Dover Solar and Battery Storage
1255 Sydney Washer Rd, Dover, FL 33527Plant Summary Information
Dover Solar and Battery Storage is ranked #177 out of 225 solar farms in Florida in terms of total annual net electricity generation.
Dover Solar and Battery Storage generated 14.4 GWh during the 3-month period between February 2026 to May 2026.
| Plant Name | Dover Solar and Battery Storage |
|---|---|
| Utility Name | Tampa Electric Co |
| Location | Hillsborough County, FL |
| Initial Operation Date | December 2023 |
| Last Update | May 2026 |
| Annual Generation | 49.2 GWh |
| Annual Consumption | 188.6 k MMBtu |
| Ranked #4,227 out of 13,081 Power Plants Nationwide | |
| Ranked #1,119 out of 7,015 Solar Power Plants Nationwide | |
| Ranked #257 out of 332 Florida Power Plants | |
| Ranked #177 out of 225 Florida Solar Power Plants | |
| Fuel Types | Solar |
Map of Dover Solar and Battery Storage
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Dover Solar and Battery Storage.
Monthly Net Generation for Dover Solar and Battery Storage
Monthly Plant Fuel Consumption for Dover Solar and Battery Storage
Dover Solar and Battery Storage Details
| Summary Information | |
|---|---|
| Plant Name | Dover Solar and Battery Storage (66129) |
| Plant Address | 1255 Sydney Washer Rd, Dover, FL 33527 |
| Utility | Tampa Electric Co (18454) |
| Latitude, Longitude | 27.95587, -82.20138 |
| Generation Dates on File | Dec 2023 to May 2026 |
| Initial Operation Date | December 2023 |
| Annual Generation | 49.2 GWh |
| Fuel Types | Solar |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Regulated |
| NERC Region | SERC |
| Balancing Authority | Tampa Electric Company (TEC) |
| NAICS Code | Utilities (22) |
| Sector | Electric Utility (1) |
| Water Source | |
| Ash Impoundment | |
| Transmission / Distribution Owner | Tampa Electric Co (18454) FL |
| Grid Voltage | 69.00 kV |
| Energy Storage | Yes |
Generator 1 Details Operating December 2023
| Technology | Solar Photovoltaic |
|---|---|
| Prime Mover | Photovoltaic |
| Ownership | Single Owner |
| Nameplate Capacity | 25 MW |
| Summer Capacity | 25 MW |
| Winter Capacity | 25 MW |
| Uprate/Derate Completed | No |
|---|---|
| Status | Operating |
| First Operation Date | December 2023 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Solar |
| Solar Details | |
| Single Axis Tracking | Yes |
|---|---|
| Azimuth Angle | 180 |
| Tilt Angle | 52 |
| DC Net Capacity | 32 MW |
| Thin Film CDTE | Yes |
| Net Metering Agreement | No |
| Virtual Net Metering Agreement | No |
Generator BESS1 Details Operating December 2024
| Technology | Batteries |
|---|---|
| Prime Mover | Battery |
| Ownership | Single Owner |
| Nameplate Capacity | 15 MW |
| Summer Capacity | 15 MW |
| Winter Capacity | 15 MW |
| Uprate/Derate Completed | No |
|---|---|
| Status | Operating |
| First Operation Date | December 2024 |
| Sector Name | Electric Utility (1) |
| Energy Source | Electricity used for energy storage |
| Energy Storage Details | |
| Nameplate Energy Capacity MWH | 30 |
|---|---|
| Maximum Charge Rate | 15 MW |
| Maximum Discharge Rate | 15 MW |
| Storage Technology | LIB |
| Nameplate Reactive Power Rating | 4.9 |
| Storage Enclosure Type | CS |
| Arbitrage | Yes |
| Frequency Regulation | Yes |
| Load Following | Yes |
| Ramping Spinning Reserve | Yes |
| Co Located Renewable Firming | Yes |
| System Peak Shaving | P |
| Voltage Or Reactive Power Support | Yes |
| Excess Wind And Solar Generation | Yes |
| Ac Coupled | Yes |
| Direct Support Of Another Unit | No |
| Support T D Asset | No |
Dover Solar and Battery Storage Plant Owners
| Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #1109 | CED Ducor 2 | Ducor, CA | 51.6 GWh |
| #1110 | Fort Gordon Solar Facility | Fort Gordon, GA | 51.4 GWh |
| #1111 | Cascade Solar | Joshua Tree, CA | 51.4 GWh |
| #1112 | RE Rosamond One LLC | Rosamond, CA | 51.2 GWh |
| #1113 | RE Gaskell West 3 LLC | Rosamond, CA | 50.8 GWh |
| #1114 | Pumpjack Solar I | McKittrick, CA | 50.6 GWh |
| #1115 | RE Kansas South LLC | Lemoore, CA | 50.5 GWh |
| #1116 | Maricopa West Solar PV, LLC | Taft, CA | 50.3 GWh |
| #1117 | Simon Solar Farm LLC | Social Circle, GA | 50.2 GWh |
| #1118 | Marion County Solar Project | Marion, OH | 50.2 GWh |
| #1120 | Paulsell | Crows Landing, CA | 47.5 GWh |
| #1121 | Antelope Big Sky Ranch | Lancaster, CA | 49.9 GWh |
| #1122 | Midpoint Solar, LLC | Blum, TX | 49.6 GWh |
| #1123 | St. James Solar (LA) | Vacherie, LA | 49.6 GWh |
| #1124 | Picture Rocks Solar, LLC | Marana, AZ | 49.6 GWh |
| #1125 | Alamo Solar | Oro Grande, CA | 49.3 GWh |
| #1126 | Vega Solar | Los Banos, CA | 49.3 GWh |
| #1127 | Oro Loma | Oro Loma, CA | 49.2 GWh |
| #1128 | Almond | Lemoore, CA | 49.2 GWh |
| #1129 | White River Solar 2 | Alpaugh, CA | 49.2 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Dover Solar and Battery Storage.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Balm Solar | Wimauma, FL | 135.0 GWh | 13.5 mi |
| Big Bend 1 Solar and Battery Storage | Apollo Beach, FL | 18.1 GWh | 16.3 mi |
| Big Bend Floating Solar I | Gibsonton, FL | 1.2 GWh | 16.6 mi |
| Bonnie Mine Solar | Bartow, FL | 66.5 GWh | 13.8 mi |
| English Creek Solar | Plant City, FL | 53.3 GWh | 8.2 mi |
| Goldfinch | Lakeland, FL | 4.8 GWh | 9.9 mi |
| H L Culbreath Bayside Power Station | Tampa, FL | 7.0 TWh | 13.9 mi |
| Hillsborough County Resource Recovery | Tampa, FL | 217.0 GWh | 8.5 mi |
| Juniper Solar (FL) | Zephyrhills, FL | 143.9 GWh | 15.8 mi |
| Lakeland Electric Co. (FL) - Airport II | Lakeland, FL | 2.2 GWh | 9.7 mi |
| Lakeland Electric Co. (FL)-Airport 1 | Lakeland, FL | 2.3 GWh | 9.7 mi |
| Laurel Oaks Solar | Plant City, FL | 122.0 GWh | 8.4 mi |
| Lithia Solar | Lithia, FL | 141.1 GWh | 14.2 mi |
| LKL BLBD, LLC | Lakeland, FL | 9.8 GWh | 13.6 mi |
| Magnolia Solar | Mulberry, FL | 143.3 GWh | 9.7 mi |
| McKay Bay Facility | Tampa, FL | 86.2 GWh | 13.4 mi |
| Mosaic Co Tampa Facility | Riverview, FL | 69.1 GWh | 13.3 mi |
| Mosaic New Wales Operations | Mulberry, FL | 356.3 GWh | 12.4 mi |
| Wimauma Solar and Battery Storage | Wimauma, FL | 129.7 GWh | 16 mi |
| Winston | Lakeland, FL | 497.0 MWh | 12.3 mi |