R C Kirkwood
Cherry Lake Road, Groveland, CA 95321Plant Summary Information
R C Kirkwood is ranked #14 out of 187 hydroelectric power plants in California in terms of total annual net electricity generation.
R C Kirkwood is comprised of 3 generators and generated 146.5 GWh during the 3-month period between December 2025 to March 2026.
| Plant Name | R C Kirkwood |
|---|---|
| Utility Name | City & County of San Francisco |
| Location | Tuolumne County, CA |
| Initial Operation Date | February 1967 |
| Last Update | Mar 2026 |
| Annual Generation | 489.5 GWh |
| Annual Consumption | 1.9 M MMBtu |
| Ranked #1,380 out of 12,332 Power Plants Nationwide | |
| Ranked #81 out of 1,256 Water Power Plants Nationwide | |
| Ranked #85 out of 1,530 California Power Plants | |
| Ranked #14 out of 187 California Water Power Plants | |
| Fuel Types | Water |
Map of R C Kirkwood
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for R C Kirkwood.
Monthly Net Generation for R C Kirkwood
Monthly Plant Fuel Consumption for R C Kirkwood
R C Kirkwood Details
| Summary Information | |
|---|---|
| Plant Name | R C Kirkwood (382) |
| Plant Address | Cherry Lake Road, Groveland, CA 95321 |
| Utility | City & County of San Francisco (16612) |
| Latitude, Longitude | 37.87767, -119.95323 |
| Generation Dates on File | Jan 2001 to Mar 2026 |
| Initial Operation Date | February 1967 |
| Annual Generation | 489.5 GWh |
| Fuel Types | Water |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Regulated |
| NERC Region | WECC |
| Balancing Authority | California Independent System Operator (CISO) |
| NAICS Code | Utilities (22) |
| Sector | Electric Utility (1) |
| Water Source | Hetch Hetchy Reservoir |
| Ash Impoundment | No |
| Transmission / Distribution Owner | City & County of San Francisco (16612) CA |
| Grid Voltage | 230.00 kV |
| Energy Storage | No |
Generator 1 Details Operating February 1967
| Technology | Conventional Hydroelectric |
|---|---|
| Prime Mover | Hydroelectric Turbine |
| Ownership | Single Owner |
| RTO ISO LMP Node Designation | INTKEP_2_UNITS-APND |
| RTO ISO Location Designation For Reporting Wholesale Sales Data | INTKEP_2_UNITS |
| Nameplate Capacity | 45.4 MW |
| Nameplate Power Factor | 0.95 |
| Summer Capacity | 40.6 MW |
| Winter Capacity | 41 MW |
| Minimum Load | 1 MW |
| Uprate/Derate Completed | No |
|---|---|
| Status | Operating |
| First Operation Date | February 1967 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Water |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | No |
Generator 2 Details Operating February 1967
| Technology | Conventional Hydroelectric |
|---|---|
| Prime Mover | Hydroelectric Turbine |
| Ownership | Single Owner |
| RTO ISO LMP Node Designation | INTKEP_2_UNITS-APND |
| RTO ISO Location Designation For Reporting Wholesale Sales Data | INTKEP_2_UNITS |
| Nameplate Capacity | 45.4 MW |
| Nameplate Power Factor | 0.95 |
| Summer Capacity | 40.5 MW |
| Winter Capacity | 40.5 MW |
| Minimum Load | 1 MW |
| Uprate/Derate Completed | No |
|---|---|
| Status | Operating |
| First Operation Date | February 1967 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Water |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | No |
Generator 3 Details Operating September 1987
| Technology | Conventional Hydroelectric |
|---|---|
| Prime Mover | Hydroelectric Turbine |
| Ownership | Single Owner |
| RTO ISO LMP Node Designation | INTKEP_2_UNITS-APND |
| RTO ISO Location Designation For Reporting Wholesale Sales Data | INTKEP_2_UNITS |
| Nameplate Capacity | 36.5 MW |
| Nameplate Power Factor | 0.9 |
| Summer Capacity | 40.3 MW |
| Winter Capacity | 35.2 MW |
| Minimum Load | 1 MW |
| Uprate/Derate Completed | No |
|---|---|
| Status | Operating |
| First Operation Date | September 1987 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Water |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | No |
R C Kirkwood Plant Owners
| Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Water.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #71 | Rock Creek | Storrie, CA | 558.5 GWh |
| #72 | Calderwood | Tallassee, TN | 549.2 GWh |
| #73 | Swift 1 | Cougar, WA | 548.4 GWh |
| #74 | Dardanelle | Dardanelle, AR | 517.3 GWh |
| #75 | Folsom | Folsom, CA | 510.7 GWh |
| #76 | Jaybird | Camino, CA | 505.2 GWh |
| #77 | Trinity | Weaverville, CA | 498.5 GWh |
| #78 | Osage Dam | Eldon, MO | 497.1 GWh |
| #79 | Nickajack | New Hope, TN | 491.2 GWh |
| #80 | White Rock/Slab Creek | Placerville, CA | 490.1 GWh |
| #82 | Yale | Amboy, WA | 488.4 GWh |
| #83 | Narrows (NC) | Badin, NC | 487.5 GWh |
| #84 | Caribou 2 | Belden, CA | 485.3 GWh |
| #85 | Cheoah | Tapoco, NC | 484.9 GWh |
| #86 | Kerckhoff 2 | Auberry, CA | 475.0 GWh |
| #87 | Merwin | Ariel, WA | 467.3 GWh |
| #88 | Box Canyon | Ione, WA | 464.1 GWh |
| #89 | John H Kerr | Boydton, VA | 462.9 GWh |
| #90 | Pit 5 | Big Bend, CA | 456.3 GWh |
| #91 | Long Lake | Ford, WA | 456.2 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding R C Kirkwood.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Beardsley | None, CA | 55.7 GWh | 23.4 mi |
| Collierville Powerhouse | Murphys, CA | 407.2 GWh | 29.7 mi |
| Dion R Holm | Groveland, CA | 601.5 GWh | 1.5 mi |
| Don Pedro | La Grange, CA | 301.4 GWh | 28.4 mi |
| Donnells | None, CA | 219.2 GWh | 25.9 mi |
| Exchequer | Snelling, CA | 267.9 GWh | 26.6 mi |
| La Grange | La Grange, CA | 4.4 GWh | 30.4 mi |
| McSwain | Snelling, CA | 31.8 GWh | 31.4 mi |
| Merced Falls | Snelling, CA | 9.4 GWh | 32 mi |
| Moccasin | Moccasin, CA | 303.6 GWh | 19.5 mi |
| Moccasin Low Head Hydro Project | Moccasin, CA | 4.0 MWh | 20 mi |
| New Melones | Jamestown, CA | 286.5 GWh | 31.7 mi |
| Pacific-Ultrapower Chinese Station | Jamestown, CA | 107.6 GWh | 28.6 mi |
| Phoenix | Sonora, CA | 8.0 GWh | 23 mi |
| Sand Bar Power Plant | Stanislaus Ntl. Fores, CA | 85.5 GWh | 23.9 mi |
| Sierra Pacific Chinese Camp | Chinese Camp, CA | 4.6 GWh | 27.3 mi |
| Sierra Pacific Sonora | Standard, CA | 34.9 GWh | 20.8 mi |
| Sonora 1 | Jamestown, CA | 621.0 MWh | 31.4 mi |
| Spring Gap | Long Barn, CA | 29.8 GWh | 23 mi |
| Stanislaus | Vallecito, CA | 315.8 GWh | 29 mi |