Fresno Hoover High School Hybrid
5550 N First Street, Fresno, CA 93710Plant Summary Information
Fresno Hoover High School Hybrid is ranked #709 out of 885 solar farms in California in terms of total annual net electricity generation.
Fresno Hoover High School Hybrid generated 278.0 MWh during the 3-month period between September 2024 to December 2024.
| Plant Name | Fresno Hoover High School Hybrid |
|---|---|
| Utility Name | Forefront Power, LLC |
| Location | Fresno County, CA |
| Initial Operation Date | March 2020 |
| Last Update | Dec 2024 |
| Annual Generation | 2.0 GWh |
| Annual Consumption | 7.2 k MMBtu |
| Ranked #10,850 out of 13,081 Power Plants Nationwide | |
| Ranked #5,712 out of 7,015 Solar Power Plants Nationwide | |
| Ranked #1,388 out of 1,606 California Power Plants | |
| Ranked #709 out of 885 California Solar Power Plants | |
| Fuel Types | Solar |
Map of Fresno Hoover High School Hybrid
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Fresno Hoover High School Hybrid.
Monthly Net Generation for Fresno Hoover High School Hybrid
Monthly Plant Fuel Consumption for Fresno Hoover High School Hybrid
Fresno Hoover High School Hybrid Details
| Summary Information | |
|---|---|
| Plant Name | Fresno Hoover High School Hybrid (63421) |
| Plant Address | 5550 N First Street, Fresno, CA 93710 |
| Utility | Forefront Power, LLC (62856) |
| Latitude, Longitude | 36.81782, -119.77071 |
| Generation Dates on File | Mar 2020 to Dec 2024 |
| Initial Operation Date | March 2020 |
| Annual Generation | 2.0 GWh |
| Fuel Types | Solar |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | Yes |
| FERC Small Power Producer Docket Number | 22-388-000 |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | WECC |
| Balancing Authority | California Independent System Operator (CISO) |
| NAICS Code | Utilities (22) |
| Sector | IPP Non-CHP (2) |
| Water Source | |
| Ash Impoundment | No |
| Transmission / Distribution Owner | Pacific Gas & Electric Co. (14328) CA |
| Grid Voltage | 21.00 kV |
| Energy Storage | Yes |
Generator 291 Details Operating March 2020
| Technology | Solar Photovoltaic |
|---|---|
| Prime Mover | Photovoltaic |
| Ownership | Single Owner |
| Nameplate Capacity | 1.2 MW |
| Summer Capacity | 1.2 MW |
| Winter Capacity | 1.2 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | March 2020 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Solar |
| Time From Cold Shutdown To Full Load | 10M |
| Multiple Fuels | No |
| Solar Details | |
| Single Axis Tracking | Yes |
|---|---|
| East West Fixed Tilt | Yes |
| Azimuth Angle | 270 |
| Tilt Angle | 7 |
| DC Net Capacity | 1.4 MW |
| Crystalline Silicon | Yes |
| Net Metering Agreement | Yes |
| Net Metering DC Capacity | 1.4 MW |
| Virtual Net Metering Agreement | No |
Generator BA291 Details Operating March 2020
| Technology | Batteries |
|---|---|
| Prime Mover | Battery |
| Ownership | Single Owner |
| Nameplate Capacity | 0.2 MW |
| Summer Capacity | 0.2 MW |
| Winter Capacity | 0.2 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | March 2020 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Electricity used for energy storage |
| Time From Cold Shutdown To Full Load | 10M |
| Multiple Fuels | No |
| Energy Storage Details | |
| Nameplate Energy Capacity MWH | 0.2 |
|---|---|
| Maximum Charge Rate | 0.2 MW |
| Maximum Discharge Rate | 0.2 MW |
| Storage Technology | LIB |
| Nameplate Reactive Power Rating | 0.2 |
| Storage Enclosure Type | CS |
| System Peak Shaving | P |
| Excess Wind And Solar Generation | Yes |
| Ac Coupled | Yes |
| Direct Support Of Another Unit | Yes |
| Direct Support Plant Id | 63421 |
| Direct Support Gen Id | 291 |
| Support T D Asset | No |
Fresno Hoover High School Hybrid Plant Owners
| Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #5702 | Grafton Solar | Grafton, MA | 2.0 GWh |
| #5703 | USS Horne North Solar LLC CSG | Felton, MN | 2.0 GWh |
| #5704 | Allium Community Solar Garden, LLC | Paynesville, MN | 2.0 GWh |
| #5705 | Bethlehem - East | Selkirk, NY | 2.0 GWh |
| #5706 | Lower Cape May HS | Cape May, NJ | 2.0 GWh |
| #5707 | Jewish Community Center PV | Scottsdale, AZ | 2.0 GWh |
| #5708 | 12 Applegate Solar LLC | Robbinsville, NJ | 2.0 GWh |
| #5709 | St. Albans SPEED Project | St. Albans, VT | 2.0 GWh |
| #5710 | Bainbridge Solar | Bainbridge, GA | 2.0 GWh |
| #5711 | Holtsville Solar Project | Holtsville, NY | 2.0 GWh |
| #5713 | Bed Bath & Beyond DC Port Reading NJ | Port Reading, NJ | 2.0 GWh |
| #5714 | ER Bison Solar CSG | Lewisburg, PA | 2.0 GWh |
| #5715 | Emerald Gardens PKI, LLC | Shelton, CT | 2.0 GWh |
| #5716 | Cenergy - Kiger | Embden, ME | 2.0 GWh |
| #5717 | Lockheed Martin Solar | Orlando, FL | 2.1 GWh |
| #5718 | THD Baltimore DC - 5830 Project Tiger | Edgemere, MD | 2.0 GWh |
| #5719 | USS Catfish Solar LLC | Franklin, MN | 2.0 GWh |
| #5720 | Siems Solar Project CSG | Mazeppa, MN | 2.0 GWh |
| #5721 | Johnson CSG 2 | Lindstrom, MN | 2.0 GWh |
| #5722 | Woburn | Woburn, MA | 2.0 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Fresno Hoover High School Hybrid.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Borden Solar Farm | Madera, CA | 98.8 GWh | 13.5 mi |
| CA - Fresno County - Juvenile Hall | Fresno, CA | 552.0 MWh | 11.1 mi |
| Clovis East High School | Clovis, CA | 1.3 GWh | 7.3 mi |
| Clovis High School | Clovis, CA | 1.6 GWh | 4.9 mi |
| Clovis North High School | Fresno, CA | 1.5 GWh | 5.3 mi |
| CSU Fresno Solar Project | Fresno, CA | 1.3 GWh | 1.7 mi |
| Fresno Bullard High School Hybrid | Fresno, CA | 2.1 GWh | 2.2 mi |
| Fresno Community Solar | Fresno, CA | 16.9 GWh | 10.5 mi |
| Fresno Sunnyside High School Hybrid | Fresno, CA | 2.5 GWh | 6.5 mi |
| Friant Hydro Facility | Friant, CA | 73.5 GWh | 13 mi |
| Gap Pacific Distribution Center | Fresno, CA | 5.4 GWh | 4.3 mi |
| JD Foods - JD Foods | Fresno, CA | 2.5 GWh | 8.1 mi |
| La Joya Del Sol | Fresno, CA | 806.0 MWh | 9.7 mi |
| Malaga Power LLC | Fresno, CA | 4.2 GWh | 9 mi |
| National Raisin | Fowler, CA | 4.6 GWh | 14.4 mi |
| OK Produce Fresno Carport | Fresno, CA | 3.3 GWh | 6.5 mi |
| Pacific Ethanol Madera Solar Array | Madera, CA | 4.0 GWh | 13 mi |
| Saint Agnes Medical Center | Fresno, CA | 32.0 GWh | 1.2 mi |
| SCCCD - Clovis Community College | Fresno, CA | 2.0 GWh | 5.1 mi |
| SCCCD - Fresno Community College | Fresno, CA | 2.8 GWh | 3.9 mi |