Wadsworth HBS RTO BTM
441 Leatherman rd, Wadsworth, OH 44281Plant Summary Information
Wadsworth HBS RTO BTM is ranked #16 out of 53 distillate fuel oil power plants in Ohio in terms of total annual net electricity generation.
Wadsworth HBS RTO BTM is comprised of 4 generators and generated 174.8 MWh during the 3-month period between September 2024 to December 2024.
| Plant Name | Wadsworth HBS RTO BTM |
|---|---|
| Utility Name | American Mun Power-Ohio, Inc |
| Location | Medina County, OH |
| Initial Operation Date | February 2020 |
| Last Update | Dec 2024 |
| Annual Generation | 608.0 MWh |
| Annual Consumption | 5.7 k MMBtu |
| Ranked #11,675 out of 12,613 Power Plants Nationwide | |
| Ranked #487 out of 1,238 Distillate Fuel Oil Power Plants Nationwide | |
| Ranked #160 out of 197 Ohio Power Plants | |
| Ranked #16 out of 53 Ohio Distillate Fuel Oil Power Plants | |
| Fuel Types | Distillate Fuel Oil |
Map of Wadsworth HBS RTO BTM
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Wadsworth HBS RTO BTM.
Monthly Net Generation for Wadsworth HBS RTO BTM
Monthly Plant Fuel Consumption for Wadsworth HBS RTO BTM
Wadsworth HBS RTO BTM Details
| Summary Information | |
|---|---|
| Plant Name | Wadsworth HBS RTO BTM (66464) |
| Plant Address | 441 Leatherman rd, Wadsworth, OH 44281 |
| Utility | American Mun Power-Ohio, Inc (40577) |
| Latitude, Longitude | 41.03539, -81.74896 |
| Generation Dates on File | Jan 2022 to Dec 2024 |
| Initial Operation Date | February 2020 |
| Annual Generation | 608.0 MWh |
| Fuel Types | Distillate Fuel Oil |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Regulated |
| NERC Region | RFC |
| Balancing Authority | PJM Interconnection, LLC (PJM) |
| NAICS Code | Utilities (22) |
| Sector | Electric Utility (1) |
| Water Source | |
| Ash Impoundment | |
| Transmission / Distribution Owner | City of Wadsworth - (OH) (19951) OH |
| Grid Voltage | 12.47 kV |
| Energy Storage | No |
Generator PB1 Details Operating February 2020
| Technology | Petroleum Liquids |
|---|---|
| Prime Mover | Internal Combustion Engine |
| Ownership | Single Owner |
| Nameplate Capacity | 2.7 MW |
| Nameplate Power Factor | 0.8 |
| Summer Capacity | 2.7 MW |
| Winter Capacity | 2.7 MW |
| Minimum Load | 2.7 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | February 2020 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Time From Cold Shutdown To Full Load | 10M |
| Multiple Fuels | No |
Generator PB2 Details Operating February 2020
| Technology | Petroleum Liquids |
|---|---|
| Prime Mover | Internal Combustion Engine |
| Ownership | Single Owner |
| Nameplate Capacity | 2.7 MW |
| Nameplate Power Factor | 0.8 |
| Summer Capacity | 2.7 MW |
| Winter Capacity | 2.7 MW |
| Minimum Load | 2.7 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | February 2020 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Time From Cold Shutdown To Full Load | 10M |
| Multiple Fuels | No |
Generator PB3 Details Operating February 2020
| Technology | Petroleum Liquids |
|---|---|
| Prime Mover | Internal Combustion Engine |
| Ownership | Single Owner |
| Nameplate Capacity | 2.7 MW |
| Nameplate Power Factor | 0.8 |
| Summer Capacity | 2.7 MW |
| Winter Capacity | 2.7 MW |
| Minimum Load | 2.7 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | February 2020 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Time From Cold Shutdown To Full Load | 10M |
| Multiple Fuels | No |
Generator PB4 Details Operating February 2020
| Technology | Petroleum Liquids |
|---|---|
| Prime Mover | Internal Combustion Engine |
| Ownership | Single Owner |
| Nameplate Capacity | 2.7 MW |
| Nameplate Power Factor | 0.8 |
| Summer Capacity | 2.7 MW |
| Winter Capacity | 2.7 MW |
| Minimum Load | 2.7 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | February 2020 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Time From Cold Shutdown To Full Load | 10M |
| Multiple Fuels | No |
Wadsworth HBS RTO BTM Plant Owners
| Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Distillate Fuel Oil.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #477 | TalenEnergy Martins Creek | Bangor, PA | 2.2 TWh |
| #478 | Johnson County | Cleburne, TX | 1.3 TWh |
| #479 | Backus Microgrid Project | Norwich, CT | 638.0 MWh |
| #480 | Plant X | Earth, TX | 815.7 GWh |
| #481 | WestRock Demopolis Mill | Demopolis, AL | 313.0 GWh |
| #482 | Marion | Marion, IL | 767.0 GWh |
| #483 | Wheaton | Eau Claire, WI | 18.6 GWh |
| #484 | Bay View Backup Power Facility | Toledo, OH | 629.0 MWh |
| #485 | Columbia Energy Center (SC) | Gaston, SC | 3.0 TWh |
| #486 | Industrial Park | Rock Falls, IL | 615.0 MWh |
| #488 | Pleasant Valley (MN) | Dexter, MN | 85.9 GWh |
| #489 | Crystal Mountain | Greenwater, WA | 607.0 MWh |
| #490 | Wadsworth IPS RTO BTM | Wadsworth, OH | 606.0 MWh |
| #491 | SEMASS Resource Recovery | West Wareham, MA | 567.1 GWh |
| #492 | Jones | Lubbock, TX | 2.9 TWh |
| #493 | Yellowstone Energy LP | Billings, MT | 458.4 GWh |
| #494 | Fort Hill 1, 2, 3 & 4 | Uncasville, CT | 579.0 MWh |
| #495 | UNH 7.9 MW Plant | Durham, NH | 53.9 GWh |
| #496 | VMEA 1 Credit Gen | Manassas, VA | 565.0 MWh |
| #497 | University of Notre Dame | Notre Dame, IN | 86.5 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Wadsworth HBS RTO BTM.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Akron WRF | Akron, OH | 5.6 GWh | 12.4 mi |
| Cleveland Thermal | Cleveland, OH | 2.2 GWh | 32.9 mi |
| Cleveland Works | Cleveland, OH | 357.3 GWh | 30.6 mi |
| Cuyahoga County Landfill | Brooklyn, OH | 4.3 GWh | 28.2 mi |
| Cuyahoga Falls 1 | Cuyahoga Falls, OH | 1.4 GWh | 16.1 mi |
| DG AMP 1048 Wadsworth | Wadsworth, OH | 10.5 GWh | 1.8 mi |
| DG AMP Rittman Rd | Wadsworth, OH | 3.5 GWh | 2.4 mi |
| DG AMP Solar Brewster | Brewster, OH | 2.3 GWh | 24.5 mi |
| DG AMP Solar Orrville 3 | Orrville, OH | 3.3 GWh | 12.4 mi |
| IGS AKC1 | Akron, OH | 4.5 GWh | 8.8 mi |
| MCCo Solar Generating Facility | Cleveland, OH | 1.1 GWh | 34.2 mi |
| Morton Salt Rittman | Rittman, OH | 13.4 GWh | 4.8 mi |
| Oberlin (OH) | Oberlin, OH | 634.0 MWh | 29.9 mi |
| Oberlin Spear Point Solar One | Oberlin, OH | 2.7 GWh | 31 mi |
| Orrville | Orrville, OH | 22.0 GWh | 12.8 mi |
| Orrville Peaking | Orrville, OH | 209.0 MWh | 12.1 mi |
| Seville | Seville, OH | 314.0 MWh | 6.4 mi |
| Summit Street Power Plant | Kent, OH | 29.3 GWh | 22.5 mi |
| Wadsworth IPS RTO BTM | Wadsworth, OH | 606.0 MWh | 3.7 mi |
| Wellington | Wellington, OH | 54.0 MWh | 26.4 mi |