Douglas Dam
850 Powerhouse Way, Dandridge, TN 37725Plant Summary Information
Douglas Dam is ranked #24 out of 97 power plants in Tennessee in terms of total annual net electricity generation.
Douglas Dam is comprised of 4 generators and generated 68.1 GWh during the 3-month period between September 2025 to December 2025.
| Plant Name | Douglas Dam |
|---|---|
| Utility Name | Tennessee Valley Authority |
| Location | Sevier County, TN |
| Initial Operation Date | March 1943 |
| Last Update | Dec 2025 |
| Annual Generation | 341.3 GWh |
| Annual Consumption | 1.3 M MMBtu |
| Ranked #1,856 out of 13,081 Power Plants Nationwide | |
| Ranked #136 out of 1,311 Water Power Plants Nationwide | |
| Ranked #24 out of 97 Tennessee Power Plants | |
| Ranked #11 out of 28 Tennessee Water Power Plants | |
| Fuel Types | Water |
Map of Douglas Dam
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Douglas Dam.
Monthly Net Generation for Douglas Dam
Monthly Plant Fuel Consumption for Douglas Dam
Douglas Dam Details
| Summary Information | |
|---|---|
| Plant Name | Douglas Dam (3400) |
| Plant Address | 850 Powerhouse Way, Dandridge, TN 37725 |
| Utility | Tennessee Valley Authority (18642) |
| Latitude, Longitude | 35.9623, -83.5393 |
| Generation Dates on File | Jan 2001 to Dec 2025 |
| Initial Operation Date | March 1943 |
| Annual Generation | 341.3 GWh |
| Fuel Types | Water |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Regulated |
| NERC Region | SERC |
| Balancing Authority | Tennessee Valley Authority (TVA) |
| NAICS Code | Utilities (22) |
| Sector | Electric Utility (1) |
| Water Source | French Broad River |
| Ash Impoundment | |
| Transmission / Distribution Owner | Tennessee Valley Authority (18642) TN |
| Grid Voltage | 161.00 kV |
| Energy Storage | No |
Generator 3 Details Operating March 1943
| Technology | Conventional Hydroelectric |
|---|---|
| Prime Mover | Hydroelectric Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 31.5 MW |
| Nameplate Power Factor | 0.9 |
| Summer Capacity | 44.5 MW |
| Winter Capacity | 27.6 MW |
| Minimum Load | 14.2 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | March 1943 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Water |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | No |
Generator 1 Details Operating January 1944
| Technology | Conventional Hydroelectric |
|---|---|
| Prime Mover | Hydroelectric Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 36.5 MW |
| Nameplate Power Factor | 0.9 |
| Summer Capacity | 44.2 MW |
| Winter Capacity | 27 MW |
| Minimum Load | 14.2 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | January 1944 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Water |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | No |
Generator 2 Details Operating May 1949
| Technology | Conventional Hydroelectric |
|---|---|
| Prime Mover | Hydroelectric Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 41.4 MW |
| Nameplate Power Factor | 0.9 |
| Summer Capacity | 44.7 MW |
| Winter Capacity | 27.5 MW |
| Minimum Load | 13 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | May 1949 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Water |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | No |
Generator 4 Details Operating August 1954
| Technology | Conventional Hydroelectric |
|---|---|
| Prime Mover | Hydroelectric Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 41.4 MW |
| Nameplate Power Factor | 0.9 |
| Summer Capacity | 44.5 MW |
| Winter Capacity | 29.1 MW |
| Minimum Load | 13 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | August 1954 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Water |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | No |
Douglas Dam Plant Owners
| Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Water.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #126 | Parker Dam | Parker, CA | 363.5 GWh |
| #127 | Poe | Storrie, CA | 363.0 GWh |
| #128 | Narrows (NC) | Badin, NC | 362.8 GWh |
| #129 | Center Hill | Lancaster, TN | 355.8 GWh |
| #130 | Pine Flat | Piedra, CA | 353.0 GWh |
| #131 | Pit 4 | Big Bend, CA | 349.3 GWh |
| #132 | John H Kerr | Boydton, VA | 346.4 GWh |
| #133 | Hartwell Lake | Hartwell, GA | 344.3 GWh |
| #134 | Balch 2 | Balch Camp, CA | 342.3 GWh |
| #135 | Cresta | Storrie, CA | 341.7 GWh |
| #137 | Walter F George | Ft. Gaines, GA | 340.7 GWh |
| #138 | H M Jackson | Sultan, WA | 333.6 GWh |
| #139 | Upper Baker | Concrete, WA | 332.7 GWh |
| #140 | Chelan | Wenatchee, WA | 325.2 GWh |
| #141 | Old Hickory | Hendersonville, TN | 324.7 GWh |
| #142 | Bartletts Ferry | Salem, AL | 324.1 GWh |
| #143 | Flaming Gorge | Dutch John, UT | 323.2 GWh |
| #144 | Cherokee Dam | Rudledge, TN | 315.3 GWh |
| #145 | Ozark | Ozark, AR | 314.7 GWh |
| #146 | Jordan Dam | Wetumpka, AL | 313.8 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Douglas Dam.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Calderwood | Tallassee, TN | 568.7 GWh | 40.8 mi |
| Cheoah | Tapoco, NC | 472.4 GWh | 42 mi |
| Cherokee Dam | Rudledge, TN | 315.3 GWh | 14.4 mi |
| Chestnut Ridge Gas Recovery | Heiskell, TN | 34.0 GWh | 29.5 mi |
| Chilhowee | Tallassee, TN | 157.7 GWh | 40.6 mi |
| Fontana Dam | Fontana Dam, NC | 900.2 GWh | 38.4 mi |
| Fort Loudoun | Lenoir City, TN | 633.1 GWh | 41.1 mi |
| Hot Springs Energy Storage & Microgrid | Hot Springs, NC | 2.1 GWh | 40.3 mi |
| John Sevier | Rogersville, TN | 4.2 TWh | 43 mi |
| Melton Hill | Lenoir City, TN | 145.1 GWh | 42.9 mi |
| Nantahala | Topton, NC | 188.4 GWh | 48.3 mi |
| Norris Dam | Norris, TN | 416.3 GWh | 35.7 mi |
| Primient Loudon Plant | Loudon, TN | 366.4 GWh | 46.4 mi |
| Santeetlah | Robbinsville, NC | 130.0 GWh | 40 mi |
| SR Albany, LLC | Greenville, TN | 41.0 MWh | 40.2 mi |
| SR Blount, LLC | Maryville, TN | 707.0 MWh | 29.5 mi |
| SR Greenville II | Greeneville, TN | 9.7 GWh | 47.3 mi |
| SR White Pine, LLC | White Pine, TN | 4.4 GWh | 18.1 mi |
| University of Tennessee Steam Plant | Knoxville, TN | 33.0 GWh | 21.7 mi |
| Walters | Waterville, NC | 289.1 GWh | 33.1 mi |