Baldwin Solar BESS
8089 Levee Road, Baldwin, IL 66217Plant Summary Information
Baldwin Solar BESS is ranked #18 out of 179 solar farms in Illinois in terms of total annual net electricity generation.
Baldwin Solar BESS generated 32.0 GWh during the 3-month period between January 2025 to April 2025.
Plant Name | Baldwin Solar BESS |
---|---|
Utility Name | Vistra Corp |
Location | Randolph County, IL |
Initial Operation Date | December 2024 |
Last Update | Apr 2025 |
Annual Generation | 43.4 GWh |
Annual Consumption | 148.5 k MMBtu |
Ranked #4,191 out of 12,299 Power Plants Nationwide | |
Ranked #991 out of 6,182 Solar Power Plants Nationwide | |
Ranked #113 out of 348 Illinois Power Plants | |
Ranked #18 out of 179 Illinois Solar Power Plants | |
Fuel Types | Solar |
Map of Baldwin Solar BESS
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Baldwin Solar BESS.
Monthly Net Generation for Baldwin Solar BESS
Baldwin Solar BESS Details
Summary Information | |
---|---|
Plant Name | Baldwin Solar BESS (68148) |
Plant Address | 8089 Levee Road, Baldwin, IL 66217 |
Utility | Vistra Corp (5504) |
Latitude, Longitude | 38.20354, -89.85394 |
Generation Dates on File | Dec 2024 to Apr 2025 |
Initial Operation Date | December 2024 |
Annual Generation | 43.4 GWh |
Fuel Types | Solar |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | SERC |
Balancing Authority | Midcontinent Independent Transmission System Operator, Inc.. (MISO) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | |
Transmission / Distribution Owner | Ameren Illinois Company (56697) IL |
Grid Voltage | 345.00 kV |
Energy Storage | Yes |
Generator 1 Details Operating December 2024
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
Nameplate Capacity | 68.4 MW |
Summer Capacity | 68.4 MW |
Winter Capacity | 68.4 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | December 2024 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Solar |
Solar Details | |
Single Axis Tracking | Yes |
---|---|
Azimuth Angle | 180 |
DC Net Capacity | 94.5 MW |
Thin Film CDTE | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | No |
Generator 2 Details Operating December 2024
Technology | Batteries |
---|---|
Prime Mover | Battery |
Ownership | Single Owner |
Nameplate Capacity | 2 MW |
Summer Capacity | 2 MW |
Winter Capacity | 2 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | December 2024 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Electricity used for energy storage |
Energy Storage Details | |
Nameplate Energy Capacity MWH | 8 |
---|---|
Maximum Charge Rate | 2 MW |
Maximum Discharge Rate | 2 MW |
Storage Technology | LIB |
Nameplate Reactive Power Rating | 0.7 |
Storage Enclosure Type | CS |
Arbitrage | P |
Direct Support Of Another Unit | No |
Support T D Asset | No |
Baldwin Solar BESS Plant Owners
Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#981 | American Falls Solar II | American Falls, ID | 44.2 GWh |
#982 | Arbor Hill Solar | Greenfield, IA | 44.1 GWh |
#983 | Kimmel Road Solar, LLC | Du Quoin, IL | 44.1 GWh |
#984 | Fort Gordon Solar Facility | Fort Gordon, GA | 44.0 GWh |
#985 | Gaston Solar Power Plant | Cherryville Township, NC | 43.9 GWh |
#986 | Avalon Solar II | Sahuarita, AZ | 43.8 GWh |
#987 | Rawhide Prairie Solar Hybrid | Wellington, CO | 43.7 GWh |
#988 | Calverton Solar Energy Center | Calverton, NY | 43.7 GWh |
#989 | Pavant Solar III | Filmore, UT | 43.6 GWh |
#990 | Orchard Ranch Solar | Orchard, ID | 43.5 GWh |
#992 | SR Arlington I | Arlington, GA | 43.5 GWh |
#993 | Alton Post Office Solar | Alton, VA | 43.4 GWh |
#994 | Greater Sandhill I | Mosca, CO | 43.4 GWh |
#995 | Tinton Falls Solar Farm | Tinton Falls, NJ | 43.3 GWh |
#996 | Rice Creek | Putnam, FL | 43.1 GWh |
#997 | Adams Nielson Solar | Lind, WA | 43.1 GWh |
#998 | Creston Solar (50 MW) | Creston, IA | 42.9 GWh |
#999 | Energix Leatherwood, LLC | Axton, VA | 42.3 GWh |
#1000 | Cameron Solar | Cameron, SC | 42.3 GWh |
#1001 | Decatur County Solar Project | Bainbridge, GA | 42.2 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Baldwin Solar BESS.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
AES Belleville Solar LLC | Belleville, IL | 12.9 GWh | 21.4 mi |
Anheuser-Busch St Louis | St. Louis, MO | 42.6 GWh | 33.4 mi |
Baldwin Energy Complex | Baldwin, IL | 6.8 TWh | 0.1 mi |
Breese | Breese, IL | 263.0 MWh | 33.1 mi |
Freeburg | Freeburg, IL | 122.0 MWh | 15.7 mi |
Kimmel Road Solar, LLC | Du Quoin, IL | 44.1 GWh | 36.4 mi |
Milam Gas Recovery | East St. Lois, IL | 19.4 GWh | 35 mi |
Pinckneyville | Pinckneyville, IL | 79.8 GWh | 28.3 mi |
Prairie State Generating Station | Marissa, IL | 11.3 TWh | 11.4 mi |
Prairie State Solar Project | Swanwick Township, IL | 230.3 GWh | 14.9 mi |
Red Bud | Red Bud, IL | 121.0 MWh | 7.9 mi |
Rush Island | Festus, MO | 603.1 GWh | 22.8 mi |
SCS American Bottoms 009885 Sauget, LLC | Sauget, IL | 3.0 GWh | 32.2 mi |
Southwestern Bell Telephone | St. Louis, MO | 72.0 MWh | 34.6 mi |
St. Clair Solar 3 | Washington Park, IL | 158.0 MWh | 31.6 mi |
Trenton East | Trenton, IL | 1.7 GWh | 27.6 mi |
Trenton West | Trenton, IL | 2.2 GWh | 27.5 mi |
Trigen St. Louis | St Louis, MO | 85.9 GWh | 34.7 mi |
Venice | Venice, IL | 26.8 GWh | 36.3 mi |
Waterloo | Waterloo, IL | 491.0 MWh | 18.9 mi |