Rio Bravo Solar 1 LLC
2 Miles NE of Hwy 33 and Lokem, McKittrick, CA 93251Plant Summary Information
Rio Bravo Solar 1 LLC is ranked #174 out of 917 solar farms in California in terms of total annual net electricity generation.
Rio Bravo Solar 1 LLC generated 6.8 GWh during the 3-month period between September 2025 to December 2025.
| Plant Name | Rio Bravo Solar 1 LLC |
|---|---|
| Utility Name | Deriva Energy |
| Location | Kern County, CA |
| Initial Operation Date | December 2016 |
| Last Update | Dec 2025 |
| Annual Generation | 52.1 GWh |
| Annual Consumption | 184.3 k MMBtu |
| Ranked #4,234 out of 13,301 Power Plants Nationwide | |
| Ranked #1,163 out of 7,209 Solar Power Plants Nationwide | |
| Ranked #460 out of 1,641 California Power Plants | |
| Ranked #174 out of 917 California Solar Power Plants | |
| Fuel Types | Solar |
| Previous Operators |
Infigen Asset Management LLC (2013 to 2013) Infigen Energy US Development LLC (2014 to 2014) SunPower Corporation, Systems (2015 to 2015) Rio Bravo Solar I, LLC (2016 to 2021) Duke Energy Renewables Services (2022 to 2024) Deriva Energy (2025 to 2025) |
Map of Rio Bravo Solar 1 LLC
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Rio Bravo Solar 1 LLC.
Monthly Net Generation for Rio Bravo Solar 1 LLC
Monthly Plant Fuel Consumption for Rio Bravo Solar 1 LLC
Rio Bravo Solar 1 LLC Details
| Summary Information | |
|---|---|
| Plant Name | Rio Bravo Solar 1 LLC (59249) |
| Plant Address | 2 Miles NE of Hwy 33 and Lokem, McKittrick, CA 93251 |
| Utility | Deriva Energy (65411) |
| Latitude, Longitude | 35.41611, -119.6825 |
| Generation Dates on File | Dec 2016 to Dec 2025 |
| Initial Operation Date | December 2016 |
| Annual Generation | 52.1 GWh |
| Fuel Types | Solar |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | WECC |
| Balancing Authority | California Independent System Operator (CISO) |
| NAICS Code | Utilities (22) |
| Sector | IPP Non-CHP (2) |
| Water Source | |
| Ash Impoundment | No |
| Transmission / Distribution Owner | Pacific Gas & Electric Co (14328) CA |
| Grid Voltage | 115.00 kV |
| Energy Storage | No |
Generator PV1 Details Operating December 2016
| Technology | Solar Photovoltaic |
|---|---|
| Prime Mover | Photovoltaic |
| Ownership | Wholly Owned by Other Entity |
| Nameplate Capacity | 20 MW |
| Summer Capacity | 19.5 MW |
| Winter Capacity | 14.1 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | December 2016 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Solar |
| Multiple Fuels | No |
| Solar Details | |
| Single Axis Tracking | Yes |
|---|---|
| Azimuth Angle | 180 |
| DC Net Capacity | 26 MW |
| Crystalline Silicon | Yes |
| Net Metering Agreement | No |
| Virtual Net Metering Agreement | No |
Rio Bravo Solar 1 LLC Plant Owners
| Owner Name | Address | Ownership |
|---|---|---|
| Leeward Asset Management, LLC | 6688 N. Central Expressway, Suite 500, Dallas, TX 75206 | 100.00% |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #1153 | Lone Valley Solar Park II LLC | Lucerne Valley, CA | 53.1 GWh |
| #1154 | Lockheed Martin Palmdale Solar PV | Palmdale, CA | 53.0 GWh |
| #1155 | East Nash PV2 | Spring Hope, NC | 53.0 GWh |
| #1156 | Barilla Solar | Fort Stockton, TX | 52.9 GWh |
| #1157 | Caden Energix Hickory LLC | Chesapeake, VA | 52.7 GWh |
| #1158 | Solar Oasis LLC | Palmdale, CA | 52.7 GWh |
| #1159 | Portal Ridge Solar B, LLC | Lancaster, CA | 52.7 GWh |
| #1160 | SEPV Mojave West | Mojave, CA | 52.7 GWh |
| #1161 | CED Ducor 1 | Ducor, CA | 52.3 GWh |
| #1162 | Western Antelope Blue Sky B | Lancaster, CA | 52.2 GWh |
| #1164 | Mountain View Solar | North Las Vegas, NV | 51.9 GWh |
| #1165 | Atwell Island West Solar | Alpaugh, CA | 51.9 GWh |
| #1166 | CED Ducor 4 | Ducor, CA | 51.8 GWh |
| #1167 | Baxley | Baxley, GA | 51.7 GWh |
| #1168 | Rio Bravo Solar II LLC | McKittrick, CA | 51.7 GWh |
| #1169 | CED Ducor 2 | Ducor, CA | 51.6 GWh |
| #1170 | Fort Gordon Solar Facility | Fort Gordon, GA | 51.4 GWh |
| #1171 | Cascade Solar | Joshua Tree, CA | 51.4 GWh |
| #1172 | RE Rosamond One LLC | Rosamond, CA | 51.2 GWh |
| #1173 | RE Gaskell West 3 LLC | Rosamond, CA | 50.8 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Rio Bravo Solar 1 LLC.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| ABEC #2 dba West-Star Dairy | Buttonwillow, CA | 8.1 GWh | 14.6 mi |
| Berry NMW Cogens | Bakersfield, CA | 75.7 GWh | 8.5 mi |
| California Valley Solar Ranch | California Valley, CA | 558.7 GWh | 14.7 mi |
| Chevron - Lost Hills Hybrid | Lost Hills, CA | 62.6 GWh | 14.1 mi |
| Cottonwood Solar, LLC (Goose Lake) | Lost Hills, CA | 29.9 GWh | 13.6 mi |
| Cymric 31X Cogen | McKittrick, CA | 17.5 GWh | 3.8 mi |
| Cymric 36W Cogen | McKittrick, CA | 53.4 GWh | 3.7 mi |
| Cymric 6Z Cogen | McKittrick, CA | 26.6 GWh | 5.3 mi |
| Dome Project | Fellows, CA | 48.4 GWh | 14.6 mi |
| Elk Hills Cogen | Tupman, CA | 99.0 GWh | 5.3 mi |
| La Paloma Generating Plant | McKittrick, CA | 1.4 TWh | 9.8 mi |
| McKittrick Cogen | McKittrick, CA | 61.2 GWh | 7 mi |
| McKittrick Limited | Bakersfield, CA | 3.5 GWh | 6.8 mi |
| Midway Sunset Cogen | Fellows, CA | 11.4 GWh | 13.4 mi |
| Pumpjack Solar I | McKittrick, CA | 50.6 GWh | 8.4 mi |
| Rio Bravo Solar II LLC | McKittrick, CA | 51.7 GWh | 3 mi |
| South Belridge Cogeneration Facility | McKittrick, CA | 477.5 GWh | 2.1 mi |
| Welport Lease Project | McKittrick, CA | 33.7 GWh | 4.4 mi |
| Wonderful Huller & Shelling | Lost Hills, CA | 3.7 GWh | 12.6 mi |
| Wonderful Orchards - Belridge | Lost Hills, CA | 12.4 GWh | 6.9 mi |