Bent Tree Wind Farm Phase 1

31072 State Highway 13, Hartland, MN 56042

Plant Summary Information

Bent Tree Wind Farm Phase 1 is ranked #33 out of 759 power plants in Minnesota in terms of total annual net electricity generation.

Bent Tree Wind Farm Phase 1 generated 102.3 GWh during the 3-month period between September 2024 to December 2024.

Plant NameBent Tree Wind Farm Phase 1
Utility NameWisconsin Power & Light Co
LocationFreeborn County, MN
Initial Operation DateFebruary 2011
Last Update Dec 2024
Annual Generation 343.0 GWh
Annual Consumption 1.3 M MMBtu
Ranked #1,818 out of 12,613 Power Plants Nationwide
Ranked #541 out of 1,374 Wind Power Plants Nationwide
Ranked #33 out of 759 Minnesota Power Plants
Ranked #20 out of 125 Minnesota Wind Power Plants
Fuel Types Wind

Map of Bent Tree Wind Farm Phase 1

Full Screen Map

Register Now for Comprehensive Access

Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Bent Tree Wind Farm Phase 1.

Create Your Account Today

Monthly Net Generation for Bent Tree Wind Farm Phase 1

Monthly Plant Fuel Consumption for Bent Tree Wind Farm Phase 1

Bent Tree Wind Farm Phase 1 Details

Summary Information
Plant NameBent Tree Wind Farm Phase 1 (57198)
Plant Address31072 State Highway 13, Hartland, MN 56042
UtilityWisconsin Power & Light Co (20856)
Latitude, Longitude43.7246, -93.45043
Generation Dates on FileFeb 2011 to Dec 2024
Initial Operation DateFebruary 2011
Annual Generation 343.0 GWh
Fuel Types Wind
 
Federal Energy Regulatory Commission (FERC) Information
FERC Cogeneration StatusNo
FERC Small Power Producer StatusNo
FERC Exempt Wholesale Generator StatusNo
Regulatory Information
Regulatory StatusRegulated
NERC RegionMRO
Balancing AuthorityMidcontinent Independent Transmission System Operator, Inc.. (MISO)
NAICS CodeUtilities (22)
Sector Electric Utility (1)
Water Source
Ash Impoundment
Transmission / Distribution OwnerITC Midwest LLC (56161)
Grid Voltage 161.00 kV
Energy StorageNo

Generator 1 Details Operating February 2011

TechnologyOnshore Wind Turbine
Prime MoverWind Turbine, Onshore
OwnershipSingle Owner
RTO ISO LMP Node DesignationALTW.BENT_TREE
RTO ISO Location Designation For Reporting Wholesale Sales DataALTW.BENT_TREE
Nameplate Capacity201.3 MW
Nameplate Power Factor0.9
Summer Capacity201.3 MW
Winter Capacity201.3 MW
Minimum Load0.4 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateFebruary 2011
Combined Heat & Power No
Sector NameElectric Utility (1)
Energy SourceWind
Solid Fuel Gasification No
Carbon Capture TechnologyNo
Turbines/Hydrokinetic Buoys122
Time From Cold Shutdown To Full Load10M
Other Planned ModificationsNo
Multiple FuelsNo
Turbine Details
Number Of Turbines122
Predominant Turbine ManufacturerVestas
Predominant Turbine Model NumberV82-1.65
Design Wind Speed16.3 MPH
Wind Quality Class2 - Medium Wind
Turbine Hub Height Feet262

Bent Tree Wind Farm Phase 1 Plant Owners

Owner NameAddressOwnership
We couldn't locate any owners for this plant

Power Plants with Similar Net Generation

Power plants with a similar annual net generation from Wind.

RankPlant NamePlant LocationAnnual Generation
#531Buffalo Gap 2 Wind FarmMerkel, TX350.4 GWh
#532Blue Summit II WindVernon, TX346.9 GWh
#533Mesquite Wind Power LLCAbilene, TX346.3 GWh
#534Midland WindKewane, IL346.2 GWh
#535Hopkins Ridge WindDayton, WA345.4 GWh
#536Cedro Hill Wind LLCBruni, TX344.5 GWh
#537Gratiot Farms Wind ProjectCarson City, MI344.5 GWh
#538Drift Sand Wind Project LLCRush Springs, OK344.1 GWh
#539Hart WindHart, TX344.0 GWh
#540Mower County Wind Energy CenterGrand Meadow, MN343.3 GWh
#542Sweetwater Wind 2 LLCSweetwater, TX340.6 GWh
#543Bishop Hill II Wind FarmCambridge, IL339.9 GWh
#544Baron Winds FarmCohocton, NY339.6 GWh
#545Cameron Wind 1 LLCRio Hondo, TX337.6 GWh
#546Lorenzo WindLorenzo, TX337.7 GWh
#547Inadale Wind Farm LLC HybridRoscoe, TX335.1 GWh
#548Papalote Creek I LLCTaft, TX335.8 GWh
#549Blue Sky Green Field Wind ProjectFond du Lac, WI335.4 GWh
#550Rugby Wind Power ProjectBarton, ND335.4 GWh
#551Spinning Spur Wind LLCVegas, TX334.2 GWh

Nearby Power Plants

Below are closest 20 power plants surrounding Bent Tree Wind Farm Phase 1.

Plant NamePlant LocationAnnual GenerationDistance
Altair Community Solar GardenNew Richmond, MN1.8 GWh14 mi
Blooming PrairieBlooming Prairie, MN234.0 MWh22.2 mi
Bolduan CSGNew Richland, MN1.8 GWh12.7 mi
Buffalo GardenWaseca, MN1.7 GWh19.2 mi
CF Novel Solar CSG Gardens Two, LLCMinnesota Lake, MN3.1 GWh21 mi
Clear Garden CSGWaseca, MN1.7 GWh21.6 mi
Freeborn Wind FarmGlenville, MN785.2 GWh19.6 mi
Goose Lake MN DPC-GMAlbert Lea, MN3.0 GWh8.8 mi
Lake MillsLake Mills, IA38.0 MWh21.6 mi
Novel David Solar LLC CSGWaseca, MN2.1 GWh19.2 mi
Novel Kanewischer Solar CSGWaseca, MN982.0 MWh22.6 mi
Oak Glen Wind FarmBlooming Prairie, MN120.5 GWh20.5 mi
Old Gold Energy Center, LLCJoice, IA78.4 GWh23.6 mi
REG Juhl Glenville Wind, LLCAlbert Lea, MN9.4 GWh12.2 mi
Severson GardenWaseca, MN943.0 MWh19.2 mi
Silver Lake GardenWaseca, MN1.6 GWh19.7 mi
USS All In Solar LLC CSGHartland, MN2.1 GWh8.3 mi
USS Solar Way LLC CSGHartland, MN1.9 GWh7 mi
WasecaSunWaseca, MN9.2 GWh22.8 mi
Wells ICWells, MN180.0 MWh13.7 mi