Easton 2
8940 Glebe Park Drive, Easton, MD 21601Plant Summary Information
Easton 2 is ranked #12 out of 20 distillate fuel oil power plants in Maryland in terms of total annual net electricity generation.
Easton 2 is comprised of 8 generators and generated 1.4 GWh during the 3-month period between May 2025 to August 2025.
| Plant Name | Easton 2 |
|---|---|
| Utility Name | Easton Utilities Comm |
| Location | Talbot County, MD |
| Initial Operation Date | March 1978 |
| Last Update | Aug 2025 |
| Annual Generation | 2.6 GWh |
| Annual Consumption | 40.0 k MMBtu |
| Ranked #9,807 out of 12,539 Power Plants Nationwide | |
| Ranked #276 out of 1,236 Distillate Fuel Oil Power Plants Nationwide | |
| Ranked #133 out of 200 Maryland Power Plants | |
| Ranked #12 out of 20 Maryland Distillate Fuel Oil Power Plants | |
| Fuel Types | Distillate Fuel Oil |
Map of Easton 2
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Easton 2.
Monthly Net Generation for Easton 2
Easton 2 Details
| Summary Information | |
|---|---|
| Plant Name | Easton 2 (4257) |
| Plant Address | 8940 Glebe Park Drive, Easton, MD 21601 |
| Utility | Easton Utilities Comm (5625) |
| Latitude, Longitude | 38.795, -76.07 |
| Generation Dates on File | Jan 2001 to Aug 2025 |
| Initial Operation Date | March 1978 |
| Annual Generation | 2.6 GWh |
| Fuel Types | Distillate Fuel Oil |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Regulated |
| NERC Region | RFC |
| Balancing Authority | PJM Interconnection, LLC (PJM) |
| NAICS Code | Utilities (22) |
| Sector | Electric Utility (1) |
| Water Source | Municipality |
| Ash Impoundment | No |
| Transmission / Distribution Owner | Easton Utilities Comm (5625) MD |
| Grid Voltage | 69.00 kV |
| Energy Storage | No |
Generator 21 Details Operating March 1978
| Technology | Petroleum Liquids |
|---|---|
| Prime Mover | Internal Combustion Engine |
| Ownership | Single Owner |
| Nameplate Capacity | 6.2 MW |
| Nameplate Power Factor | 0.8 |
| Summer Capacity | 6.2 MW |
| Winter Capacity | 6.2 MW |
| Minimum Load | 0.5 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | March 1978 |
| Combined Heat & Power | No |
|---|---|
| Sector Name | Electric Utility (1) |
| Energy Source | Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 1H |
| Other Planned Modifications | No |
| Multiple Fuels | No |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Generator 22 Details Operating March 1978
| Technology | Petroleum Liquids |
|---|---|
| Prime Mover | Internal Combustion Engine |
| Ownership | Single Owner |
| Nameplate Capacity | 6.2 MW |
| Nameplate Power Factor | 0.8 |
| Summer Capacity | 6.2 MW |
| Winter Capacity | 6.2 MW |
| Minimum Load | 0.5 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | March 1978 |
| Combined Heat & Power | No |
|---|---|
| Sector Name | Electric Utility (1) |
| Energy Source | Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 1H |
| Other Planned Modifications | No |
| Multiple Fuels | No |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Generator 23 Details Operating June 1989
| Technology | Petroleum Liquids |
|---|---|
| Prime Mover | Internal Combustion Engine |
| Ownership | Single Owner |
| Nameplate Capacity | 6.3 MW |
| Nameplate Power Factor | 0.8 |
| Summer Capacity | 6.3 MW |
| Winter Capacity | 6.3 MW |
| Minimum Load | 0.5 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | June 1989 |
| Combined Heat & Power | No |
|---|---|
| Sector Name | Electric Utility (1) |
| Energy Source | Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 1H |
| Other Planned Modifications | No |
| Multiple Fuels | No |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Generator 24 Details Operating June 1989
| Technology | Petroleum Liquids |
|---|---|
| Prime Mover | Internal Combustion Engine |
| Ownership | Single Owner |
| Nameplate Capacity | 6.3 MW |
| Nameplate Power Factor | 0.8 |
| Summer Capacity | 6.3 MW |
| Winter Capacity | 6.3 MW |
| Minimum Load | 0.5 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | June 1989 |
| Combined Heat & Power | No |
|---|---|
| Sector Name | Electric Utility (1) |
| Energy Source | Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 1H |
| Other Planned Modifications | No |
| Multiple Fuels | No |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Generator 201 Details Operating May 1995
| Technology | Petroleum Liquids |
|---|---|
| Prime Mover | Internal Combustion Engine |
| Ownership | Single Owner |
| Nameplate Capacity | 1.5 MW |
| Nameplate Power Factor | 0.8 |
| Summer Capacity | 1.5 MW |
| Winter Capacity | 1.5 MW |
| Minimum Load | 0.5 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | May 1995 |
| Combined Heat & Power | No |
|---|---|
| Sector Name | Electric Utility (1) |
| Energy Source | Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 1H |
| Other Planned Modifications | No |
| Multiple Fuels | No |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Generator 202 Details Operating May 1995
| Technology | Petroleum Liquids |
|---|---|
| Prime Mover | Internal Combustion Engine |
| Ownership | Single Owner |
| Nameplate Capacity | 1.5 MW |
| Nameplate Power Factor | 0.8 |
| Summer Capacity | 1.5 MW |
| Winter Capacity | 1.5 MW |
| Minimum Load | 0.5 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | May 1995 |
| Combined Heat & Power | No |
|---|---|
| Sector Name | Electric Utility (1) |
| Energy Source | Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 1H |
| Other Planned Modifications | No |
| Multiple Fuels | No |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Generator 203 Details Operating November 2004
| Technology | Petroleum Liquids |
|---|---|
| Prime Mover | Combustion Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 5.4 MW |
| Nameplate Power Factor | 0.8 |
| Summer Capacity | 4.5 MW |
| Winter Capacity | 5.1 MW |
| Minimum Load | 0.5 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | November 2004 |
| Combined Heat & Power | No |
|---|---|
| Sector Name | Electric Utility (1) |
| Energy Source | Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 1H |
| Other Planned Modifications | No |
| Multiple Fuels | No |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Generator 204 Details Operating November 2004
| Technology | Petroleum Liquids |
|---|---|
| Prime Mover | Combustion Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 5.4 MW |
| Nameplate Power Factor | 0.8 |
| Summer Capacity | 4.5 MW |
| Winter Capacity | 5.1 MW |
| Minimum Load | 0.5 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | November 2004 |
| Combined Heat & Power | No |
|---|---|
| Sector Name | Electric Utility (1) |
| Energy Source | Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 1H |
| Other Planned Modifications | No |
| Multiple Fuels | No |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Easton 2 Plant Owners
| Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Distillate Fuel Oil.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #266 | Togiak | Togiak, AK | 2.9 GWh |
| #267 | DeCordova Steam Electric Station | Granbury, TX | 36.9 GWh |
| #268 | Selawik | Selawik, AK | 2.8 GWh |
| #269 | Charles City | Providence Forge, VA | 47.9 GWh |
| #270 | Lauderdale | Ft. Lauderdale, FL | 244.0 GWh |
| #271 | Crisfield | Crisfield, MD | 2.7 GWh |
| #272 | Wake County LFG Facility | Apex, NC | 54.9 GWh |
| #273 | Schofield Generating Station | Schofield Barracks, HI | 7.3 GWh |
| #274 | King & Queen | Little Plymouth, VA | 59.9 GWh |
| #275 | John P Madgett | Alma, WI | 1.2 TWh |
| #277 | Piqua Power Plant | Piqua, OH | 2.6 GWh |
| #278 | San Miguel | Christine, TX | 1.4 TWh |
| #279 | Hamlet Generating Facility | Hamlet, NC | 144.9 GWh |
| #280 | Glenwood | Glenwood Landing, NY | 2.6 GWh |
| #281 | Wyodak | Gillette, WY | 2.0 TWh |
| #282 | Cleveland Cnty Generating Facility | Kings Mountain, NC | 712.0 GWh |
| #283 | Chevak | Chevak, AK | 2.5 GWh |
| #284 | False Island | Thorne Bay, AK | 2.5 GWh |
| #285 | Gwitchyaa Zhee | Fort Yukon, AK | 2.5 GWh |
| #286 | Troy Energy LLC | Luckey, OH | 988.6 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Easton 2.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Ameresco Delaware Central | Sandtown, DE | 23.3 GWh | 24.9 mi |
| Bd of Educ of Queen Anne's Cnty, Cnty HS | Centreville, MD | 2.6 GWh | 16.7 mi |
| Bluegrass Solar | Church Hill, MD | 154.2 GWh | 27.2 mi |
| Chesapeake College | Wye Mills, MD | 2.4 GWh | 11 mi |
| Chester Woods Point Solar, LLC CSG | Chester, MD | 3.9 GWh | 16.3 mi |
| Church Hill | Church Hill, MD | 6.7 GWh | 22 mi |
| CNE at Cambridge MD | Cambridge, MD | 5.5 GWh | 19.5 mi |
| Easton | Easton, MD | 1.6 GWh | 1.2 mi |
| Federalsburg Energy Storage 1 LLC | Federaslburg, MD | 1.3 GWh | 22.1 mi |
| Heimlich Solar | Greenwood, DE | 9.2 GWh | 25 mi |
| MEBA | Easton, MD | 2.4 GWh | 4 mi |
| Mustang One | Cambridge, MD | 3.0 GWh | 15.9 mi |
| OER Checkerspot | Tracy's Landing, MD | 2.7 GWh | 27.2 mi |
| Perdue Bridgeville Photovoltaic | Bridgeville, DE | 2.0 GWh | 25.3 mi |
| Queen Anne's County | Centreville, MD | 2.6 GWh | 16.6 mi |
| Rock Hall | Rock Hall, MD | 1.6 GWh | 25.7 mi |
| Todd Solar | Hurlock, MD | 33.9 GWh | 17.8 mi |
| UMCES Ground Mount | Cambridge, MD | 3.5 GWh | 15.1 mi |
| Vienna Operations | Vienna, MD | 4.6 GWh | 25.1 mi |
| Wye Mills VNEM CSG | Queen Anne, MD | 18.5 GWh | 10.1 mi |