Jordanelle Dam Hydroelectric Project
7000 North Old Hwy 40, Heber, UT 84032Plant Summary Information
Jordanelle Dam Hydroelectric Project is ranked #2 out of 25 hydroelectric power plants in Utah in terms of total annual net electricity generation.
Jordanelle Dam Hydroelectric Project is comprised of 2 generators and generated 5.3 GWh during the 3-month period between September 2025 to December 2025.
| Plant Name | Jordanelle Dam Hydroelectric Project |
|---|---|
| Utility Name | Central Utah Water Conservancy District |
| Location | Wasatch County, UT |
| Initial Operation Date | July 2008 |
| Last Update | Dec 2025 |
| Annual Generation | 49.3 GWh |
| Annual Consumption | 175.2 k MMBtu |
| Ranked #4,223 out of 13,081 Power Plants Nationwide | |
| Ranked #477 out of 1,311 Water Power Plants Nationwide | |
| Ranked #51 out of 120 Utah Power Plants | |
| Ranked #2 out of 25 Utah Water Power Plants | |
| Fuel Types | Water |
Map of Jordanelle Dam Hydroelectric Project
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Jordanelle Dam Hydroelectric Project.
Monthly Net Generation for Jordanelle Dam Hydroelectric Project
Monthly Plant Fuel Consumption for Jordanelle Dam Hydroelectric Project
Jordanelle Dam Hydroelectric Project Details
| Summary Information | |
|---|---|
| Plant Name | Jordanelle Dam Hydroelectric Project (61853) |
| Plant Address | 7000 North Old Hwy 40, Heber, UT 84032 |
| Utility | Central Utah Water Conservancy District (61476) |
| Latitude, Longitude | 40.59661, -111.42359 |
| Generation Dates on File | Jan 2017 to Dec 2025 |
| Initial Operation Date | July 2008 |
| Annual Generation | 49.3 GWh |
| Fuel Types | Water |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Regulated |
| NERC Region | WECC |
| Balancing Authority | PacifiCorp - East (PACE) |
| NAICS Code | Water Supply and Irrigation Systems (22131) |
| Sector | Commercial Non-CHP (4) |
| Water Source | Provo River |
| Ash Impoundment | No |
| Transmission / Distribution Owner | Heber Light & Power Company (8366) UT |
| Grid Voltage | 12.47 kV |
| Energy Storage | No |
Generator GEN 1 Details Operating July 2008
| Technology | Conventional Hydroelectric |
|---|---|
| Prime Mover | Hydroelectric Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 6.5 MW |
| Nameplate Power Factor | 0.9 |
| Summer Capacity | 6.5 MW |
| Winter Capacity | 6.5 MW |
| Minimum Load | 2.6 MW |
| Uprate/Derate Completed | No |
|---|---|
| Status | Operating |
| First Operation Date | July 2008 |
| Combined Heat & Power | No |
| Sector Name | Commercial Non-CHP (4) |
| Energy Source | Water |
| Solid Fuel Gasification | No |
| Time From Cold Shutdown To Full Load | 10M |
Generator GEN 2 Details Operating July 2008
| Technology | Conventional Hydroelectric |
|---|---|
| Prime Mover | Hydroelectric Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 6.5 MW |
| Nameplate Power Factor | 0.9 |
| Summer Capacity | 6.5 MW |
| Winter Capacity | 6.5 MW |
| Minimum Load | 2.6 MW |
| Uprate/Derate Completed | No |
|---|---|
| Status | Operating |
| First Operation Date | July 2008 |
| Combined Heat & Power | No |
| Sector Name | Commercial Non-CHP (4) |
| Energy Source | Water |
| Solid Fuel Gasification | No |
| Time From Cold Shutdown To Full Load | 10M |
Jordanelle Dam Hydroelectric Project Plant Owners
| Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Water.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #467 | Pontook Hydro Facility | Dummer, NH | 50.9 GWh |
| #468 | French Meadows | Foresthill, CA | 50.8 GWh |
| #469 | Johnson 1 | Elwood, NE | 50.8 GWh |
| #470 | Deer Rips | Auburn, ME | 50.8 GWh |
| #471 | Nimbus | Folsom, CA | 50.6 GWh |
| #472 | E J West | Lake Luzerne, NY | 50.3 GWh |
| #473 | Crescent | Crescent, NY | 50.1 GWh |
| #474 | Pejepscot Hydroelectric Project | Topsham, ME | 49.7 GWh |
| #475 | Kingsley | Ogallala, NE | 49.4 GWh |
| #476 | Lockhart | Lockhart, SC | 49.3 GWh |
| #478 | Kilbourn | Wisconsin Dells, WI | 49.2 GWh |
| #479 | Browns Falls | Oswegatchie, NY | 49.2 GWh |
| #480 | Sturgeon | Tillson, NY | 49.1 GWh |
| #481 | South Fork Tolt | North Bend, WA | 48.6 GWh |
| #482 | Peavy Falls | Crystal Falls, MI | 48.4 GWh |
| #483 | Blake | Parishville, NY | 48.2 GWh |
| #484 | Beaver Falls | Ketchikan, AK | 48.0 GWh |
| #485 | Middle Gorge | Bishop, CA | 48.0 GWh |
| #486 | Vischer Ferry | Rexford, NY | 47.1 GWh |
| #487 | Horseshoe Bend Hydroelectric Co | Horseshoe Bend, ID | 46.8 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Jordanelle Dam Hydroelectric Project.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Bartholomew | Springville, UT | 1.6 GWh | 29.9 mi |
| BYU Central Heating Plant | Provo, UT | 115.9 GWh | 26.8 mi |
| Deer Creek (UT) | Heber, UT | 22.2 GWh | 14.4 mi |
| Echo Dam | Echo, UT | 8.6 GWh | 25.4 mi |
| Gadsby | Salt Lake City, UT | 191.3 GWh | 29 mi |
| Granite | Salt lake City, UT | 4.2 GWh | 18.9 mi |
| Heber City | Heber City, UT | 16.5 GWh | 6.4 mi |
| HTW Plant 303 COGEN | Salt Lake City, UT | 48.2 GWh | 24.7 mi |
| Lake Creek Dam | Heber City, UT | 3.1 GWh | 9.2 mi |
| Lake Side Power Plant | Vineyard, UT | 6.3 TWh | 25.2 mi |
| Little Cottonwood | Sandy, UT | 8.6 GWh | 19.8 mi |
| Murray Turbine | Murray, UT | 220.0 MWh | 25 mi |
| Provo Power Plant | Provo, UT | 4.4 GWh | 27.5 mi |
| Salt Palace Solar Gen Plant | Salt Lake City, UT | 1.1 GWh | 27.4 mi |
| Snake Creek | Midway, UT | 3.8 GWh | 5.5 mi |
| Snowbird Power Plant | Snowbird, UT | 14.6 GWh | 12.1 mi |
| Stairs | Salt Lake City, UT | 4.1 GWh | 17.4 mi |
| Tesoro SLC Cogeneration Plant | Salt Lake City, UT | 199.9 GWh | 28.6 mi |
| Wanship | Wanship, UT | 4.9 GWh | 13.4 mi |
| Whitehead | Springville, UT | 11.4 GWh | 30.5 mi |