John H Kerr
5460 Buggs Island Road, Boydton, VA 23917Plant Summary Information
John H Kerr is ranked #25 out of 243 power plants in Virginia in terms of total annual net electricity generation.
John H Kerr is comprised of 9 generators and generated 35.5 GWh during the 3-month period between September 2025 to December 2025.
| Plant Name | John H Kerr |
|---|---|
| Utility Name | USCE-Wilmington District |
| Location | Mecklenburg County, VA |
| Initial Operation Date | November 1952 |
| Last Update | Dec 2025 |
| Annual Generation | 346.4 GWh |
| Annual Consumption | 1.2 M MMBtu |
| Ranked #1,838 out of 13,081 Power Plants Nationwide | |
| Ranked #132 out of 1,311 Water Power Plants Nationwide | |
| Ranked #25 out of 243 Virginia Power Plants | |
| Ranked #1 out of 17 Virginia Water Power Plants | |
| Fuel Types | Water |
Map of John H Kerr
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for John H Kerr.
Monthly Net Generation for John H Kerr
Monthly Plant Fuel Consumption for John H Kerr
John H Kerr Details
| Summary Information | |
|---|---|
| Plant Name | John H Kerr (3833) |
| Plant Address | 5460 Buggs Island Road, Boydton, VA 23917 |
| Utility | USCE-Wilmington District (18574) |
| Latitude, Longitude | 36.59943, -78.3005 |
| Generation Dates on File | Jan 2001 to Dec 2025 |
| Initial Operation Date | November 1952 |
| Annual Generation | 346.4 GWh |
| Fuel Types | Water |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Regulated |
| NERC Region | SERC |
| Balancing Authority | PJM Interconnection, LLC (PJM) |
| NAICS Code | Utilities (22) |
| Sector | Electric Utility (1) |
| Water Source | John H Kerr Reservoir |
| Ash Impoundment | No |
| Transmission / Distribution Owner | Virginia Electric & Power Co (19876) VA |
| Grid Voltage | 115.00 kV |
| Energy Storage | No |
Generator 2 Details Operating November 1952
| Technology | Conventional Hydroelectric |
|---|---|
| Prime Mover | Hydroelectric Turbine |
| Ownership | Single Owner |
| RTO ISO LMP Node Designation | KERRDP 115KV TX1 |
| Nameplate Capacity | 46.8 MW |
| Nameplate Power Factor | 0.9 |
| Summer Capacity | 46.8 MW |
| Winter Capacity | 46.8 MW |
| Minimum Load | 32 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | November 1952 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Water |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 10M |
| Multiple Fuels | No |
Generator 1 Details Operating December 1952
| Technology | Conventional Hydroelectric |
|---|---|
| Prime Mover | Hydroelectric Turbine |
| Ownership | Single Owner |
| RTO ISO LMP Node Designation | KERRDP 115KV TX1 |
| Nameplate Capacity | 13.8 MW |
| Nameplate Power Factor | 0.9 |
| Summer Capacity | 13.8 MW |
| Winter Capacity | 13.8 MW |
| Minimum Load | 13 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | December 1952 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Water |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 10M |
| Multiple Fuels | No |
Generator 3 Details Operating January 1953
| Technology | Conventional Hydroelectric |
|---|---|
| Prime Mover | Hydroelectric Turbine |
| Ownership | Single Owner |
| RTO ISO LMP Node Designation | KERRDP 115KV TX1 |
| Nameplate Capacity | 46.8 MW |
| Nameplate Power Factor | 0.9 |
| Summer Capacity | 46.8 MW |
| Winter Capacity | 46.8 MW |
| Minimum Load | 32 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | January 1953 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Water |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 10M |
| Multiple Fuels | No |
Generator 6 Details Operating October 1953
| Technology | Conventional Hydroelectric |
|---|---|
| Prime Mover | Hydroelectric Turbine |
| Ownership | Single Owner |
| RTO ISO LMP Node Designation | KERRDP 115KV TX1 |
| Nameplate Capacity | 46.8 MW |
| Nameplate Power Factor | 0.9 |
| Summer Capacity | 46.8 MW |
| Winter Capacity | 46.8 MW |
| Minimum Load | 32 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | October 1953 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Water |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 10M |
| Multiple Fuels | No |
Generator 7 Details Operating December 1953
| Technology | Conventional Hydroelectric |
|---|---|
| Prime Mover | Hydroelectric Turbine |
| Ownership | Single Owner |
| RTO ISO LMP Node Designation | KERRDP 115KV TX1 |
| Nameplate Capacity | 46.8 MW |
| Nameplate Power Factor | 0.9 |
| Summer Capacity | 46.8 MW |
| Winter Capacity | 46.8 MW |
| Minimum Load | 32 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | December 1953 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Water |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 10M |
| Multiple Fuels | No |
Generator 4 Details Operating March 1953
| Technology | Conventional Hydroelectric |
|---|---|
| Prime Mover | Hydroelectric Turbine |
| Ownership | Single Owner |
| RTO ISO LMP Node Designation | KERRDP 115KV TX1 |
| Nameplate Capacity | 46.8 MW |
| Nameplate Power Factor | 0.9 |
| Summer Capacity | 46.8 MW |
| Winter Capacity | 46.8 MW |
| Minimum Load | 32 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | March 1953 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Water |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 10M |
| Multiple Fuels | No |
Generator 5 Details Operating September 1953
| Technology | Conventional Hydroelectric |
|---|---|
| Prime Mover | Hydroelectric Turbine |
| Ownership | Single Owner |
| RTO ISO LMP Node Designation | KERRDP 115KV TX1 |
| Nameplate Capacity | 46.8 MW |
| Nameplate Power Factor | 0.9 |
| Summer Capacity | 46.8 MW |
| Winter Capacity | 46.8 MW |
| Minimum Load | 32 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | September 1953 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Water |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 10M |
| Multiple Fuels | No |
Generator A Details Operating December 2008
| Technology | Conventional Hydroelectric |
|---|---|
| Prime Mover | Hydroelectric Turbine |
| Ownership | Single Owner |
| RTO ISO LMP Node Designation | KERRDP 115KV TX1 |
| Nameplate Capacity | 1.1 MW |
| Nameplate Power Factor | 0.8 |
| Summer Capacity | 1 MW |
| Winter Capacity | 1 MW |
| Minimum Load | 0.1 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | December 2008 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Water |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 10M |
| Multiple Fuels | No |
Generator B Details Operating August 2008
| Technology | Conventional Hydroelectric |
|---|---|
| Prime Mover | Hydroelectric Turbine |
| Ownership | Single Owner |
| RTO ISO LMP Node Designation | KERRDP 115KV TX1 |
| Nameplate Capacity | 1.1 MW |
| Nameplate Power Factor | 0.8 |
| Summer Capacity | 1 MW |
| Winter Capacity | 1 MW |
| Minimum Load | 0.1 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | August 2008 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Water |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 10M |
| Multiple Fuels | No |
John H Kerr Plant Owners
| Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Water.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #122 | Table Rock | Branson, MO | 367.8 GWh |
| #123 | Hawks Nest Hydro | Gauley Bridge, WV | 366.3 GWh |
| #124 | Lower Baker | Concrete, WA | 364.8 GWh |
| #125 | C J Strike | Bruneau, ID | 364.1 GWh |
| #126 | Parker Dam | Parker, CA | 363.5 GWh |
| #127 | Poe | Storrie, CA | 363.0 GWh |
| #128 | Narrows (NC) | Badin, NC | 362.8 GWh |
| #129 | Center Hill | Lancaster, TN | 355.8 GWh |
| #130 | Pine Flat | Piedra, CA | 353.0 GWh |
| #131 | Pit 4 | Big Bend, CA | 349.3 GWh |
| #133 | Hartwell Lake | Hartwell, GA | 344.3 GWh |
| #134 | Balch 2 | Balch Camp, CA | 342.3 GWh |
| #135 | Cresta | Storrie, CA | 341.7 GWh |
| #136 | Douglas Dam | Dandridge, TN | 341.3 GWh |
| #137 | Walter F George | Ft. Gaines, GA | 340.7 GWh |
| #138 | H M Jackson | Sultan, WA | 333.6 GWh |
| #139 | Upper Baker | Concrete, WA | 332.7 GWh |
| #140 | Chelan | Wenatchee, WA | 325.2 GWh |
| #141 | Old Hickory | Hendersonville, TN | 324.7 GWh |
| #142 | Bartletts Ferry | Salem, AL | 324.1 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding John H Kerr.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Bluestone Solar | Chase City, VA | 79.6 GWh | 17.8 mi |
| Bolton Farm | Warrenton, NC | 7.3 GWh | 15.4 mi |
| Bullock Solar, LLC | Manson, NC | 101.2 GWh | 8.6 mi |
| Eagle Solar | Warrenton, NC | 7.8 GWh | 12.7 mi |
| Five Forks Solar | Macon, NC | 32.7 GWh | 15.9 mi |
| Granville Solar PV Power Project | Oxford, NC | 4.8 GWh | 20.8 mi |
| Grasshopper Solar | Chase City, VA | 121.8 GWh | 19.2 mi |
| Hawtree Solar | Warrenton, NC | 119.5 GWh | 11.8 mi |
| Kelly Solar, LLC | Henderson, NC | 8.7 GWh | 16.6 mi |
| Kenneth Solar | Warrenton, NC | 4.6 GWh | 14.1 mi |
| Otter Creek Solar | Chase City, VA | 123.4 GWh | 18.4 mi |
| Red Hill Solar Center, LLC | Warrenton, NC | 6.5 GWh | 16.1 mi |
| Spring Valley Farm 2, LLC | Henderson, NC | 8.5 GWh | 17 mi |
| Stagecoach Solar | Henderson, NC | 8.7 GWh | 15.5 mi |
| Stainback Solar Farm | Middleburg, NC | 9.6 GWh | 14.2 mi |
| Vicksburg Solar | Henderson, NC | 8.2 GWh | 19.1 mi |
| Virginia Line Solar, LLC | Manson, NC | 80.8 GWh | 5.3 mi |
| Warrenton Farm | Warrenton, NC | 6.2 GWh | 14.6 mi |
| Warrenton I Solar | Warrenton, NC | 8.9 GWh | 14.6 mi |
| Wortham Solar Farm | Henderson, NC | 8.8 GWh | 17.6 mi |