Golden Plains
2209 460th St, Buffalo Center, IA 50424Plant Summary Information
Golden Plains is ranked #34 out of 280 power plants in Iowa in terms of total annual net electricity generation.
Golden Plains generated 196.5 GWh during the 3-month period between August 2025 to November 2025.
| Plant Name | Golden Plains |
|---|---|
| Utility Name | Interstate Power and Light Co |
| Location | Winnebago County, IA |
| Initial Operation Date | March 2020 |
| Last Update | Nov 2025 |
| Annual Generation | 720.0 GWh |
| Annual Consumption | 2.7 M MMBtu |
| Ranked #975 out of 12,574 Power Plants Nationwide | |
| Ranked #189 out of 1,370 Wind Power Plants Nationwide | |
| Ranked #34 out of 280 Iowa Power Plants | |
| Ranked #22 out of 124 Iowa Wind Power Plants | |
| Fuel Types | Wind |
Map of Golden Plains
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Golden Plains.
Monthly Net Generation for Golden Plains
Golden Plains Details
| Summary Information | |
|---|---|
| Plant Name | Golden Plains (62081) |
| Plant Address | 2209 460th St, Buffalo Center, IA 50424 |
| Utility | Interstate Power and Light Co (9417) |
| Latitude, Longitude | 43.43064, -94.01641 |
| Generation Dates on File | Mar 2020 to Nov 2025 |
| Initial Operation Date | March 2020 |
| Annual Generation | 720.0 GWh |
| Fuel Types | Wind |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Regulated |
| NERC Region | MRO |
| Balancing Authority | Midcontinent Independent Transmission System Operator, Inc.. (MISO) |
| NAICS Code | Utilities (22) |
| Sector | Electric Utility (1) |
| Water Source | |
| Ash Impoundment | |
| Transmission / Distribution Owner | ITC Midwest LLC (56161) |
| Grid Voltage | 345.00 kV |
| Energy Storage | No |
Generator 1 Details Operating March 2020
| Technology | Onshore Wind Turbine |
|---|---|
| Prime Mover | Wind Turbine, Onshore |
| Ownership | Single Owner |
| RTO ISO LMP Node Designation | ALTW.GOLDENPLN |
| RTO ISO Location Designation For Reporting Wholesale Sales Data | ALTW.GOLDENPLN |
| Nameplate Capacity | 199.8 MW |
| Nameplate Power Factor | 0.95 |
| Summer Capacity | 199.8 MW |
| Winter Capacity | 199.8 MW |
| Minimum Load | 0.1 MW |
| Uprate/Derate Completed | No |
|---|---|
| Status | Operating |
| First Operation Date | March 2020 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Wind |
| Solid Fuel Gasification | No |
| Turbines/Hydrokinetic Buoys | 82 |
| Other Planned Modifications | No |
| Multiple Fuels | No |
| Turbine Details | |
| Number Of Turbines | 82 |
|---|---|
| Predominant Turbine Manufacturer | GE |
| Predominant Turbine Model Number | 2.5-127 |
| Design Wind Speed | 17 MPH |
| Wind Quality Class | 2 - Medium Wind |
| Turbine Hub Height Feet | 295 |
Golden Plains Plant Owners
| Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #179 | Upstream Wind Energy LLC | Neligh, NE | 741.0 GWh |
| #180 | Armadillo Flats Wind Project, LLC | Enid, OK | 734.9 GWh |
| #181 | Pryor Mountain Wind | Bridger, MT | 732.3 GWh |
| #182 | Big Sky Wind LLC | Ohio, IL | 730.9 GWh |
| #183 | Kingman Wind | Cunningham, KS | 729.2 GWh |
| #184 | Goodnight | Claude, TX | 726.7 GWh |
| #185 | Bright Stalk Wind Farm I | Chenoa, IL | 723.8 GWh |
| #186 | Whispering Willow North | Latimer, IA | 723.6 GWh |
| #187 | Goodwell Wind Project LLC | Goodwell, OK | 721.7 GWh |
| #188 | Cross Winds Energy Park | Unionville, MI | 720.9 GWh |
| #190 | Mammoth Plains | Oakwood, OK | 719.9 GWh |
| #191 | Ida Grove II | Ida Grove, IA | 715.5 GWh |
| #192 | Ekola Flats | Hanna, WY | 709.9 GWh |
| #193 | Turtle Creek Wind Farm LLC | St. Ansgar, IA | 708.2 GWh |
| #194 | Panther Creek Wind Farm Three | Big Spring, TX | 706.2 GWh |
| #195 | FPL Energy Crystal Lake Wind II LLC | Britt, IA | 705.9 GWh |
| #196 | Amadeus Wind Farm | Rotan, TX | 705.2 GWh |
| #197 | TX Jumbo Road Wind | Hereford, TX | 704.5 GWh |
| #198 | East Fork Wind Project, LLC | Colby, KS | 702.6 GWh |
| #199 | Diamond Spring, LLC | Sulphur, OK | 701.5 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Golden Plains.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Algona | Algona, IA | 507.0 MWh | 27.1 mi |
| Bancroft | Bancroft, IA | 96.0 MWh | 13.9 mi |
| Big Blue | Blue Earth, MN | 70.0 GWh | 15.3 mi |
| Blue Breezes II LLC | Blue Earth, MN | 2.4 GWh | 17.1 mi |
| Blue Breezes LLC | Blue Earth, MN | 2.4 GWh | 17 mi |
| Blue Earth | Blue Earth, MN | 96.0 MWh | 14.9 mi |
| Crystal Lake 3 LLC | Britt, IA | 235.9 GWh | 10.2 mi |
| Fairmont (MN) | Fairmont, MN | 6.1 GWh | 27.4 mi |
| Fairmont Wind | Fairmont, MN | 14.6 GWh | 23.8 mi |
| Forest City Light Plant | Forest City, IA | 225.0 MWh | 22.4 mi |
| Forest City Solar | Forest City, IA | 5.1 GWh | 22.2 mi |
| FPL Energy Crystal Lake Wind II LLC | Britt, IA | 705.9 GWh | 15.4 mi |
| FPL Energy Crystal Lake Wind LLC | Britt, IA | 571.6 GWh | 17.7 mi |
| Iowa Distributed Wind Generation Project | Algona, IA | 4.6 GWh | 28.1 mi |
| Lake Mills | Lake Mills, IA | 38.0 MWh | 24.3 mi |
| Lake Mills Gas Recovery | Lake Mills, IA | 24.8 GWh | 23.2 mi |
| Lakota Wind Wind Farm | Lakota, IA | 34.7 GWh | 7.3 mi |
| Ledyard Windpower, LLC | Lakota, IA | 605.2 GWh | 4.5 mi |
| Wells IC | Wells, MN | 180.0 MWh | 26.2 mi |
| Winnebago Wind Power Project | Forest City, IA | 59.3 GWh | 14.7 mi |