Lapetus
7351 Northwest 2001, Andrews, TX 79714Plant Summary Information
Lapetus is ranked #106 out of 215 solar farms in Texas in terms of total annual net electricity generation.
Lapetus generated 39.2 GWh during the 3-month period between September 2025 to December 2025.
| Plant Name | Lapetus |
|---|---|
| Utility Name | Duke Energy Renewables Services |
| Location | Andrews County, TX |
| Initial Operation Date | December 2019 |
| Last Update | Dec 2025 |
| Annual Generation | 221.1 GWh |
| Annual Consumption | 797.1 k MMBtu |
| Ranked #2,356 out of 12,613 Power Plants Nationwide | |
| Ranked #378 out of 6,463 Solar Power Plants Nationwide | |
| Ranked #428 out of 816 Texas Power Plants | |
| Ranked #106 out of 215 Texas Solar Power Plants | |
| Fuel Types | Solar |
| Previous Operator |
Lapetus Energy Project LLC (2018 to 2021) Duke Energy Renewables Services (2022 to 2024) |
Map of Lapetus
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Lapetus.
Monthly Net Generation for Lapetus
Monthly Plant Fuel Consumption for Lapetus
Lapetus Details
| Summary Information | |
|---|---|
| Plant Name | Lapetus (62448) |
| Plant Address | 7351 Northwest 2001, Andrews, TX 79714 |
| Utility | Duke Energy Renewables Services (65411) |
| Latitude, Longitude | 32.46005, -102.67281 |
| Generation Dates on File | Dec 2019 to Dec 2025 |
| Initial Operation Date | December 2019 |
| Annual Generation | 221.1 GWh |
| Fuel Types | Solar |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | TRE |
| Balancing Authority | Electric Reliability Council of Texas, Inc. (ERCO) |
| NAICS Code | Utilities (22) |
| Sector | IPP Non-CHP (2) |
| Water Source | |
| Ash Impoundment | |
| Transmission / Distribution Owner | Oncor Electric Delivery Company LLC (44372) TX |
| Grid Voltage | 138.00 kV |
| Energy Storage | No |
Generator LAP Details Operating December 2019
| Technology | Solar Photovoltaic |
|---|---|
| Prime Mover | Photovoltaic |
| Ownership | Wholly Owned by Other Entity |
| Nameplate Capacity | 100 MW |
| Summer Capacity | 100 MW |
| Winter Capacity | 100 MW |
| Uprate/Derate Completed | No |
|---|---|
| Status | Operating |
| First Operation Date | December 2019 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Solar |
| Solar Details | |
| Single Axis Tracking | Yes |
|---|---|
| Azimuth Angle | 180 |
| DC Net Capacity | 133 MW |
| Crystalline Silicon | Yes |
| Net Metering Agreement | No |
| Virtual Net Metering Agreement | No |
Lapetus Plant Owners
| Owner Name | Address | Ownership |
|---|---|---|
| Lapetus Energy Project, LLC | 550 S. Caldwell Street, NAS09, Suite 925, Charlotte, NC 28202 | 100.00% |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #368 | Albemarle Beach Solar | Roper, NC | 226.7 GWh |
| #369 | Alamo 6 | Fort Stockton, TX | 226.3 GWh |
| #370 | Assembly Solar II LLC | Lennon, MI | 225.9 GWh |
| #371 | Three Peaks Power | Cedar City, UT | 225.8 GWh |
| #372 | BPL Files Solar | Itasca, TX | 224.7 GWh |
| #373 | Butler Solar Project 103 | Butler, GA | 224.1 GWh |
| #374 | Techren Solar I LLC | Boulder, NV | 224.1 GWh |
| #375 | Carvers Creek Solar | Gloucester, VA | 224.0 GWh |
| #376 | Lamesa Solar | Lamesa, TX | 223.3 GWh |
| #377 | Bartonsville Energy Facility, LLC | Stephens, VA | 222.6 GWh |
| #379 | Fish Springs | Reno, NV | 217.5 GWh |
| #380 | Prairie State Solar Project | Swanwick Township, IL | 220.4 GWh |
| #381 | SR Clay, LLC | Fort Gaines, GA | 219.9 GWh |
| #382 | Powell Creek Solar | Miller City, OH | 219.8 GWh |
| #383 | Briar Creek Solar 1 | Corsicana, TX | 219.5 GWh |
| #384 | East Pecos Solar | McCamey, TX | 219.4 GWh |
| #385 | Enterprise Solar, LLC | Newcastle, UT | 219.3 GWh |
| #386 | Ross County Solar, LLC | Greenfield, OH | 218.6 GWh |
| #387 | Henrietta Solar Project | Lemoore, CA | 218.0 GWh |
| #388 | Calhoun County Solar Project | Sheridan Township, MI | 217.4 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Lapetus.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| 2W Permian Solar Project Hybrid | Andrews, TX | 1.0 TWh | 25.2 mi |
| Bakke | Andrews, TX | 221.0 MWh | 13.7 mi |
| Ector County Energy Center | Goldsmith, TX | 648.7 GWh | 27.5 mi |
| Frankel | Andrews, TX | 165.0 MWh | 8.4 mi |
| Goldsmith | Goldsmith, TX | 184.0 MWh | 33.6 mi |
| Jumbo Hill Wind Project | Andrews, TX | 598.9 GWh | 16.9 mi |
| Maddox | Hobbs, NM | 571.9 GWh | 40.6 mi |
| Mustang Station | Denver City, TX | 2.5 TWh | 35.7 mi |
| Mustang Station Unit 4 | Denver City, TX | 1.7 TWh | 35.8 mi |
| N. Mary Francis | Odessa, TX | 216.0 MWh | 39.8 mi |
| Notrees Windpower Hybrid | Goldsmith, TX | 237.1 GWh | 33.4 mi |
| Oxy Renewable Energy - Goldsmith | Goldsmith, TX | 40.5 GWh | 31.8 mi |
| Prospero Solar | Andrews, TX | 759.4 GWh | 15.4 mi |
| Prospero Solar II | Andrews, TX | 667.0 GWh | 16.2 mi |
| SPS1 Dollarhide | Jal, NM | 23.0 GWh | 35.6 mi |
| SPS2 Jal | Jal, NM | 21.1 GWh | 35.4 mi |
| SPS3 Lea | Eunice, NM | 23.0 GWh | 37.9 mi |
| SPS4 Monument | Monument, NM | 22.9 GWh | 39.8 mi |
| Tumbleweed | Andrews, TX | 200.0 MWh | 10.1 mi |
| Wasson CO2 Removal Plant | Denver City, TX | 145.6 GWh | 38.3 mi |