Eastover Solar
1590 Vanboklen Road, Eastover, SC 29044Plant Summary Information
Eastover Solar is ranked #39 out of 203 power plants in South Carolina in terms of total annual net electricity generation.
Eastover Solar generated 43.3 GWh during the 3-month period between May 2026 to August 2026.
| Plant Name | Eastover Solar |
|---|---|
| Utility Name | Eastover Solar, LLC |
| Location | Richland County, SC |
| Initial Operation Date | March 2023 |
| Last Update | Aug 2026 |
| Annual Generation | 141.2 GWh |
| Annual Consumption | 510.7 k MMBtu |
| Ranked #3,137 out of 13,301 Power Plants Nationwide | |
| Ranked #777 out of 7,209 Solar Power Plants Nationwide | |
| Ranked #39 out of 203 South Carolina Power Plants | |
| Ranked #12 out of 125 South Carolina Solar Power Plants | |
| Fuel Types | Solar |
Map of Eastover Solar
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Eastover Solar.
Monthly Net Generation for Eastover Solar
Monthly Plant Fuel Consumption for Eastover Solar
Eastover Solar Details
| Summary Information | |
|---|---|
| Plant Name | Eastover Solar (66717) |
| Plant Address | 1590 Vanboklen Road, Eastover, SC 29044 |
| Utility | Eastover Solar, LLC (65730) |
| Latitude, Longitude | 33.91854, -80.6467 |
| Generation Dates on File | Mar 2023 to Aug 2026 |
| Initial Operation Date | March 2023 |
| Annual Generation | 141.2 GWh |
| Fuel Types | Solar |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | Yes |
| FERC Exempt Wholesale Generator Docket Number | 19-752-005, 19-752-006 |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | SERC |
| Balancing Authority | Duke Energy Progress East (CPLE) |
| NAICS Code | Utilities (22) |
| Sector | IPP Non-CHP (2) |
| Water Source | |
| Ash Impoundment | No |
| Transmission / Distribution Owner | Duke Energy Progress - (NC) (3046) SC |
| Grid Voltage | 230.00 kV |
| Energy Storage | Yes |
Generator ESTOR Details Operating March 2023
| Technology | Solar Photovoltaic |
|---|---|
| Prime Mover | Photovoltaic |
| Ownership | Single Owner |
| Nameplate Capacity | 73.6 MW |
| Summer Capacity | 73.6 MW |
| Winter Capacity | 73.6 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | March 2023 |
|---|---|
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Solar |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Multiple Fuels | No |
| Solar Details | |
| Single Axis Tracking | Yes |
|---|---|
| Bifacial | No |
| Azimuth Angle | 180 |
| DC Net Capacity | 103 MW |
| Crystalline Silicon | Yes |
| Net Metering Agreement | No |
| Virtual Net Metering Agreement | No |
Generator STOR Details Operating March 2023
| Technology | Batteries |
|---|---|
| Prime Mover | Battery |
| Ownership | Single Owner |
| Nameplate Capacity | 18 MW |
| Summer Capacity | 18 MW |
| Winter Capacity | 18 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | March 2023 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Electricity used for energy storage |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | No |
| Energy Storage Details | |
| Nameplate Energy Capacity MWH | 72 |
|---|---|
| Maximum Charge Rate | 18 MW |
| Maximum Discharge Rate | 18 MW |
| Storage Technology | OTH |
| Nameplate Reactive Power Rating | 53.5 |
| Storage Enclosure Type | CS |
| Load Following | P |
| Excess Wind And Solar Generation | Yes |
| DC Coupled | Yes |
| Direct Support Of Another Unit | Yes |
| Direct Support Plant Id | 66717 |
| Direct Support Gen Id | ESTOR |
| Support T D Asset | No |
Eastover Solar Plant Owners
| Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #767 | Polaris Solar Park | Ashley, MI | 143.4 GWh |
| #768 | Mulligan Solar, LLC | Broadwell, IL | 143.3 GWh |
| #769 | Magnolia Solar | Mulberry, FL | 143.2 GWh |
| #770 | Pink Trial Solar Energy Center | Port St. Lucie, FL | 142.9 GWh |
| #771 | East Atmore Solar | Flomaton, AL | 142.9 GWh |
| #772 | Canoe | Holt, FL | 136.3 GWh |
| #773 | Bluefield Preserve Solar | Okeechobee, FL | 142.4 GWh |
| #774 | Blackwater River Solar Energy Center | Milton, FL | 136.9 GWh |
| #775 | FPL Flowers Creek Solar Energy Center | Altha, FL | 141.9 GWh |
| #776 | Millican Solar Energy LLC | Prineville, OR | 141.6 GWh |
| #778 | Wilmot Energy Center II | Sahuarita, AZ | 133.0 GWh |
| #779 | Fish Creek Solar Park | Greenville, MI | 141.0 GWh |
| #780 | Miami Dade Solar Energy Center | Miami, FL | 141.0 GWh |
| #781 | Magnolia Springs Solar Center | Green Cove Springs, FL | 140.8 GWh |
| #782 | Palmer Solar | Fountain, CO | 140.7 GWh |
| #783 | Tower Solar, LLC | Boardman, OR | 140.4 GWh |
| #784 | Mesquite Solar 4, LLC | Tonopah, AZ | 133.6 GWh |
| #785 | White Oak Solar, LLC | Waynesboro, GA | 139.8 GWh |
| #786 | Alton Post Office Solar | Alton, VA | 139.7 GWh |
| #787 | Wimauma Solar and Battery Storage | Wimauma, FL | 136.2 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Eastover Solar.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Abbot Solar | Manning, SC | 3.8 GWh | 28.6 mi |
| Bloom Solar | Summerton, SC | 3.8 GWh | 27.8 mi |
| Bond Solar | Summerton, SC | 3.5 GWh | 26.4 mi |
| Cameron Solar | Cameron, SC | 38.8 GWh | 24.1 mi |
| Cameron Solar II | Cameron, SC | 7.3 GWh | 24.5 mi |
| Coit GT | Columbia, SC | 2.0 GWh | 23 mi |
| Columbia Energy Center (SC) | Gaston, SC | 2.8 TWh | 21.5 mi |
| Gaston II | Swansea, SC | 11.3 GWh | 28.3 mi |
| Gaston Solar I - SC | Gaston, SC | 16.5 GWh | 28.4 mi |
| Gunsight Solar, LLC | Swansea, SC | 173.1 GWh | 26.4 mi |
| Jamison Solar Farm | Orangeburg, SC | 1.9 GWh | 26.2 mi |
| Lee County Landfill | Bishopville, SC | 11.8 GWh | 28.3 mi |
| Lone Star Solar | Cameron, SC | 177.5 GWh | 18.6 mi |
| Midlands | St. Matthews, SC | 156.1 GWh | 25.2 mi |
| Otarre Solar Park | Cayce, SC | 2.8 GWh | 23.2 mi |
| Richland County Landfill | Lugoff, SC | 5.1 GWh | 15.2 mi |
| St. Matthews Solar | Matthews, SC | 16.6 GWh | 17.3 mi |
| Sylvamo Corporation Eastover Facility | Eastover, SC | 542.4 GWh | 2.2 mi |
| Wateree | Eastover, SC | 2.5 TWh | 6.5 mi |
| Wateree Hydro | Ridgeway, SC | 137.3 GWh | 29 mi |