CPV Towantic Energy Center

Woodruff Hill Road, Oxford, CT 6478

Plant Summary Information

CPV Towantic Energy Center is ranked #3 out of 158 power plants in Connecticut in terms of total annual net electricity generation.

CPV Towantic Energy Center is comprised of 3 generators and generated 1.5 TWh during the 3-month period between December 2024 to March 2025.

Plant NameCPV Towantic Energy Center
Utility NameCPV Towantic, LLC
LocationNaugatuck Valley Planning Region, CT
Initial Operation DateMay 2018
Last Update Mar 2025
Annual Generation 5.6 TWh
Annual Consumption 40.3 M MMBtu
Ranked #190 out of 12,288 Power Plants Nationwide
Ranked #86 out of 2,221 Natural Gas Power Plants Nationwide
Ranked #3 out of 158 Connecticut Power Plants
Ranked #2 out of 53 Connecticut Natural Gas Power Plants
Fuel Types Natural Gas

Map of CPV Towantic Energy Center

Full Screen Map

Register Now for Comprehensive Access

Subscribe now to access all power plant data, utility information, FERC EQR data, and more for CPV Towantic Energy Center.

Create Your Account Today

Monthly Net Generation for CPV Towantic Energy Center

CPV Towantic Energy Center Details

Summary Information
Plant NameCPV Towantic Energy Center (56047)
Plant AddressWoodruff Hill Road, Oxford, CT 6478
UtilityCPV Towantic, LLC (19002)
Latitude, Longitude41.48124, -73.12311
Generation Dates on FileMay 2018 to Mar 2025
Initial Operation DateMay 2018
Annual Generation 5.6 TWh
Fuel Types Natural Gas
 
Federal Energy Regulatory Commission (FERC) Information
FERC Cogeneration StatusNo
FERC Small Power Producer StatusNo
FERC Exempt Wholesale Generator StatusYes
FERC Exempt Wholesale Generator Docket NumberEG16-34-000
Regulatory Information
Regulatory StatusNon-Regulated
NERC RegionNPCC
Balancing AuthorityISO New England Inc. (ISNE)
NAICS CodeUtilities (22)
Sector IPP Non-CHP (2)
Water SourceN/A
Ash Impoundment No
Transmission / Distribution OwnerConnecticut Light & Power Co (4176) CT
Grid Voltage 115.00 kV
Energy StorageNo
 
Natural Gas Information
Pipeline Name ALGONQUIN GAS TRANSMISSION COMPANY
Natural Gas StorageNo

Generator CTG1 Details Operating May 2018

TechnologyNatural Gas Fired Combined Cycle
Prime MoverCombined Cycle Combustion Turbine Part
Unit CodeCC1
OwnershipSingle Owner
Can Bypass Heat Recovery Steam GeneratorNo
RTO ISO LMP Node DesignationUN.TOWANTIC1A.0TO1A
RTO ISO Location Designation For Reporting Wholesale Sales DataUN.TOWANTIC1A.0TO1A
Nameplate Capacity280.5 MW
Nameplate Power Factor0.85
Summer Capacity246.56 MW
Winter Capacity288 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateMay 2018
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceNatural Gas / Distillate Fuel Oil
Solid Fuel Gasification No
Carbon Capture TechnologyNo
Time From Cold Shutdown To Full Load12H
Multiple FuelsYes
Cofire FuelsNo
Switch Between Oil And Natural GasYes
Multifuel Details
Switch When OperatingYes
Net Summer Capacity With Natural Gas259.5 MW
Net Winter Capacity With Natural Gas288 MW
Net Summer Capacity With Oil223 MW
Net Winter Capacity With Oil266.73 MW
Time To Switch From Gas To Oil1H
Time To Switch From Oil To Gas1H
Factors That Limit SwitchingYes
Storage LimitsYes
Air Permit LimitsYes

Generator CTG2 Details Operating May 2018

TechnologyNatural Gas Fired Combined Cycle
Prime MoverCombined Cycle Combustion Turbine Part
Unit CodeCC1
OwnershipSingle Owner
Can Bypass Heat Recovery Steam GeneratorNo
RTO ISO LMP Node DesignationUN.TOWANTIC1B.0TO1B
RTO ISO Location Designation For Reporting Wholesale Sales DataUN.TOWANTIC1B.0TO1B
Nameplate Capacity280.5 MW
Nameplate Power Factor0.85
Summer Capacity246.56 MW
Winter Capacity288 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateMay 2018
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceNatural Gas / Distillate Fuel Oil
Solid Fuel Gasification No
Carbon Capture TechnologyNo
Time From Cold Shutdown To Full Load12H
Multiple FuelsYes
Cofire FuelsNo
Switch Between Oil And Natural GasYes
Multifuel Details
Switch When OperatingYes
Net Summer Capacity With Natural Gas253.49 MW
Net Winter Capacity With Natural Gas288 MW
Net Summer Capacity With Oil223.8 MW
Net Winter Capacity With Oil255.36 MW
Time To Switch From Gas To Oil1H
Time To Switch From Oil To Gas1H
Factors That Limit SwitchingYes
Storage LimitsYes
Air Permit LimitsYes

Generator STG Details Operating May 2018

TechnologyNatural Gas Fired Combined Cycle
Prime MoverCombined Cycle Steam Part
Unit CodeCC1
OwnershipSingle Owner
Duct BurnersYes
Nameplate Capacity280.5 MW
Nameplate Power Factor0.85
Summer Capacity282.49 MW
Winter Capacity293 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateMay 2018
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceNatural Gas / Distillate Fuel Oil
Solid Fuel Gasification No
Carbon Capture TechnologyNo
Time From Cold Shutdown To Full Load12H
Subcritical TechnologyNo
Multiple FuelsYes
Cofire FuelsNo
Switch Between Oil And Natural GasYes
Multifuel Details
Switch When OperatingYes
Net Summer Capacity With Natural Gas281.98 MW
Net Winter Capacity With Natural Gas293 MW
Net Summer Capacity With Oil221.5 MW
Net Winter Capacity With Oil194.32 MW
Time To Switch From Gas To Oil1H
Time To Switch From Oil To Gas1H
Factors That Limit SwitchingYes
Storage LimitsYes
Air Permit LimitsYes

CPV Towantic Energy Center Plant Owners

Owner NameAddressGeneratorOwnership
We couldn't locate any owners for this plant

Power Plants with Similar Net Generation

Power plants with a similar annual net generation from Natural Gas.

RankPlant NamePlant LocationAnnual Generation
#76Cottonwood Energy ProjectDeweyville, TX5.9 TWh
#77Lamar Power ProjectParis, TX5.9 TWh
#78PolkMulberry, FL5.9 TWh
#79Hamilton LibertyTowanda, PA5.8 TWh
#80Channelview Cogeneration PlantChannelview, TX5.8 TWh
#81Lake Road Generating PlantDayville, CT5.8 TWh
#82W S LeeWilliamston, SC5.8 TWh
#83St Joseph Energy CenterNew Carlisle, IN5.7 TWh
#84SantanGilbert, AZ5.7 TWh
#85CaledoniaSteens, MS5.6 TWh
#87Choctaw CountyFrench Camp, MS5.5 TWh
#88Oneta Energy CenterBroken Arrow, OK5.5 TWh
#89Doswell Energy CenterAshland, VA5.5 TWh
#90Linden Cogen PlantLinden, NJ5.5 TWh
#91Carroll County EnergyCarrollton, OH5.4 TWh
#92Hays Energy ProjectSan Marcos, TX5.3 TWh
#93Kiamichi Energy FacilityKiowa, OK5.3 TWh
#94Eagle Valley (IN)Martinsville, IN5.3 TWh
#95Zeeland Generating StationZeeland, MI5.3 TWh
#96Kendall County Generation FacilityMinooka, IL5.3 TWh

Nearby Power Plants

Below are closest 20 power plants surrounding CPV Towantic Energy Center.

Plant NamePlant LocationAnnual GenerationDistance
Amazon BDL3 Solar ProjectNew Haven, CT1.6 GWh14.3 mi
Bristol Solar One, LLCBristol, CT4.9 GWh16.3 mi
Covanta Bristol EnergyBristol, CT108.5 GWh15.8 mi
Derby Fuel CellDerby, CT105.9 GWh10.9 mi
Derby HydroShelton, CT23.9 GWh10.9 mi
Emerald Gardens PKI, LLCShelton, CT2.1 GWh14.5 mi
Kimberly Clark-Unit 1,2,3New Milford, CT219.0 GWh15.9 mi
Medtronic - New HavenNorth Haven, CT2.2 GWh16.4 mi
Medtronic - New Haven 2North Haven, CT15.7 GWh16.6 mi
New Milford Gas RecoveryNew Milford, CT4.7 GWh16.3 mi
North Haven Solar OneNorth Haven, CT2.5 GWh16.5 mi
Park SolarWoodbridge, CT866.0 MWh12.2 mi
ShepaugSouthbury, CT116.6 GWh9.2 mi
Sikorsky Aircraft CHPStratford, CT53.1 GWh16 mi
StevensonMonroe, CT95.8 GWh7.2 mi
UI RCP Woodbridge FCWoodbridge, CT17.7 GWh10.4 mi
Wallingford EnergyWallingford, CT87.8 GWh15.1 mi
Wallingford SolarWallingford, CT20.9 GWh15 mi
Waterbury GenerationWaterbury, CT43.8 GWh6.1 mi
Watertown Solar One, LLCWatertown, CT2.9 GWh9.7 mi