Kit Carson Windpower
22330 County Road 44, Burlington, CO 80807Plant Summary Information
Kit Carson Windpower is ranked #25 out of 34 wind farms in Colorado in terms of total annual net electricity generation.
Kit Carson Windpower generated 45.4 GWh during the 3-month period between September 2024 to December 2024.
| Plant Name | Kit Carson Windpower |
|---|---|
| Utility Name | Duke Energy Renewables Services |
| Location | Kit Carson County, CO |
| Initial Operation Date | November 2010 |
| Last Update | Dec 2024 |
| Annual Generation | 168.5 GWh |
| Annual Consumption | 630.1 k MMBtu |
| Ranked #2,696 out of 12,539 Power Plants Nationwide | |
| Ranked #788 out of 1,362 Wind Power Plants Nationwide | |
| Ranked #56 out of 282 Colorado Power Plants | |
| Ranked #25 out of 34 Colorado Wind Power Plants | |
| Fuel Types | Wind |
| Previous Operator |
Kit Carson Windpower LLC (2013 to 2021) Duke Energy Renewables Services (2022 to 2024) |
Map of Kit Carson Windpower
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Kit Carson Windpower.
Monthly Net Generation for Kit Carson Windpower
Kit Carson Windpower Details
| Summary Information | |
|---|---|
| Plant Name | Kit Carson Windpower (57244) |
| Plant Address | 22330 County Road 44, Burlington, CO 80807 |
| Utility | Duke Energy Renewables Services (65411) |
| Latitude, Longitude | 39.3383, -102.3533 |
| Generation Dates on File | Nov 2010 to Dec 2024 |
| Initial Operation Date | November 2010 |
| Annual Generation | 168.5 GWh |
| Fuel Types | Wind |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | WECC |
| Balancing Authority | Western Area Power Administration - Rocky Mountain Region (WACM) |
| NAICS Code | Utilities (22) |
| Sector | IPP Non-CHP (2) |
| Water Source | |
| Ash Impoundment | |
| Transmission / Distribution Owner | Tri-State G & T Assn, Inc (30151) |
| Grid Voltage | 230.00 kV |
| Energy Storage | No |
Generator KCW Details Operating November 2010
| Technology | Onshore Wind Turbine |
|---|---|
| Prime Mover | Wind Turbine, Onshore |
| Ownership | Single Owner |
| Nameplate Capacity | 51 MW |
| Summer Capacity | 51 MW |
| Winter Capacity | 51 MW |
| Minimum Load | 0.1 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | November 2010 |
| Combined Heat & Power | No |
|---|---|
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Wind |
| Solid Fuel Gasification | No |
| Turbines/Hydrokinetic Buoys | 34 |
| Planned New Prime Mover | WT |
| Planned Energy Source | WND |
| Planned Repower | December 2025 |
| Multiple Fuels | No |
| Turbine Details | |
| Number Of Turbines | 34 |
|---|---|
| Predominant Turbine Manufacturer | GE |
| Predominant Turbine Model Number | 1.5 SLE |
| Design Wind Speed | 16.8 MPH |
| Wind Quality Class | 2 - Medium Wind |
| Turbine Hub Height Feet | 272 |
Kit Carson Windpower Plant Owners
| Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #778 | Painted Hills Wind Park | Whitewater, CA | 173.5 GWh |
| #779 | Hawkeye Wind Farm | Sumner, IA | 173.3 GWh |
| #780 | Highland North Wind Farm | Sidman, PA | 173.0 GWh |
| #781 | Langdon Wind II LLC | Osnabrock, ND | 170.9 GWh |
| #782 | Bliss (NY) | Bliss, NY | 170.7 GWh |
| #783 | Chateaugay | Chateaugay, NY | 170.5 GWh |
| #784 | Spearville 3 LLC | Spearville, KS | 170.4 GWh |
| #785 | Whitetail | Oilton, TX | 170.4 GWh |
| #786 | Centennial Wind Farm | Fort Supply, OK | 170.2 GWh |
| #787 | Willow Creek Energy Center | Lone, OR | 168.7 GWh |
| #789 | Woodward Mountain II | Girvin, TX | 168.0 GWh |
| #790 | Woodward Mountain I | Girvin, TX | 168.0 GWh |
| #791 | Horse Butte Wind I, LLC | Iona, ID | 167.4 GWh |
| #792 | Bison I Wind Energy Center | New Salem, ND | 165.9 GWh |
| #793 | Cerro Gordo Wind Farm | Union, IA | 165.0 GWh |
| #794 | Scurry County Wind II | Snyder, TX | 164.9 GWh |
| #795 | Hardscrabble Wind Power LLC | Little Falls, NY | 163.8 GWh |
| #796 | Eurus Combine Hills Turbine Ranch 2 | Milton Freewater, OR | 163.6 GWh |
| #797 | Wolverine Creek | Idaho Falls, ID | 163.5 GWh |
| #798 | Blue Canyon Windpower VI LLC | Carnegie, OK | 163.5 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Kit Carson Windpower.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Bronco Plains Wind II, LLC | Kit Carson, CO | 688.5 GWh | 34.7 mi |
| Bronco Plains Wind, LLC | Flagler, CO | 1.1 TWh | 39.9 mi |
| Burlington (CO) | Burlington, CO | 4.4 GWh | 6 mi |
| Carousel Wind Farm LLC | Burlington, CO | 613.9 GWh | 9.6 mi |
| Cedar Point Wind | Limon, CO | 671.2 GWh | 71 mi |
| Central Plains Wind Farm | Marienthal, KS | 102.2 GWh | 86.2 mi |
| Cheyenne Ridge Wind Farm | Cheyenne Wells, CO | 1.6 TWh | 23.5 mi |
| Colby | Colby, KS | 1.2 GWh | 70.4 mi |
| Crossing Trails Wind Power Project LLC. | Seibert, CO | 396.7 GWh | 32.2 mi |
| East Fork Wind Project, LLC | Colby, KS | 727.4 GWh | 68.4 mi |
| Lamar Plant | Lamar, CO | 12.6 GWh | 90.7 mi |
| Limon Generating Station | Limon, CO | 216.3 GWh | 72.7 mi |
| Limon III Wind LLC | Limon, CO | 623.9 GWh | 59.9 mi |
| Limon Wind I | Limon, CO | 567.2 GWh | 65.2 mi |
| Limon Wind II | Limon, CO | 473.6 GWh | 65.6 mi |
| Midwest Energy Community Solar Array | Colby, KS | 1.8 GWh | 70.3 mi |
| Rush Creek Wind | Matheson, CO | 2.2 TWh | 80.6 mi |
| Solomon Forks Wind Project, LLC | Colby, KS | 1.1 TWh | 68.4 mi |
| St Francis | St Francis, KS | 19.6 MWh | 41.6 mi |
| Western Plains Wind | Oakley, KS | 12.2 GWh | 88 mi |