Bronco Plains Wind II, LLC
TBD, Kit Carson, CO 80834Plant Summary Information
Bronco Plains Wind II, LLC is ranked #17 out of 277 power plants in Colorado in terms of total annual net electricity generation.
Bronco Plains Wind II, LLC generated 209.4 GWh during the 3-month period between December 2025 to March 2026.
| Plant Name | Bronco Plains Wind II, LLC |
|---|---|
| Utility Name | Bronco Plains Wind II, LLC |
| Location | Kit Carson County, CO |
| Initial Operation Date | December 2023 |
| Last Update | Mar 2026 |
| Annual Generation | 753.5 GWh |
| Annual Consumption | 2.6 M MMBtu |
| Ranked #945 out of 12,332 Power Plants Nationwide | |
| Ranked #176 out of 1,358 Wind Power Plants Nationwide | |
| Ranked #17 out of 277 Colorado Power Plants | |
| Ranked #6 out of 33 Colorado Wind Power Plants | |
| Fuel Types | Wind |
Map of Bronco Plains Wind II, LLC
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Bronco Plains Wind II, LLC.
Monthly Net Generation for Bronco Plains Wind II, LLC
Monthly Plant Fuel Consumption for Bronco Plains Wind II, LLC
Bronco Plains Wind II, LLC Details
| Summary Information | |
|---|---|
| Plant Name | Bronco Plains Wind II, LLC (66014) |
| Plant Address | TBD, Kit Carson, CO 80834 |
| Utility | Bronco Plains Wind II, LLC (65166) |
| Latitude, Longitude | 39.184, -102.97 |
| Generation Dates on File | Dec 2023 to Mar 2026 |
| Initial Operation Date | December 2023 |
| Annual Generation | 753.5 GWh |
| Fuel Types | Wind |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | WECC |
| Balancing Authority | Public Service Company of Colorado (PSCO) |
| NAICS Code | Utilities (22) |
| Sector | IPP Non-CHP (2) |
| Water Source | |
| Ash Impoundment | No |
| Transmission / Distribution Owner | Public Service Co of Colorado (15466) CO |
| Grid Voltage | 345.00 kV |
| Energy Storage | No |
Generator WBOPT Details Operating December 2023
| Technology | Onshore Wind Turbine |
|---|---|
| Prime Mover | Wind Turbine, Onshore |
| Ownership | Single Owner |
| Nameplate Capacity | 200 MW |
| Summer Capacity | 199 MW |
| Winter Capacity | 199 MW |
| Minimum Load | 2.3 MW |
| Uprate/Derate Completed | No |
|---|---|
| Status | Operating |
| First Operation Date | December 2023 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Wind |
| Turbines/Hydrokinetic Buoys | 72 |
| Turbine Details | |
| Number Of Turbines | 72 |
|---|---|
| Predominant Turbine Manufacturer | GE |
| Predominant Turbine Model Number | 2.82-127 |
| Design Wind Speed | 12 MPH |
| Wind Quality Class | 1 - High Wind |
| Turbine Hub Height Feet | 89 |
Bronco Plains Wind II, LLC Plant Owners
| Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #166 | Burke Wind, LLC | Bowbells, ND | 769.2 GWh |
| #167 | Plymouth Wind | Remsen, IA | 768.9 GWh |
| #168 | Buffalo Dunes Wind Project | Satanta, KS | 767.9 GWh |
| #169 | Ekola Flats | Hanna, WY | 765.2 GWh |
| #170 | Red Pine Wind Project | Ivanhoe, MN | 762.8 GWh |
| #171 | Cimarron Bend Wind Project II, LLC | Minneola, KS | 762.1 GWh |
| #172 | Crocker Wind Farm | Conde, SD | 762.0 GWh |
| #173 | Helena Wind | Pawnee, TX | 761.1 GWh |
| #174 | Kingman Wind | Cunningham, KS | 759.0 GWh |
| #175 | Blue Summit III Wind | Chilicothe, TX | 757.5 GWh |
| #177 | Walnut Ridge Wind Farm | Sheffield, IL | 753.1 GWh |
| #178 | Golden Plains | Buffalo Center, IA | 750.4 GWh |
| #179 | Freeborn Wind Farm | Glenville, MN | 748.7 GWh |
| #180 | Cimarron Bend Wind Project I, LLC | Minneola, KS | 748.4 GWh |
| #181 | Sweetland Wind Farm, LLC | St. Lawrence, SD | 746.5 GWh |
| #182 | Solano Wind | Rio Vista, CA | 741.2 GWh |
| #183 | Great Pathfinder Wind | Stratford, IA | 738.6 GWh |
| #184 | Diversion Wind Energy LLC | Seymour, TX | 738.1 GWh |
| #185 | Pryor Mountain Wind | Bridger, MT | 737.3 GWh |
| #186 | Rio Bravo Windpower, LLC | Roma, TX | 736.5 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Bronco Plains Wind II, LLC.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Bronco Plains Wind, LLC | Flagler, CO | 1.1 TWh | 7.2 mi |
| Brush Generation Facility | Brush, CO | 153.7 GWh | 81.1 mi |
| Burlington (CO) | Burlington, CO | 3.3 GWh | 40.7 mi |
| Carousel Wind Farm LLC | Burlington, CO | 613.9 GWh | 43.9 mi |
| Cedar Point Wind | Limon, CO | 688.0 GWh | 41.3 mi |
| Cheyenne Ridge Wind Farm | Cheyenne Wells, CO | 1.7 TWh | 42.3 mi |
| Crossing Trails Wind Power Project LLC. | Seibert, CO | 398.7 GWh | 12.4 mi |
| Golden West Power Partners LLC | Calhan, CO | 825.5 GWh | 68.8 mi |
| Grazing Yak Solar | Calhan, CO | 79.8 GWh | 70.3 mi |
| Kit Carson Windpower | Burlington, CO | 168.5 GWh | 34.7 mi |
| Limon Generating Station | Limon, CO | 216.3 GWh | 39.1 mi |
| Limon III Wind LLC | Limon, CO | 680.0 GWh | 29.4 mi |
| Limon Wind I | Limon, CO | 581.9 GWh | 35 mi |
| Limon Wind II | Limon, CO | 511.1 GWh | 34.5 mi |
| Manchief Electric Generating Station | Brush, CO | 260.4 GWh | 80.9 mi |
| NSE Camber BH CSG 2, LLC | Ordway, CO | 3.9 GWh | 79.3 mi |
| Pawnee | Brush, CO | 1.5 TWh | 81 mi |
| Rush Creek Wind | Matheson, CO | 2.2 TWh | 46.9 mi |
| St Francis | St Francis, KS | 19.6 MWh | 74 mi |
| Titan Solar | Deer Trail, CO | 94.9 GWh | 65.6 mi |