -85.9714 |
| Generation Dates on File | Jan 2001 to Dec 2025 |
| Initial Operation Date | September 1950 |
| Annual Generation | 1.7 TWh |
| Fuel Types | Natural Gas |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Regulated |
| NERC Region | RFC |
| Balancing Authority | Midcontinent Independent Transmission System Operator, Inc.. (MISO) |
| NAICS Code | Utilities (22) |
| Sector | Electric Utility (1) |
| Water Source | White River |
| Ash Impoundment | No |
| Transmission / Distribution Owner | Duke Energy Indiana Inc (15470) IN |
| Grid Voltage | 138.00 kV |
| Energy Storage | No |
| Natural Gas Information | |
| Pipeline Name | PANHANDLE EASTERN PIPELINE COMPANY |
| Natural Gas Storage | No |
| Liquefied Natural Gas Storage | No |
Generator 1 Details Operating December 1950
| Technology | Natural Gas Fired Combined Cycle |
|---|---|
| Prime Mover | Combined Cycle Steam Part |
| Unit Code | CC1 |
| Ownership | Single Owner |
| Duct Burners | No |
| RTO ISO LMP Node Designation | CP/Comm Pricing |
| RTO ISO Location Designation For Reporting Wholesale Sales Data | CP/Comm Pricing |
| Nameplate Capacity | 50 MW |
| Nameplate Power Factor | 0.8 |
| Summer Capacity | 42 MW |
| Winter Capacity | 43 MW |
| Minimum Load | 42 MW |
|---|---|
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | December 1950 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Natural Gas |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 12H |
| Multiple Fuels | No |
Generator 2 Details Operating September 1950
| Technology | Natural Gas Fired Combined Cycle |
|---|---|
| Prime Mover | Combined Cycle Steam Part |
| Unit Code | CC1 |
| Ownership | Single Owner |
| Duct Burners | No |
| RTO ISO LMP Node Designation | CP/Comm Pricing |
| RTO ISO Location Designation For Reporting Wholesale Sales Data | CP/Comm Pricing |
| Nameplate Capacity | 50 MW |
| Nameplate Power Factor | 0.8 |
| Summer Capacity | 43 MW |
| Winter Capacity | 44 MW |
| Minimum Load | 43 MW |
|---|---|
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | September 1950 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Natural Gas |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 12H |
| Multiple Fuels | No |
Generator 3 Details Operating June 2003
| Technology | Natural Gas Fired Combined Cycle |
|---|---|
| Prime Mover | Combined Cycle Combustion Turbine Part |
| Unit Code | CC1 |
| Ownership | Single Owner |
| Can Bypass Heat Recovery Steam Generator | Yes |
| RTO ISO LMP Node Designation | CP/Comm Pricing |
| RTO ISO Location Designation For Reporting Wholesale Sales Data | CP/Comm Pricing |
| Nameplate Capacity | 61 MW |
| Nameplate Power Factor | 0.8 |
| Summer Capacity | 60 MW |
| Winter Capacity | 74 MW |
| Minimum Load | 60 MW |
|---|---|
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | June 2003 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Natural Gas |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 12H |
| Multiple Fuels | No |
Generator 4 Details Operating June 2003
| Technology | Natural Gas Fired Combined Cycle |
|---|---|
| Prime Mover | Combined Cycle Combustion Turbine Part |
| Unit Code | CC1 |
| Ownership | Single Owner |
| Can Bypass Heat Recovery Steam Generator | Yes |
| RTO ISO LMP Node Designation | CP/Comm Pricing |
| RTO ISO Location Designation For Reporting Wholesale Sales Data | CP/Comm Pricing |
| Nameplate Capacity | 61 MW |
| Nameplate Power Factor | 0.8 |
| Summer Capacity | 60 MW |
| Winter Capacity | 74 MW |
| Minimum Load | 60 MW |
|---|---|
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | June 2003 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Natural Gas |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 12H |
| Multiple Fuels | No |
Generator 5 Details Operating June 2003
| Technology | Natural Gas Fired Combined Cycle |
|---|---|
| Prime Mover | Combined Cycle Combustion Turbine Part |
| Unit Code | CC1 |
| Ownership | Single Owner |
| Can Bypass Heat Recovery Steam Generator | Yes |
| RTO ISO LMP Node Designation | CP/Comm Pricing |
| RTO ISO Location Designation For Reporting Wholesale Sales Data | CP/Comm Pricing |
| Nameplate Capacity | 61 MW |
| Nameplate Power Factor | 0.8 |
| Summer Capacity | 59 MW |
| Winter Capacity | 75 MW |
| Minimum Load | 59 MW |
|---|---|
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | June 2003 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Natural Gas |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 12H |
| Multiple Fuels | No |
Noblesville Plant Owners
| Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #339 | Dow St Charles Operations | Taft, LA | 1.8 TWh |
| #340 | Rockingham County CT Station | Reidsville, NC | 1.8 TWh |
| #341 | George M Sullivan Generation Plant 2 | Anchorage, AK | 1.8 TWh |
| #342 | Freeport Energy | Freeport, TX | 1.8 TWh |
| #343 | Pleasants Energy LLC | St Mary's, WV | 1.8 TWh |
| #344 | Apex Generating Station | Las Vegas, NV | 1.8 TWh |
| #345 | Higgins Generating Station | Primm, NV | 1.7 TWh |
| #346 | Greenwood (MI) | Avoca, MI | 1.7 TWh |
| #347 | Pioneer Generation Station | Williston, ND | 1.7 TWh |
| #348 | Rathdrum Power LLC | Rathdrum, ID | 1.7 TWh |
| #350 | McClain Energy Facility | Newcastle, OK | 1.7 TWh |
| #351 | AES Huntington Beach Energy Project | Huntington Beach, CA | 1.7 TWh |
| #352 | Langley Gulch Power Plant | New Plymouth, ID | 1.7 TWh |
| #353 | St Francis Energy Facility | Campbell, MO | 1.7 TWh |
| #354 | Cunningham | Hobbs, NM | 1.7 TWh |
| #355 | Russell City Energy Center | Hayward, CA | 1.7 TWh |
| #356 | Nichols | Amarillo, TX | 1.7 TWh |
| #357 | Houston Chemical Complex Battleground | Houston, TX | 1.7 TWh |
| #358 | Shell Chemical Appalachia LLC | Monaca, PA | 1.7 TWh |
| #359 | Barney M Davis | Corpus Christi, TX | 1.6 TWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Noblesville.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Anderson | Anderson, IN | 92.3 GWh | 12.7 mi |
| Anderson 3 | Anderson, IN | 16.3 GWh | 17.4 mi |
| Anderson 4 | Anderson, IN | 14.5 GWh | 17.8 mi |
| Anderson 5 | Anderson, IN | 5.8 GWh | 17.9 mi |
| Anderson 6 | Anderson, IN | 13.3 GWh | 11.9 mi |
| Duke Building 129 | Indianapolis, IN | 4.4 GWh | 19.4 mi |
| Duke Building 87 | Indianapolis, IN | 3.4 GWh | 20.7 mi |
| Duke Building 98 | Indianapolis, IN | 4.1 GWh | 20.2 mi |
| Georgetown | Indianapolis, IN | 307.0 GWh | 19.7 mi |
| IMPA Anderson Solar Park | Anderson, IN | 7.5 GWh | 12.8 mi |
| IMPA Anderson Solar Park 2 | Anderson, IN | 12.0 GWh | 15.1 mi |
| IMPA Frankton Solar Park | Frankton, IN | 1.1 GWh | 13.3 mi |
| IMPA Pendleton Solar Park | Pendleton, IN | 3.1 GWh | 13 mi |
| IMPA Tipton 2 Solar Park | Tipton, IN | 3.5 GWh | 14.3 mi |
| M. G. Emmett J. Bean Federal Center | Indianapolis, IN | 519.0 MWh | 17 mi |
| Marion Solar LNG | Indianapolis, IN | 1.8 GWh | 19 mi |
| POET Biorefining- Alexandria, LLC | Alexandria, IN | 18.5 GWh | 21.6 mi |
| Sheridan School Corporation Solar | Sheridan, IN | 1.9 GWh | 13.2 mi |
| Tipton Solar Park | Tipton, IN | 8.7 GWh | 13.6 mi |
| Wildcat Wind Farm I, LLC | Elwood, IN | 671.7 GWh | 18.7 mi |