Goodnight
4690 HWY 207, Claude, TX 79019Plant Summary Information
Goodnight is ranked #56 out of 226 wind farms in Texas in terms of total annual net electricity generation.
Goodnight generated 142.3 GWh during the 3-month period between July 2025 to October 2025.
| Plant Name | Goodnight |
|---|---|
| Utility Name | FGE Goodnight I, LLC |
| Location | Armstrong County, TX |
| Initial Operation Date | April 2024 |
| Last Update | Oct 2025 |
| Annual Generation | 749.8 GWh |
| Annual Consumption | 2.8 M MMBtu |
| Ranked #941 out of 12,553 Power Plants Nationwide | |
| Ranked #173 out of 1,366 Wind Power Plants Nationwide | |
| Ranked #172 out of 804 Texas Power Plants | |
| Ranked #56 out of 226 Texas Wind Power Plants | |
| Fuel Types | Wind |
| Previous Operators |
Tri Global Energy, LLC (2013 to 2015) FGE Goodnight, LLC (2016 to 2021) FGE Goodnight I, LLC (2022 to 2024) |
Map of Goodnight
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Goodnight.
Monthly Net Generation for Goodnight
Goodnight Details
| Summary Information | |
|---|---|
| Plant Name | Goodnight (59246) |
| Plant Address | 4690 HWY 207, Claude, TX 79019 |
| Utility | FGE Goodnight I, LLC (65226) |
| Latitude, Longitude | 35.09389, -101.32611 |
| Generation Dates on File | Apr 2024 to Oct 2025 |
| Initial Operation Date | April 2024 |
| Annual Generation | 749.8 GWh |
| Fuel Types | Wind |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | TRE |
| Balancing Authority | Electric Reliability Council of Texas, Inc. (ERCO) |
| NAICS Code | Utilities (22) |
| Sector | IPP Non-CHP (2) |
| Water Source | |
| Ash Impoundment | No |
| Transmission / Distribution Owner | Oncor Electric Delivery Company LLC (44372) TX |
| Grid Voltage | 34.00 kV / 345.00 kV |
| Energy Storage | No |
Generator GOOD1 Details Operating April 2024
| Technology | Onshore Wind Turbine |
|---|---|
| Prime Mover | Wind Turbine, Onshore |
| Ownership | Single Owner |
| RTO ISO LMP Node Designation | ERCOT Panhandle |
| RTO ISO Location Designation For Reporting Wholesale Sales Data | ERCOT Panhandle |
| Nameplate Capacity | 265.5 MW |
| Nameplate Power Factor | 0.98 |
| Summer Capacity | 265.5 MW |
| Winter Capacity | 265.5 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | April 2024 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Wind |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Turbines/Hydrokinetic Buoys | 59 |
| Time From Cold Shutdown To Full Load | 10M |
| Multiple Fuels | No |
| Turbine Details | |
| Number Of Turbines | 59 |
|---|---|
| Predominant Turbine Manufacturer | Vestas |
| Predominant Turbine Model Number | V136-4.2 |
| Design Wind Speed | 18.9 MPH |
| Wind Quality Class | 2 - Medium Wind |
| Turbine Hub Height Feet | 269 |
Goodnight Plant Owners
| Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #163 | Bluestem | Beaver, OK | 763.8 GWh |
| #164 | Armadillo Flats Wind Project, LLC | Enid, OK | 763.7 GWh |
| #165 | West Raymond Wind Farm LLC | Lyford, TX | 763.3 GWh |
| #166 | Canadian Breaks, LLC | Vega, TX | 758.9 GWh |
| #167 | Palo Duro Wind | Perryton, TX | 757.4 GWh |
| #168 | TX Jumbo Road Wind | Hereford, TX | 754.2 GWh |
| #169 | Cimarron Bend Wind Project II, LLC | Minneola, KS | 752.9 GWh |
| #170 | Pattern Gulf Wind | Armstrong, TX | 750.8 GWh |
| #171 | Sweetland Wind Farm, LLC | St. Lawrence, SD | 750.7 GWh |
| #172 | Helena Wind | Pawnee, TX | 750.6 GWh |
| #174 | Red Dirt Wind Project | Hennessy, OK | 748.9 GWh |
| #175 | Red Pine Wind Project | Ivanhoe, MN | 748.1 GWh |
| #176 | Pryor Mountain Wind | Bridger, MT | 746.0 GWh |
| #177 | Trinity Hills | Olney, TX | 744.4 GWh |
| #178 | Blue Summit III Wind | Chilicothe, TX | 738.2 GWh |
| #179 | Haystack Wind Project, LLC | Carroll, NE | 738.2 GWh |
| #180 | Freeborn Wind Farm | Glenville, MN | 736.0 GWh |
| #181 | Goodwell Wind Project LLC | Goodwell, OK | 735.9 GWh |
| #182 | Big Sky Wind LLC | Ohio, IL | 730.9 GWh |
| #183 | Miami Wind Energy Center | Miami, TX | 730.4 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Goodnight.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Astra Wind Farm | Happy, TX | 542.5 GWh | 46.8 mi |
| Black Hawk Station | Borger, TX | 1.3 TWh | 41.6 mi |
| Borger Plant | Borger, TX | 46.6 GWh | 39.9 mi |
| Briscoe Wind Farm | Silverton, TX | 451.1 GWh | 46 mi |
| Colbeck's Corner, LLC | Groom, TX | 789.0 GWh | 13.6 mi |
| Engineered Carbons Borger Cogen | Borger, TX | 80.2 GWh | 40 mi |
| Grandview Wind Farm, LLC | Panhandle, TX | 835.0 GWh | 10 mi |
| Harrington | Amarillo, TX | 2.1 TWh | 27.6 mi |
| Hecate Energy Frye Solar LLC | Kress, TX | 1.3 TWh | 49.9 mi |
| Llano Estacado Wind Ranch | White Deer, TX | 94.8 GWh | 26.2 mi |
| Majestic 1 Wind Farm | Panhandle, TX | 365.1 GWh | 23.6 mi |
| Majestic II Wind | Panhandle, TX | 157.4 GWh | 24.7 mi |
| Nichols | Amarillo, TX | 1.7 TWh | 27.1 mi |
| Pantex | Amarillo, TX | 10.2 GWh | 19.6 mi |
| Pattern Panhandle Wind 2 LLC | Panhandle, TX | 614.0 GWh | 24.2 mi |
| Pattern Panhandle Wind LLC | Panhandle, TX | 541.3 GWh | 23.4 mi |
| Route 66 Wind Plant | Panhandle, TX | 608.2 GWh | 9.8 mi |
| Salt Fork Wind Project, LLC | Clarendon, TX | 679.6 GWh | 22.9 mi |
| Spinning Spur Wind LLC | Vegas, TX | 334.2 GWh | 50.5 mi |
| UL Advanced Wind Turbine Test Facility | Canyon, TX | 8.8 GWh | 27.4 mi |