Dunlap TP 1
394 Canal Lane, New Brannfels, TX 78155Plant Summary Information
Dunlap TP 1 is ranked #15 out of 15 hydroelectric power plants in Texas in terms of total annual net electricity generation.
Dunlap TP 1 is comprised of 2 generators and generated 618.0 MWh during the 3-month period between September 2023 to December 2023.
Plant Name | Dunlap TP 1 |
---|---|
Utility Name | Guadalupe Blanco River Authority |
Location | Guadalupe County, TX |
Initial Operation Date | January 1927 |
Last Update | Dec 2023 |
Annual Generation | 698.0 MWh |
Annual Consumption | 2.4 k MMBtu |
Ranked #10,771 out of 11,623 Power Plants Nationwide | |
Ranked #1,224 out of 1,242 Water Power Plants Nationwide | |
Ranked #640 out of 769 Texas Power Plants | |
Ranked #15 out of 15 Texas Water Power Plants | |
Fuel Types | Water |
Map of Dunlap TP 1
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Dunlap TP 1.
Monthly Net Generation for Dunlap TP 1
Dunlap TP 1 Details
Summary Information | |
---|---|
Plant Name | Dunlap TP 1 (3582) |
Plant Address | 394 Canal Lane, New Brannfels, TX 78155 |
Utility | Guadalupe Blanco River Authority (7751) |
Latitude, Longitude | 29.64019, -98.04593 |
Generation Dates on File | Jan 2001 to Dec 2023 |
Initial Operation Date | January 1927 |
Annual Generation | 698.0 MWh |
Fuel Types | Water |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Regulated |
NERC Region | TRE |
Balancing Authority | Electric Reliability Council of Texas, Inc. (ERCO) |
NAICS Code | Utilities (22) |
Sector | Electric Utility (1) |
Water Source | Guadalupe River |
Ash Impoundment | No |
Transmission / Distribution Owner | Guadalupe Valley Elec Coop Inc (7752) TX |
Grid Voltage | 34.50 kV |
Energy Storage | No |
Generator 1 Details Operating January 1927
Technology | Conventional Hydroelectric |
---|---|
Prime Mover | Hydroelectric Turbine |
Ownership | Single Owner |
Nameplate Capacity | 1.8 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 1.8 MW |
Winter Capacity | 1.8 MW |
Minimum Load | 1.7 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | January 1927 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Water |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Generator 2 Details Operating January 1927
Technology | Conventional Hydroelectric |
---|---|
Prime Mover | Hydroelectric Turbine |
Ownership | Single Owner |
Nameplate Capacity | 1.8 MW |
Nameplate Power Factor | 0.8 |
Summer Capacity | 1.8 MW |
Winter Capacity | 1.8 MW |
Minimum Load | 1.7 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | January 1927 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Water |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Dunlap TP 1 Plant Owners
Owner Name | Address | Generator | Ownership |
---|---|---|---|
We couldn't locate any owners for this plant |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Water.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#1214 | Pelican | Pelican, AK | 1.6 GWh |
#1215 | Theresa Plant | Theresa, NY | 1.3 GWh |
#1216 | Marshall (MI) | Marshall, MI | 611.0 MWh |
#1217 | Salida | Salida, CO | 1.1 GWh |
#1218 | Halifax | Halifax, VA | 1.1 GWh |
#1219 | Tacoma | Durango, CO | 957.0 MWh |
#1220 | Timothy Lake Powerhouse | Estacada, OR | 946.0 MWh |
#1221 | W K Sanders | Hyde Park, VT | 915.0 MWh |
#1222 | Longfalls Facility | West Carthage, NY | 881.0 MWh |
#1223 | Walden | Walden, NY | 840.0 MWh |
#1225 | Kaweah 2 | Three Rivers, CA | 693.0 MWh |
#1226 | Talcville | Edwards, NY | 643.0 MWh |
#1227 | Granite Falls | Granite Falls, MN | 604.0 MWh |
#1228 | Redwood Falls | Redwood Falls, MN | 880.0 MWh |
#1229 | Santa Ana 3 | Highlands, CA | 424.0 MWh |
#1230 | Springville Hydroelectric | Camarillo, CA | 363.0 MWh |
#1231 | Barron | Barron, WI | 349.0 MWh |
#1232 | Rocky Brook Hydroelectric | Brinnon, WA | 219.0 MWh |
#1233 | St Louis | St. Louis, MI | 175.0 MWh |
#1234 | Georgia-Pacific Big Island | Big Island, VA | 53.4 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Dunlap TP 1.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Arthur Von Rosenberg | Elmendorf, TX | 2.9 TWh | 33.4 mi |
Blue Wing Solar Energy Generation | San Antonio, TX | 17.8 GWh | 31.5 mi |
CPS 1 Community Solar | Adkins, TX | 1.8 GWh | 22.6 mi |
FELPS 1 - Calaveras | Floresville, TX | 2.1 GWh | 31.5 mi |
FELPS 2 - Calaveras | Floresville, TX | 2.1 GWh | 31.5 mi |
Guadalupe Generating Station | Marion, TX | 6.3 TWh | 5.9 mi |
Hays Energy Project | San Marcos, TX | 5.3 TWh | 10.3 mi |
HEB_CPSSADC | San Antonio, TX | 1.2 GWh | 24.4 mi |
IKEA Live Oak Rooftop PV System | Live Oak, TX | 2.1 GWh | 16.5 mi |
J K Spruce | San Antonio, TX | 6.0 TWh | 28.2 mi |
Mesquite Creek LFGTE Project | New Braunfels, TX | 21.4 GWh | 6.8 mi |
Niagara Bottling - Seguin | Seguin, TX | 8.1 GWh | 5.4 mi |
O W Sommers | San Antonio, TX | 1.9 TWh | 28.4 mi |
OCI Alamo 2, LLC | Converse, TX | 9.5 GWh | 20.8 mi |
OCI Alamo 3 LLC | San Antonio, TX | 10.3 GWh | 18.8 mi |
OCI Alamo 4, LLC | Brackettville, TX | 78.9 GWh | 18.8 mi |
OCI Alamo Solar I Hybrid | San Antonio, TX | 88.3 GWh | 35 mi |
Rio Nogales Power Project | Seguin, TX | 5.2 TWh | 5.4 mi |
SunE CPS1 LLC | San Antonio, TX | 9.0 GWh | 35.3 mi |
V H Braunig | Elmendorf, TX | 2.3 TWh | 33.3 mi |