Lapetus
7351 Northwest 2001, Andrews, TX 79714Plant Summary Information
Lapetus is ranked #60 out of 150 solar farms in Texas in terms of total annual net electricity generation.
Lapetus generated 41.5 GWh during the 3-month period between November 2023 to February 2024.
Plant Name | Lapetus |
---|---|
Utility Name | Duke Energy Renewables Services |
Location | Andrews County, TX |
Initial Operation Date | December 2019 |
Last Update | Feb 2024 |
Annual Generation | 203.0 GWh |
Annual Consumption | 692.5 k MMBtu |
Ranked #2,341 out of 11,455 Power Plants Nationwide | |
Ranked #238 out of 5,173 Solar Power Plants Nationwide | |
Ranked #379 out of 726 Texas Power Plants | |
Ranked #60 out of 150 Texas Solar Power Plants | |
Fuel Types | Solar |
Previous Operator |
Lapetus Energy Project LLC (2018 to 2021) Duke Energy Renewables Services (2022 to 2022) |
Map of Lapetus
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Lapetus.
Monthly Net Generation for Lapetus
Lapetus Details
Summary Information | |
---|---|
Plant Name | Lapetus (62448) |
Plant Address | 7351 Northwest 2001 Andrews, TX 79714 |
Utility | Duke Energy Renewables Services (65411) |
Latitude, Longitude | 32.46005, -102.67281 |
Generation Dates on File | Dec 2019 to Feb 2024 |
Initial Operation Date | December 2019 |
Annual Generation | 203.0 GWh |
Fuel Types | Solar |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | TRE |
Balancing Authority | Electric Reliability Council of Texas, Inc. (ERCO) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | |
Transmission / Distribution Owner | Oncor Electric Delivery Company LLC (44372) TX |
Grid Voltage | 138.00 kV |
Energy Storage | No |
Generator LAP Details Operating December 2019
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Wholly Owned by Other Entity |
Nameplate Capacity | 100 MW |
Summer Capacity | 100 MW |
Winter Capacity | 100 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | December 2019 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Solar |
Solar Details | |
Single Axis Tracking | Yes |
---|---|
Azimuth Angle | 180 |
DC Net Capacity | 133 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | No |
Lapetus Plant Owners
Owner Name | Address | Ownership |
---|---|---|
Lapetus Energy Project, LLC | 550 S. Caldwell Street, NAS09, Suite 925, Charlotte, NC 28202 | 100.00% |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#228 | Oberon II Solar Project | Desert Center, CA | 201.9 GWh |
#229 | Wagyu | Damon, TX | 206.8 GWh |
#230 | Aulander Holloman Solar, LLC | Aulander, NC | 206.4 GWh |
#231 | Clover Creek Solar Community Solar | Mona, UT | 206.3 GWh |
#232 | Techren Solar I LLC | Boulder, NV | 205.7 GWh |
#233 | Two Creeks Solar | Two Rivers, WI | 205.1 GWh |
#234 | Granite Mountain Solar East, LLC | Cedar City, UT | 205.1 GWh |
#235 | Solverde 1 | Lancaster, CA | 204.8 GWh |
#236 | Playa Solar 1, LLC | North Las Vegas, NV | 203.4 GWh |
#237 | North Star Solar Project | North Branch, MN | 203.0 GWh |
#239 | OETN1 | Obion, TN | 200.8 GWh |
#240 | Desert Harvest, LLC | Desert Center, CA | 200.3 GWh |
#241 | Lancaster Solar GA | Arlington, GA | 197.9 GWh |
#242 | Sadler Solar | Emporia, VA | 197.7 GWh |
#243 | Water Strider Solar | Nathalie, VA | 196.2 GWh |
#244 | Iron Springs Solar, LLC | Cedar City, UT | 195.8 GWh |
#245 | Pioneer Solar (CO), LLC | Bennett, CO | 194.8 GWh |
#246 | Longbow Solar, LLC | Liverpool, TX | 194.0 GWh |
#247 | Sunflower County | Ruleville, MS | 191.1 GWh |
#248 | Southfork Solar | Parrish, FL | 190.8 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Lapetus.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
2W Permian Solar Project Hybrid | Andrews, TX | 972.4 GWh | 25.2 mi |
Bakke | Andrews, TX | 491.0 MWh | 13.7 mi |
Ector County Energy Center | Goldsmith, TX | 120.8 GWh | 27.5 mi |
Frankel | Andrews, TX | 287.1 MWh | 8.4 mi |
Goldsmith | Goldsmith, TX | 424.3 MWh | 33.6 mi |
Jumbo Hill Wind Project | Andrews, TX | 635.0 GWh | 16.9 mi |
Maddox | Hobbs, NM | 733.7 GWh | 40.6 mi |
Mustang Station | Denver City, TX | 2.2 TWh | 35.7 mi |
Mustang Station Unit 4 | Denver City, TX | 822.5 GWh | 35.8 mi |
N. Mary Francis | Odessa, TX | 495.0 MWh | 39.8 mi |
Notrees Windpower Hybrid | Goldsmith, TX | 273.1 GWh | 33.4 mi |
Oxy Renewable Energy - Goldsmith | Goldsmith, TX | 45.5 GWh | 31.8 mi |
Prospero Solar | Andrews, TX | 777.8 GWh | 15.4 mi |
Prospero Solar II | Andrews, TX | 721.2 GWh | 16.2 mi |
SPS1 Dollarhide | Jal, NM | 23.6 GWh | 35.6 mi |
SPS2 Jal | Jal, NM | 23.6 GWh | 35.4 mi |
SPS3 Lea | Eunice, NM | 21.3 GWh | 37.9 mi |
SPS4 Monument | Monument, NM | 23.4 GWh | 39.8 mi |
Tumbleweed | Andrews, TX | 511.0 MWh | 10.1 mi |
Wasson CO2 Removal Plant | Denver City, TX | 137.6 GWh | 38.3 mi |