Jack County
3844 Henderson Ranch rd., Bridgeport, TX 76426Plant Summary Information
Jack County is ranked #15 out of 726 power plants in Texas in terms of total annual net electricity generation.
Jack County is comprised of 6 generators and generated 2.2 TWh during the 3-month period between November 2023 to February 2024.
Plant Name | Jack County |
---|---|
Utility Name | Brazos Electric Power Coop Inc |
Location | Wise County, TX |
Initial Operation Date | February 2006 |
Last Update | Feb 2024 |
Annual Generation | 6.9 TWh |
Annual Consumption | 49.5 M MMBtu |
Ranked #150 out of 11,455 Power Plants Nationwide | |
Ranked #59 out of 2,284 Natural Gas Power Plants Nationwide | |
Ranked #15 out of 726 Texas Power Plants | |
Ranked #9 out of 291 Texas Natural Gas Power Plants | |
Fuel Types | Natural Gas |
Map of Jack County
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Jack County.
Monthly Net Generation for Jack County
Jack County Details
Summary Information | |
---|---|
Plant Name | Jack County (55230) |
Plant Address | 3844 Henderson Ranch rd. Bridgeport, TX 76426 |
Utility | Brazos Electric Power Coop Inc (2172) |
Latitude, Longitude | 33.101, -97.9574 |
Generation Dates on File | Feb 2006 to Feb 2024 |
Initial Operation Date | February 2006 |
Annual Generation | 6.9 TWh |
Fuel Types | Natural Gas |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Regulated |
NERC Region | TRE |
Balancing Authority | Electric Reliability Council of Texas, Inc. (ERCO) |
NAICS Code | Utilities (22) |
Sector | Electric Utility (1) |
Water Source | Lake Bridgeport |
Ash Impoundment | Yes Lined Operating |
Transmission / Distribution Owner | Oncor Electric Delivery Company LLC (44372) TX |
Grid Voltage | 345.00 kV / 138.00 kV |
Energy Storage | No |
Natural Gas Information | |
Local Distribution Company (LDC) | ATMOS ENERGY CORPORATION |
Pipeline Name |
NATURAL GAS PL CO OF AMERICA LLC NATURAL GAS PL CO OF AMERICA LLC |
Natural Gas Storage | No |
Generator CT1 Details Operating February 2006
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Combustion Turbine Part |
Unit Code | CC01 |
Ownership | Single Owner |
Can Bypass Heat Recovery Steam Generator | No |
RTO ISO LMP Node Designation | JACKCNTY_CC1 |
RTO ISO Location Designation For Reporting Wholesale Sales Data | JACKCNTY_CT1 |
Nameplate Capacity | 170 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 165 MW |
Winter Capacity | 170 MW |
Minimum Load | 164 MW |
---|---|
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | February 2006 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Generator CT2 Details Operating February 2006
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Combustion Turbine Part |
Unit Code | CC01 |
Ownership | Single Owner |
Can Bypass Heat Recovery Steam Generator | No |
RTO ISO LMP Node Designation | JACKCNTY_CC2 |
RTO ISO Location Designation For Reporting Wholesale Sales Data | JACKCNTY_CT2 |
Nameplate Capacity | 170 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 165 MW |
Winter Capacity | 170 MW |
Minimum Load | 164 MW |
---|---|
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | February 2006 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Generator ST1 Details Operating February 2006
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Steam Part |
Unit Code | CC01 |
Ownership | Single Owner |
Duct Burners | Yes |
RTO ISO LMP Node Designation | JACKCNTY_STG |
RTO ISO Location Designation For Reporting Wholesale Sales Data | JACKCNTY_STG |
Nameplate Capacity | 300 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 290.5 MW |
Winter Capacity | 300 MW |
Minimum Load | 60 MW |
---|---|
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | February 2006 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Generator CT3 Details Operating March 2011
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Combustion Turbine Part |
Unit Code | CC02 |
Ownership | Single Owner |
Can Bypass Heat Recovery Steam Generator | No |
RTO ISO LMP Node Designation | JACKCNTY2_CC3 |
RTO ISO Location Designation For Reporting Wholesale Sales Data | JACKCNTY2_CT3 |
Nameplate Capacity | 170 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 165 MW |
Winter Capacity | 170 MW |
Minimum Load | 164 MW |
---|---|
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | March 2011 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Generator CT4 Details Operating March 2011
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Combustion Turbine Part |
Unit Code | CC02 |
Ownership | Single Owner |
Can Bypass Heat Recovery Steam Generator | No |
RTO ISO LMP Node Designation | JACKCNTY2_CC4 |
RTO ISO Location Designation For Reporting Wholesale Sales Data | JACKCNTY2_CT4 |
Nameplate Capacity | 170 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 165 MW |
Winter Capacity | 170 MW |
Minimum Load | 164 MW |
---|---|
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | March 2011 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Generator ST2 Details Operating March 2011
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Steam Part |
Unit Code | CC02 |
Ownership | Single Owner |
Duct Burners | Yes |
RTO ISO LMP Node Designation | JACKCNTY2_ST2 |
RTO ISO Location Designation For Reporting Wholesale Sales Data | JACKCNTY2_ST2 |
Nameplate Capacity | 300 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 290.5 MW |
Winter Capacity | 300 MW |
Minimum Load | 60 MW |
---|---|
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | March 2011 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Jack County Plant Owners
Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#49 | Brunswick County Power Station | Freeman, VA | 7.3 TWh |
#50 | Tenaska Westmoreland Generating Station | Smithton, PA | 7.2 TWh |
#51 | Manatee | Parrish, FL | 7.2 TWh |
#52 | Seminole (FL) | Palatka, FL | 10.8 TWh |
#53 | Oregon Clean Energy Center | Oregon, OH | 7.1 TWh |
#54 | Hamilton Patriot Generation Plant | Montgomery, PA | 7.0 TWh |
#55 | Turkey Point | Homestead, FL | 21.7 TWh |
#56 | Lake Side Power Plant | Vineyard, UT | 7.0 TWh |
#57 | P L Bartow | St. Petersburg, FL | 6.9 TWh |
#58 | Lee Combined Cycle Plant | Goldsboro, NC | 6.9 TWh |
#60 | Clean Energy Future-Lordstown, LLC | Lordstown, OH | 6.8 TWh |
#61 | E B Harris Electric Generating Plant | Autaugaville, AL | 6.7 TWh |
#62 | W S Lee | Williamston, SC | 6.7 TWh |
#63 | Dania Beach 7 | Ft. Lauderdale, FL | 6.7 TWh |
#64 | Hamilton Liberty | Towanda, PA | 6.6 TWh |
#65 | Marcus Hook Energy LP | Marcus Hook, PA | 6.5 TWh |
#66 | Acadia Energy Center | Eunice, LA | 6.5 TWh |
#67 | Magnolia Power Plant | Ashland, MS | 6.5 TWh |
#68 | Cottonwood Energy Project | Deweyville, TX | 6.4 TWh |
#69 | Hickory Run Energy Station | New Castle, PA | 6.4 TWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Jack County.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Barton Chapel Wind Farm | Jacksboro, TX | 263.5 GWh | 21.7 mi |
Bridgeport Gas Processing Plant | Bridgeport, TX | 46.7 GWh | 11.1 mi |
Denton Energy Center | Denton, TX | 319.8 GWh | 44 mi |
Graham | Graham, TX | 167.2 GWh | 37.9 mi |
Keechi Wind | Jacksboro, TX | 460.9 GWh | 12.1 mi |
Noble Solar | Krum, TX | 616.2 GWh | 43.1 mi |
R W Miller | Palo Pinto, TX | 486.2 GWh | 36.8 mi |
Senate Wind LLC | Bryson, TX | 536.4 GWh | 24.7 mi |
Shannon Wind | Windhorst, TX | 555.9 GWh | 36.6 mi |
WAL2980 | Fort Worth, TX | 337.7 MWh | 41.4 mi |
WAL3773 | Fort Worth, TX | 347.4 MWh | 36 mi |
WAL4509 | Tarrant, TX | 313.4 MWh | 40.8 mi |
WAL5312 | Fort Worth, TX | 242.2 MWh | 44.7 mi |
WAL5316 | Saginaw, TX | 320.8 MWh | 36.3 mi |
WAL5764 | Fort Worth, TX | 273.2 MWh | 32.9 mi |
WAL940 | Westworth Village, TX | 337.1 MWh | 38.6 mi |
WAL972 | Fort Worth, TX | 49.7 MWh | 36.8 mi |
Westside Landfill Gas Recovery | Aledo, TX | 16.3 GWh | 35.6 mi |
Windthorst-2 | Archer, TX | 250.1 GWh | 41.5 mi |
Wise County Power LLC | Poolville, TX | 3.7 TWh | 4 mi |