Bent Tree Wind Farm Phase 1
31072 State Highway 13, Hartland, MN 56042Plant Summary Information
Bent Tree Wind Farm Phase 1 is ranked #33 out of 759 power plants in Minnesota in terms of total annual net electricity generation.
Bent Tree Wind Farm Phase 1 generated 102.3 GWh during the 3-month period between September 2024 to December 2024.
| Plant Name | Bent Tree Wind Farm Phase 1 |
|---|---|
| Utility Name | Wisconsin Power & Light Co |
| Location | Freeborn County, MN |
| Initial Operation Date | February 2011 |
| Last Update | Dec 2024 |
| Annual Generation | 343.0 GWh |
| Annual Consumption | 1.3 M MMBtu |
| Ranked #1,799 out of 12,553 Power Plants Nationwide | |
| Ranked #534 out of 1,366 Wind Power Plants Nationwide | |
| Ranked #33 out of 759 Minnesota Power Plants | |
| Ranked #19 out of 125 Minnesota Wind Power Plants | |
| Fuel Types | Wind |
Map of Bent Tree Wind Farm Phase 1
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Bent Tree Wind Farm Phase 1.
Monthly Net Generation for Bent Tree Wind Farm Phase 1
Bent Tree Wind Farm Phase 1 Details
| Summary Information | |
|---|---|
| Plant Name | Bent Tree Wind Farm Phase 1 (57198) |
| Plant Address | 31072 State Highway 13, Hartland, MN 56042 |
| Utility | Wisconsin Power & Light Co (20856) |
| Latitude, Longitude | 43.7246, -93.45043 |
| Generation Dates on File | Feb 2011 to Dec 2024 |
| Initial Operation Date | February 2011 |
| Annual Generation | 343.0 GWh |
| Fuel Types | Wind |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Regulated |
| NERC Region | MRO |
| Balancing Authority | Midcontinent Independent Transmission System Operator, Inc.. (MISO) |
| NAICS Code | Utilities (22) |
| Sector | Electric Utility (1) |
| Water Source | |
| Ash Impoundment | |
| Transmission / Distribution Owner | ITC Midwest LLC (56161) |
| Grid Voltage | 161.00 kV |
| Energy Storage | No |
Generator 1 Details Operating February 2011
| Technology | Onshore Wind Turbine |
|---|---|
| Prime Mover | Wind Turbine, Onshore |
| Ownership | Single Owner |
| RTO ISO LMP Node Designation | ALTW.BENT_TREE |
| RTO ISO Location Designation For Reporting Wholesale Sales Data | ALTW.BENT_TREE |
| Nameplate Capacity | 201.3 MW |
| Nameplate Power Factor | 0.9 |
| Summer Capacity | 201.3 MW |
| Winter Capacity | 201.3 MW |
| Minimum Load | 0.4 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | February 2011 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Wind |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Turbines/Hydrokinetic Buoys | 122 |
| Time From Cold Shutdown To Full Load | 10M |
| Other Planned Modifications | No |
| Multiple Fuels | No |
| Turbine Details | |
| Number Of Turbines | 122 |
|---|---|
| Predominant Turbine Manufacturer | Vestas |
| Predominant Turbine Model Number | V82-1.65 |
| Design Wind Speed | 16.3 MPH |
| Wind Quality Class | 2 - Medium Wind |
| Turbine Hub Height Feet | 262 |
Bent Tree Wind Farm Phase 1 Plant Owners
| Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #524 | Baron Winds Farm | Cohocton, NY | 350.8 GWh |
| #525 | Fenton Wind Farm | Chandler, MN | 350.1 GWh |
| #526 | Los Vientos Wind 1B | Sebastian, TX | 349.3 GWh |
| #527 | Hopkins Ridge Wind | Dayton, WA | 349.3 GWh |
| #528 | Crescent Wind Park | Hillsdale, MI | 347.8 GWh |
| #529 | Crossroads Wind Farm | Canton, OK | 347.6 GWh |
| #530 | Blue Summit II Wind | Vernon, TX | 346.3 GWh |
| #531 | Cedro Hill Wind LLC | Bruni, TX | 344.5 GWh |
| #532 | Mower County Wind Energy Center | Grand Meadow, MN | 343.3 GWh |
| #533 | Midland Wind | Kewane, IL | 343.2 GWh |
| #535 | Redbed Plains Wind Farm | Tuttle, OK | 342.5 GWh |
| #536 | Tyler Bluff Wind Project, LLC | Muenster, TX | 342.2 GWh |
| #537 | Mesquite Wind Power LLC | Abilene, TX | 341.7 GWh |
| #538 | Sweetwater Wind 2 LLC | Sweetwater, TX | 340.6 GWh |
| #539 | Bishop Hill II Wind Farm | Cambridge, IL | 339.9 GWh |
| #540 | Cameron Wind 1 LLC | Rio Hondo, TX | 337.6 GWh |
| #541 | Gratiot Farms Wind Project | Carson City, MI | 338.5 GWh |
| #542 | Inadale Wind Farm LLC Hybrid | Roscoe, TX | 335.1 GWh |
| #543 | Papalote Creek I LLC | Taft, TX | 335.8 GWh |
| #544 | Rugby Wind Power Project | Barton, ND | 335.4 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Bent Tree Wind Farm Phase 1.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Altair Community Solar Garden | New Richmond, MN | 1.8 GWh | 14 mi |
| Blooming Prairie | Blooming Prairie, MN | 234.0 MWh | 22.2 mi |
| Bolduan CSG | New Richland, MN | 1.8 GWh | 12.7 mi |
| Buffalo Garden | Waseca, MN | 1.7 GWh | 19.2 mi |
| CF Novel Solar CSG Gardens Two, LLC | Minnesota Lake, MN | 3.1 GWh | 21 mi |
| Clear Garden CSG | Waseca, MN | 1.7 GWh | 21.6 mi |
| Freeborn Wind Farm | Glenville, MN | 736.0 GWh | 19.6 mi |
| Goose Lake MN DPC-GM | Albert Lea, MN | 3.0 GWh | 8.8 mi |
| Lake Mills | Lake Mills, IA | 38.0 MWh | 21.6 mi |
| Novel David Solar LLC CSG | Waseca, MN | 2.1 GWh | 19.2 mi |
| Novel Kanewischer Solar CSG | Waseca, MN | 982.0 MWh | 22.6 mi |
| Oak Glen Wind Farm | Blooming Prairie, MN | 120.5 GWh | 20.5 mi |
| Old Gold Energy Center, LLC | Joice, IA | 78.4 GWh | 23.6 mi |
| REG Juhl Glenville Wind, LLC | Albert Lea, MN | 9.4 GWh | 12.2 mi |
| Severson Garden | Waseca, MN | 943.0 MWh | 19.2 mi |
| Silver Lake Garden | Waseca, MN | 1.6 GWh | 19.7 mi |
| USS All In Solar LLC CSG | Hartland, MN | 2.1 GWh | 8.3 mi |
| USS Solar Way LLC CSG | Hartland, MN | 1.9 GWh | 7 mi |
| WasecaSun | Waseca, MN | 9.2 GWh | 22.8 mi |
| Wells IC | Wells, MN | 180.0 MWh | 13.7 mi |