Copenhagen Wind Farm
County Road 12, Copenhagen, NY 13626Plant Summary Information
Copenhagen Wind Farm is ranked #49 out of 944 power plants in New York in terms of total annual net electricity generation.
Copenhagen Wind Farm generated 71.5 GWh during the 3-month period between November 2025 to February 2026.
| Plant Name | Copenhagen Wind Farm |
|---|---|
| Utility Name | EDF Renewable Asset Holdings, Inc. |
| Location | Lewis County, NY |
| Initial Operation Date | December 2018 |
| Last Update | Feb 2026 |
| Annual Generation | 252.5 GWh |
| Annual Consumption | 942.8 k MMBtu |
| Ranked #2,221 out of 12,637 Power Plants Nationwide | |
| Ranked #674 out of 1,376 Wind Power Plants Nationwide | |
| Ranked #49 out of 944 New York Power Plants | |
| Ranked #11 out of 34 New York Wind Power Plants | |
| Fuel Types | Wind |
| Previous Operator |
Copenhagen Wind Farm, LLC (2013 to 2018) EDF Renewable Asset Holdings, Inc. (2015 to 2024) |
Map of Copenhagen Wind Farm
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Copenhagen Wind Farm.
Monthly Net Generation for Copenhagen Wind Farm
Monthly Plant Fuel Consumption for Copenhagen Wind Farm
Copenhagen Wind Farm Details
| Summary Information | |
|---|---|
| Plant Name | Copenhagen Wind Farm (58979) |
| Plant Address | County Road 12, Copenhagen, NY 13626 |
| Utility | EDF Renewable Asset Holdings, Inc. (57170) |
| Latitude, Longitude | 43.91306, -75.69861 |
| Generation Dates on File | Dec 2018 to Feb 2026 |
| Initial Operation Date | December 2018 |
| Annual Generation | 252.5 GWh |
| Fuel Types | Wind |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | NPCC |
| Balancing Authority | New York Independent System Operator (NYIS) |
| NAICS Code | Utilities (22) |
| Sector | IPP Non-CHP (2) |
| Water Source | |
| Ash Impoundment | No |
| Transmission / Distribution Owner | Niagara Mohawk Power Corp. (13573) NY |
| Grid Voltage | 115.00 kV |
| Energy Storage | No |
Generator CPHGN Details Operating December 2018
| Technology | Onshore Wind Turbine |
|---|---|
| Prime Mover | Wind Turbine, Onshore |
| Ownership | Single Owner |
| Nameplate Capacity | 79.9 MW |
| Summer Capacity | 79.9 MW |
| Winter Capacity | 79.9 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | December 2018 |
| Planned Retirement | December 2043 |
|---|---|
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Wind |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Turbines/Hydrokinetic Buoys | 40 |
| Multiple Fuels | No |
| Turbine Details | |
| Number Of Turbines | 40 |
|---|---|
| Predominant Turbine Manufacturer | Vestas |
| Predominant Turbine Model Number | V110-2.0 |
| Design Wind Speed | 15 MPH |
| Wind Quality Class | 3 - Low Wind |
| Turbine Hub Height Feet | 312 |
Copenhagen Wind Farm Plant Owners
| Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #664 | Saratoga Wind Farm | Lime Springs, IA | 258.1 GWh |
| #665 | EcoGrove Wind LLC | Lena, IL | 258.0 GWh |
| #666 | Sendero | Hebbronville, TX | 257.7 GWh |
| #667 | FPL Energy Vansycle LLC (OR) | Touchet, OR | 257.0 GWh |
| #668 | Bowman Wind | Bowman, ND | 256.4 GWh |
| #669 | Stanton Wind Energy LLC | Lenorah, TX | 253.9 GWh |
| #670 | Broken Bow Wind II, LLC | Broken Bow, NE | 253.6 GWh |
| #671 | Red Barn Energy | Montfort, WI | 253.3 GWh |
| #672 | Arkwright Summit Wind Farm LLC | Fredonia, NY | 252.7 GWh |
| #673 | South Trent Wind Farm | Sweetwater, TX | 252.5 GWh |
| #675 | San Roman Wind I, LLC | Los Fresnos, TX | 252.3 GWh |
| #676 | Criterion | Oakland, MD | 252.3 GWh |
| #677 | Ironwood Wind | Spearville, KS | 251.7 GWh |
| #678 | Hancock County Wind Energy Center | Garner, IA | 251.3 GWh |
| #679 | Sandy Ridge Wind 2, LLC | Tyrone, PA | 251.1 GWh |
| #680 | Brookfield | Pigeon, MI | 251.1 GWh |
| #681 | Minco Wind II, LLC | Minco, OK | 251.0 GWh |
| #682 | Pheasant Run Wind LLC | Pigeon, MI | 250.8 GWh |
| #683 | Smoky Hills Wind Project Phase I | Lincoln, KS | 250.8 GWh |
| #684 | Rockland Wind Farm | American Falls, ID | 250.6 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Copenhagen Wind Farm.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Beebee Island Hydro Plant | Watertown, NY | 50.9 GWh | 11.3 mi |
| Black River | Black River, NY | 27.1 GWh | 8.3 mi |
| Carthage A | Carthage, NY | 8.3 GWh | 6.1 mi |
| Carthage B | Carthage, NY | 5.6 GWh | 5.7 mi |
| Carthage Energy LLC | Carthage, NY | 3.5 GWh | 6.2 mi |
| Copenhagen Plant | Copenhagen, NY | 8.6 GWh | 2.1 mi |
| Copenhagen Solar | Copenhagen, NY | 2.3 GWh | 3.6 mi |
| Deferiet | Deferiet, NY | 62.9 GWh | 8.7 mi |
| Diamond Island Plant | Watertown, NY | 2.6 GWh | 10.4 mi |
| Herrings | Carthage, NY | 23.0 GWh | 7.9 mi |
| Kamargo | Black River, NY | 27.5 GWh | 8.4 mi |
| Kings Falls Hydroelectric | Copenhagen, NY | 2.0 GWh | 3.2 mi |
| Longfalls Facility | West Carthage, NY | 881.0 MWh | 6 mi |
| Maple Ridge Wind Farm | Lowville, NY | 664.3 GWh | 10.8 mi |
| Number Three Wind Project | Lowville, NY | 281.8 GWh | 8.2 mi |
| NY 26 Carthage CSG | Carthage, NY | 2.5 GWh | 5 mi |
| Sewalls | Watertown, NY | 15.1 GWh | 10.7 mi |
| St. Lawrence University - Sutton | Watertown, NY | 2.4 GWh | 8.7 mi |
| Watertown | Watertown, NY | 28.0 GWh | 9.8 mi |
| West End Dam Hydroelectric Project | Carthage, NY | 22.8 GWh | 6.2 mi |