Arthur Von Rosenberg
15290 Streich Rd., Elmendorf, TX 78112Plant Summary Information
Arthur Von Rosenberg is ranked #39 out of 799 power plants in Texas in terms of total annual net electricity generation.
Arthur Von Rosenberg is comprised of 3 generators and generated 1.1 TWh during the 3-month period between June 2025 to September 2025.
| Plant Name | Arthur Von Rosenberg |
|---|---|
| Utility Name | City of San Antonio - (TX) |
| Location | Bexar County, TX |
| Initial Operation Date | June 2000 |
| Last Update | Sep 2025 |
| Annual Generation | 3.4 TWh |
| Annual Consumption | 25.7 M MMBtu |
| Ranked #340 out of 12,539 Power Plants Nationwide | |
| Ranked #188 out of 2,243 Natural Gas Power Plants Nationwide | |
| Ranked #39 out of 799 Texas Power Plants | |
| Ranked #29 out of 314 Texas Natural Gas Power Plants | |
| Fuel Types | Natural Gas |
Map of Arthur Von Rosenberg
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Arthur Von Rosenberg.
Monthly Net Generation for Arthur Von Rosenberg
Arthur Von Rosenberg Details
| Summary Information | |
|---|---|
| Plant Name | Arthur Von Rosenberg (7512) |
| Plant Address | 15290 Streich Rd., Elmendorf, TX 78112 |
| Utility | City of San Antonio - (TX) (16604) |
| Latitude, Longitude | 29.25705, -98.38405 |
| Generation Dates on File | Jan 2001 to Sep 2025 |
| Initial Operation Date | June 2000 |
| Annual Generation | 3.4 TWh |
| Fuel Types | Natural Gas |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Regulated |
| NERC Region | TRE |
| Balancing Authority | Electric Reliability Council of Texas, Inc. (ERCO) |
| NAICS Code | Utilities (22) |
| Sector | Electric Utility (1) |
| Water Source | Braunig Lake |
| Ash Impoundment | No |
| Transmission / Distribution Owner | City of San Antonio - (TX) (16604) TX |
| Grid Voltage | 345.00 kV |
| Energy Storage | No |
| Natural Gas Information | |
| Pipeline Name | ENTERPRISE TEXAS PIPELINE |
| Natural Gas Storage | No |
Generator 1 Details Operating June 2000
| Technology | Natural Gas Fired Combined Cycle |
|---|---|
| Prime Mover | Combined Cycle Combustion Turbine Part |
| Unit Code | CC1 |
| Ownership | Single Owner |
| Can Bypass Heat Recovery Steam Generator | No |
| RTO ISO LMP Node Designation | BRA_AVR_CST1 |
| RTO ISO Location Designation For Reporting Wholesale Sales Data | BRA_AVR_CST1 |
| Nameplate Capacity | 187.5 MW |
| Nameplate Power Factor | 0.9 |
| Summer Capacity | 164 MW |
| Winter Capacity | 176 MW |
| Minimum Load | 90 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | June 2000 |
|---|---|
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Natural Gas |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 12H |
| Planned Net Summer Capacity Uprate | 10 MW |
| Planned Net Winter Capacity Uprate | 20 MW |
| Planned Uprate | January 2025 |
| Multiple Fuels | No |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Generator 2 Details Operating June 2000
| Technology | Natural Gas Fired Combined Cycle |
|---|---|
| Prime Mover | Combined Cycle Combustion Turbine Part |
| Unit Code | CC1 |
| Ownership | Single Owner |
| Can Bypass Heat Recovery Steam Generator | No |
| RTO ISO LMP Node Designation | BRA_AVR1_CT2 |
| RTO ISO Location Designation For Reporting Wholesale Sales Data | BRA_AVR1_CT2 |
| Nameplate Capacity | 187.5 MW |
| Nameplate Power Factor | 0.9 |
| Summer Capacity | 164 MW |
| Winter Capacity | 176 MW |
| Minimum Load | 90 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | June 2000 |
|---|---|
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Natural Gas |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 12H |
| Planned Net Summer Capacity Uprate | 10 MW |
| Planned Net Winter Capacity Uprate | 20 MW |
| Planned Uprate | January 2025 |
| Multiple Fuels | No |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Generator 3 Details Operating June 2000
| Technology | Natural Gas Fired Combined Cycle |
|---|---|
| Prime Mover | Combined Cycle Steam Part |
| Unit Code | CC1 |
| Ownership | Single Owner |
| Duct Burners | Yes |
| RTO ISO LMP Node Designation | BRA_AVR_CST1 |
| RTO ISO Location Designation For Reporting Wholesale Sales Data | BRA_AVR_CST1 |
| Nameplate Capacity | 200 MW |
| Nameplate Power Factor | 0.9 |
| Summer Capacity | 190 MW |
| Winter Capacity | 197 MW |
| Minimum Load | 60 MW |
| Uprate/Derate Completed | No |
|---|---|
| Status | Operating |
| First Operation Date | June 2000 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Natural Gas |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 12H |
| Multiple Fuels | No |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Arthur Von Rosenberg Plant Owners
| Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #178 | Washington Energy Facility | Beverly, OH | 3.5 TWh |
| #179 | Woodbridge Energy Center | Keasbey, NJ | 3.5 TWh |
| #180 | Bethlehem Energy Center | Glenmont, NY | 3.5 TWh |
| #181 | Perryville Power Station | Sterlington, LA | 3.5 TWh |
| #182 | Cherokee | Denver, CO | 3.5 TWh |
| #183 | ANP Bellingham Energy Project | Bellingham, MA | 3.5 TWh |
| #184 | McWilliams | Gantt, AL | 3.5 TWh |
| #185 | Harquahala Generating Project | Tonopah, AZ | 3.5 TWh |
| #186 | High Desert Power Plant | Victorville, CA | 3.5 TWh |
| #187 | Bridgeport Station | Bridgeport, CT | 3.5 TWh |
| #189 | Arlington Valley Energy Facility | Arlington, AZ | 3.4 TWh |
| #190 | Dearborn Industrial Generation | Dearborn, MI | 4.0 TWh |
| #191 | Central Alabama Generating Station | Billingsley, AL | 3.4 TWh |
| #192 | Jasper | Hardeeville, SC | 3.4 TWh |
| #193 | Grays Harbor Energy Facility | Elma, WA | 3.4 TWh |
| #194 | Marshalltown Generating Station | Marshalltown, IA | 3.4 TWh |
| #195 | Athens Generating Plant | Athens, NY | 3.4 TWh |
| #196 | Jack Fusco Energy Center | Thompsons, TX | 3.4 TWh |
| #197 | L V Sutton Combined Cycle | Wilmington, NC | 3.4 TWh |
| #198 | Rhode Island State Energy Center | Johnston, RI | 3.3 TWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Arthur Von Rosenberg.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Blue Wing Solar Energy Generation | San Antonio, TX | 19.1 GWh | 3.4 mi |
| Covel Gardens Gas Recovery | San Antonio, TX | 20.6 GWh | 17.4 mi |
| CPS 1 Community Solar | Adkins, TX | 1.8 GWh | 10.8 mi |
| FELPS 1 - Calaveras | Floresville, TX | 1.8 GWh | 8.4 mi |
| FELPS 2 - Calaveras | Floresville, TX | 1.9 GWh | 8.4 mi |
| FELPS 6- Floresville West | Floresville, TX | 2.1 GWh | 14.3 mi |
| FELPS 7- Floresville West | Floresville, TX | 2.1 GWh | 14.3 mi |
| HEB_CPSSADC | San Antonio, TX | 944.0 MWh | 11.2 mi |
| IKEA Live Oak Rooftop PV System | Live Oak, TX | 2.1 GWh | 17.4 mi |
| J K Spruce | San Antonio, TX | 6.4 TWh | 5.3 mi |
| Leon Creek | San Antonio, TX | 227.5 GWh | 13.3 mi |
| Nelson Gardens Landfill Gas to Energy | San Antonio, TX | 6.7 GWh | 17.4 mi |
| O W Sommers | San Antonio, TX | 2.5 TWh | 5 mi |
| OCI Alamo 2, LLC | Converse, TX | 8.8 GWh | 15 mi |
| OCI Alamo 3 LLC | San Antonio, TX | 9.9 GWh | 16.2 mi |
| OCI Alamo Solar I Hybrid | San Antonio, TX | 84.0 GWh | 3.8 mi |
| SunE CPS1 LLC | San Antonio, TX | 4.5 GWh | 2.2 mi |
| SunE CPS2 LLC | San Antonio, TX | 7.0 GWh | 2.2 mi |
| SunE CPS3 LLC | Somerset, TX | 7.2 GWh | 17.4 mi |
| V H Braunig | Elmendorf, TX | 1.3 TWh | 0.1 mi |