Union Carbide Seadrift Cogen
Highway 185, Seadrift, TX 77983Plant Summary Information
Union Carbide Seadrift Cogen is ranked #96 out of 314 natural gas power plants in Texas in terms of total annual net electricity generation.
Union Carbide Seadrift Cogen is comprised of 8 generators and generated 151.4 GWh during the 3-month period between September 2024 to December 2024.
| Plant Name | Union Carbide Seadrift Cogen |
|---|---|
| Utility Name | Union Carbide Corp-Seadrift |
| Location | Calhoun County, TX |
| Initial Operation Date | January 1964 |
| Last Update | Dec 2024 |
| Annual Generation | 638.9 GWh |
| Annual Consumption | 7.9 M MMBtu |
| Ranked #1,073 out of 12,539 Power Plants Nationwide | |
| Ranked #532 out of 2,243 Natural Gas Power Plants Nationwide | |
| Ranked #202 out of 799 Texas Power Plants | |
| Ranked #96 out of 314 Texas Natural Gas Power Plants | |
| Fuel Types | Natural Gas : 92.1% Other Gas : 7.9% |
Map of Union Carbide Seadrift Cogen
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Union Carbide Seadrift Cogen.
Monthly Net Generation for Union Carbide Seadrift Cogen
Union Carbide Seadrift Cogen Details
| Summary Information | |
|---|---|
| Plant Name | Union Carbide Seadrift Cogen (50150) |
| Plant Address | Highway 185, Seadrift, TX 77983 |
| Utility | Union Carbide Corp-Seadrift (19450) |
| Latitude, Longitude | 28.5105, -96.7706 |
| Generation Dates on File | Jan 2001 to Dec 2024 |
| Initial Operation Date | January 1964 |
| Annual Generation | 638.9 GWh |
| Fuel Types | Natural Gas : 92.1% Other Gas : 7.9% |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | Yes |
| FERC Cogeneration Docket Number | 85-15-001 |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | TRE |
| Balancing Authority | Electric Reliability Council of Texas, Inc. (ERCO) |
| NAICS Code | Chemical Manufacturing (325) |
| Sector | Industrial CHP (7) |
| Water Source | Surface |
| Ash Impoundment | No |
| Transmission / Distribution Owner | AEP Texas Central Company (3278) TX |
| Grid Voltage | 69.00 kV |
| Energy Storage | No |
| Natural Gas Information | |
| Pipeline Name |
SOUTHCROSS ENERGY LLC HOUSTON PL CO LP FLORIDA GAS TRANSMISSION COMPANY |
| Pipeline Notes | CHANNEL |
| Natural Gas Storage | No |
| Liquefied Natural Gas Storage | No |
Generator GE10 Details Operating January 1964
| Technology | Natural Gas Steam Turbine |
|---|---|
| Prime Mover | Steam Turbine |
| Unit Code | G621 |
| Ownership | Single Owner |
| RTO ISO LMP Node Designation | UCC_COG_PUN1 |
| RTO ISO Location Designation For Reporting Wholesale Sales Data | ERCOT SOUTH ZONE |
| Nameplate Capacity | 15 MW |
| Nameplate Power Factor | 0.85 |
| Summer Capacity | 15 MW |
| Winter Capacity | 15 MW |
| Minimum Load | 2 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | January 1964 |
|---|---|
| Combined Heat & Power | Yes |
| Sector Name | Industrial CHP (7) |
| Topping Or Bottoming | B |
| Energy Source | Natural Gas / Other Gas |
| Startup Source | Natural Gas |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 12H |
| Multiple Fuels | Yes |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Generator IGT Details Operating January 1969
| Technology | Natural Gas Fired Combustion Turbine |
|---|---|
| Prime Mover | Combustion Turbine |
| Unit Code | G621 |
| Ownership | Single Owner |
| RTO ISO LMP Node Designation | UCC_COG_PUN1 |
| RTO ISO Location Designation For Reporting Wholesale Sales Data | ERCOT SOUTH ZONE |
| Nameplate Capacity | 12 MW |
| Nameplate Power Factor | 0.9 |
| Summer Capacity | 12 MW |
| Winter Capacity | 12 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | January 1969 |
| Combined Heat & Power | No |
| Sector Name | Industrial CHP (7) |
| Energy Source | Natural Gas |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 12H |
| Multiple Fuels | No |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Generator GEN5 Details Operating November 1987
| Technology | Natural Gas Steam Turbine |
|---|---|
| Prime Mover | Steam Turbine |
| Unit Code | G621 |
| Ownership | Single Owner |
| RTO ISO LMP Node Designation | UCC_COG_PUN1 |
| RTO ISO Location Designation For Reporting Wholesale Sales Data | ERCOT SOUTH ZONE |
| Nameplate Capacity | 15 MW |
| Nameplate Power Factor | 0.9 |
| Summer Capacity | 15 MW |
| Winter Capacity | 15 MW |
| Minimum Load | 2 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | November 1987 |
|---|---|
| Combined Heat & Power | Yes |
| Sector Name | Industrial CHP (7) |
| Topping Or Bottoming | B |
| Energy Source | Natural Gas / Other Gas |
| Startup Source | Natural Gas |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 12H |
| Multiple Fuels | Yes |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Generator GEN6 Details Operating November 1987
| Technology | Natural Gas Fired Combustion Turbine |
|---|---|
| Prime Mover | Combustion Turbine |
| Unit Code | G621 |
| Ownership | Single Owner |
| RTO ISO LMP Node Designation | UCC_COG_PUN1 |
| RTO ISO Location Designation For Reporting Wholesale Sales Data | ERCOT SOUTH ZONE |
| Nameplate Capacity | 35 MW |
| Nameplate Power Factor | 0.9 |
| Summer Capacity | 30 MW |
| Winter Capacity | 38 MW |
| Minimum Load | 17 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | November 1987 |
| Combined Heat & Power | Yes |
| Sector Name | Industrial CHP (7) |
| Topping Or Bottoming | T |
| Energy Source | Natural Gas |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 12H |
| Multiple Fuels | No |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Generator GEN7 Details Out of Service November 1987
| Technology | Natural Gas Steam Turbine |
|---|---|
| Prime Mover | Steam Turbine |
| Unit Code | G621 |
| Ownership | Single Owner |
| RTO ISO LMP Node Designation | UCC_COG_PUN1 |
| RTO ISO Location Designation For Reporting Wholesale Sales Data | ERCOT SOUTH ZONE |
| Nameplate Capacity | 6 MW |
| Nameplate Power Factor | 0.9 |
| Summer Capacity | 6 MW |
| Winter Capacity | 6 MW |
| Minimum Load | 1.5 MW |
| Uprate/Derate Completed | No |
| Status | Out of Service |
| First Operation Date | November 1987 |
|---|---|
| Combined Heat & Power | Yes |
| Sector Name | Industrial CHP (7) |
| Topping Or Bottoming | B |
| Energy Source | Natural Gas |
| Startup Source | Natural Gas |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 12H |
| Multiple Fuels | No |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Generator GEN8 Details Operating November 1987
| Technology | Natural Gas Fired Combustion Turbine |
|---|---|
| Prime Mover | Combustion Turbine |
| Unit Code | G621 |
| Ownership | Single Owner |
| RTO ISO LMP Node Designation | UCC_COG_PUN1 |
| RTO ISO Location Designation For Reporting Wholesale Sales Data | ERCOT SOUTH ZONE |
| Nameplate Capacity | 35 MW |
| Nameplate Power Factor | 0.9 |
| Summer Capacity | 30 MW |
| Winter Capacity | 38 MW |
| Minimum Load | 17 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | November 1987 |
| Combined Heat & Power | Yes |
| Sector Name | Industrial CHP (7) |
| Topping Or Bottoming | T |
| Energy Source | Natural Gas |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 12H |
| Multiple Fuels | No |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Generator GEN9 Details Operating November 1987
| Technology | Natural Gas Steam Turbine |
|---|---|
| Prime Mover | Steam Turbine |
| Unit Code | G621 |
| Ownership | Single Owner |
| RTO ISO LMP Node Designation | UCC_COG_PUN1 |
| RTO ISO Location Designation For Reporting Wholesale Sales Data | ERCOT SOUTH ZONE |
| Nameplate Capacity | 15 MW |
| Nameplate Power Factor | 0.9 |
| Summer Capacity | 15 MW |
| Winter Capacity | 15 MW |
| Minimum Load | 2 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | November 1987 |
|---|---|
| Combined Heat & Power | Yes |
| Sector Name | Industrial CHP (7) |
| Topping Or Bottoming | B |
| Energy Source | Natural Gas / Other Gas |
| Startup Source | Natural Gas |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 12H |
| Multiple Fuels | Yes |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Generator GE11 Details Operating November 2000
| Technology | Natural Gas Fired Combustion Turbine |
|---|---|
| Prime Mover | Combustion Turbine |
| Unit Code | G621 |
| Ownership | Single Owner |
| RTO ISO LMP Node Designation | UCC_COG_PUN1 |
| RTO ISO Location Designation For Reporting Wholesale Sales Data | ERCOT SOUTH ZONE |
| Nameplate Capacity | 35 MW |
| Nameplate Power Factor | 0.85 |
| Summer Capacity | 30 MW |
| Winter Capacity | 38 MW |
| Minimum Load | 20 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | November 2000 |
| Combined Heat & Power | Yes |
| Sector Name | Industrial CHP (7) |
| Topping Or Bottoming | T |
| Energy Source | Natural Gas |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 12H |
| Multiple Fuels | No |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Union Carbide Seadrift Cogen Plant Owners
| Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #522 | Procter & Gamble Mehoopany Mill | Mehoopany, PA | 612.1 GWh |
| #523 | Frontier | Oklahoma City, OK | 607.4 GWh |
| #524 | Hawthorn | Kansas City, MO | 2.8 TWh |
| #525 | General Electric Plastic | Burkeville, AL | 602.0 GWh |
| #526 | SCA Cogen 2 | Sacramento, CA | 601.6 GWh |
| #527 | Morris Cogeneration LLC | Morris, IL | 598.9 GWh |
| #528 | Roseville Energy Park | Roseville, CA | 598.5 GWh |
| #529 | Topaz Generating | Texas City, TX | 597.6 GWh |
| #530 | Encogen | Bellingham, WA | 593.2 GWh |
| #531 | Beatrice | Beatrice, NE | 589.9 GWh |
| #533 | Geismar Cogen | Geismar, LA | 585.7 GWh |
| #534 | Axiall Natrium Plant | New Martinsville, WV | 602.0 GWh |
| #535 | Bethpage Power Plant | Hicksville, NY | 573.5 GWh |
| #536 | Berkshire Power | Agawam, MA | 573.3 GWh |
| #537 | Eklutna Generation Station | Chugiak, AK | 573.0 GWh |
| #538 | Shell Chemical | Geismar, LA | 572.3 GWh |
| #539 | NAFTA Region Olefins Complex Cogen Fac | Port Arthur, TX | 562.0 GWh |
| #540 | Brandywine Power Facility | Brandywine, MD | 592.5 GWh |
| #541 | Freeport LP Pretreatment Facility | Freeport, TX | 555.9 GWh |
| #542 | Gregory Power Plant | Gregory, TX | 552.7 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Union Carbide Seadrift Cogen.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| CFB Power Plant | Point Comfort, TX | 853.6 GWh | 17 mi |
| CG PS Victoria WWTP, LLC | Victoria, TX | 114.0 MWh | 24.4 mi |
| Coleto Creek | Fannin, TX | 3.0 TWh | 30.3 mi |
| Cranell Wind Farm LLC | TBD, TX | 588.6 GWh | 46.3 mi |
| Formosa Utility Venture Ltd | Point Comfort, TX | 4.8 TWh | 18.7 mi |
| Ganado Solar | Gail, TX | 343.8 GWh | 43.9 mi |
| HEB00092 | Victoria, TX | 365.0 MWh | 27.3 mi |
| Oriana Solar LLC | Victoria, TX | 38.2 GWh | 30 mi |
| OTHERCitizensHospital | Victoria, TX | 625.0 MWh | 24.4 mi |
| Papalote Creek II LLC | Taft, TX | 507.1 GWh | 47.9 mi |
| Peregrine Solar | Gollad, TX | 478.1 GWh | 41.9 mi |
| Port Comfort Power LLC | Point Comfort, TX | 76.1 GWh | 16.6 mi |
| Sam Rayburn | Nursery, TX | 194.0 GWh | 34.5 mi |
| Seadrift Coke LP | Port Lavaca, TX | 31.9 GWh | 1.4 mi |
| Tres Bahias | Port Lavaca, TX | 438.7 GWh | 20 mi |
| Tres City Power LLC | Victoria, TX | 35.3 GWh | 23.9 mi |
| Tres Port Power, LLC | Victoria, TX | 60.8 GWh | 16.7 mi |
| Victoria | Victoria, TX | 1.5 TWh | 24.1 mi |
| Victoria Port Power II LLC | Victoria, TX | 185.4 GWh | 16.8 mi |
| Victoria Texas Plant | Victoria, TX | 472.4 GWh | 16 mi |