Copenhagen Wind Farm
County Road 12, Copenhagen, NY 13626Plant Summary Information
Copenhagen Wind Farm is ranked #46 out of 912 power plants in New York in terms of total annual net electricity generation.
Copenhagen Wind Farm generated 78.4 GWh during the 3-month period between February 2025 to May 2025.
Plant Name | Copenhagen Wind Farm |
---|---|
Utility Name | EDF Renewable Asset Holdings, Inc. |
Location | Lewis County, NY |
Initial Operation Date | December 2018 |
Last Update | May 2025 |
Annual Generation | 262.3 GWh |
Annual Consumption | 951.0 k MMBtu |
Ranked #2,091 out of 12,312 Power Plants Nationwide | |
Ranked #642 out of 1,355 Wind Power Plants Nationwide | |
Ranked #46 out of 912 New York Power Plants | |
Ranked #9 out of 34 New York Wind Power Plants | |
Fuel Types | Wind |
Previous Operator |
Copenhagen Wind Farm, LLC (2013 to 2018) EDF Renewable Asset Holdings, Inc. (2015 to 2024) |
Map of Copenhagen Wind Farm
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Copenhagen Wind Farm.
Monthly Net Generation for Copenhagen Wind Farm
Copenhagen Wind Farm Details
Summary Information | |
---|---|
Plant Name | Copenhagen Wind Farm (58979) |
Plant Address | County Road 12, Copenhagen, NY 13626 |
Utility | EDF Renewable Asset Holdings, Inc. (57170) |
Latitude, Longitude | 43.91306, -75.69861 |
Generation Dates on File | Dec 2018 to May 2025 |
Initial Operation Date | December 2018 |
Annual Generation | 262.3 GWh |
Fuel Types | Wind |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | NPCC |
Balancing Authority | New York Independent System Operator (NYIS) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | No |
Transmission / Distribution Owner | Niagara Mohawk Power Corp. (13573) NY |
Grid Voltage | 115.00 kV |
Energy Storage | No |
Generator CPHGN Details Operating December 2018
Technology | Onshore Wind Turbine |
---|---|
Prime Mover | Wind Turbine, Onshore |
Ownership | Single Owner |
Nameplate Capacity | 79.9 MW |
Summer Capacity | 79.9 MW |
Winter Capacity | 79.9 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | December 2018 |
Planned Retirement | December 2043 |
---|---|
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Wind |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Turbines/Hydrokinetic Buoys | 40 |
Multiple Fuels | No |
Turbine Details | |
Number Of Turbines | 40 |
---|---|
Predominant Turbine Manufacturer | Vestas |
Predominant Turbine Model Number | V110-2.0 |
Design Wind Speed | 15 MPH |
Wind Quality Class | 3 - Low Wind |
Turbine Hub Height Feet | 312 |
Copenhagen Wind Farm Plant Owners
Owner Name | Address | Ownership | |
---|---|---|---|
We couldn't locate any owners for this plant |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#632 | Apple Blossom Wind Farm | Pigeon, MI | 266.0 GWh |
#633 | Shiloh III Wind Project LLC | Birds Landing, CA | 265.2 GWh |
#634 | Bull Creek Wind | O'Donnell, TX | 265.2 GWh |
#635 | Mehoopany Wind Energy LLC | Noxen, PA | 265.0 GWh |
#636 | Hancock County Wind Energy Center | Garner, IA | 264.6 GWh |
#637 | Gray County Wind Energy | Montezuma, KS | 264.1 GWh |
#638 | Mendota Hills, LLC | Paw Paw, IL | 263.7 GWh |
#639 | Harvest Wind Project | Roosevelt, WA | 263.7 GWh |
#640 | Windstar 1 | Tehachapi, CA | 263.0 GWh |
#641 | Blue Canyon Windpower V LLC | Carnegie, OK | 262.8 GWh |
#643 | Lake Winds Energy Park | Ludington, MI | 262.1 GWh |
#644 | Red Barn Energy | Montfort, WI | 262.0 GWh |
#645 | Rising Tree Wind Farm III | Mojave, CA | 261.4 GWh |
#646 | Pheasant Run Wind LLC | Pigeon, MI | 261.2 GWh |
#647 | Borderlands Wind, LLC | Quemado, NM | 261.0 GWh |
#648 | Sigel Wind Park | Harbor Beach, MI | 260.7 GWh |
#649 | Keenan II Renewable Energy Co LLC | Woodward, OK | 260.6 GWh |
#650 | Wapsipinicon Wind Project | Dexter, MN | 259.7 GWh |
#651 | NaturEner Glacier Wind Energy 2 | Ethridge, MT | 259.7 GWh |
#652 | Rocky Ridge Wind Project | Hobart, OK | 259.5 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Copenhagen Wind Farm.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Beebee Island Hydro Plant | Watertown, NY | 50.9 GWh | 11.3 mi |
Black River | Black River, NY | 27.1 GWh | 8.3 mi |
Carthage A | Carthage, NY | 8.2 GWh | 6.1 mi |
Carthage B | Carthage, NY | 5.5 GWh | 5.7 mi |
Copenhagen Plant | Copenhagen, NY | 8.6 GWh | 2.1 mi |
DANC LFGTE Facility | Rodman, NY | 25.9 GWh | 12.7 mi |
Deferiet | Deferiet, NY | 62.9 GWh | 8.7 mi |
Diamond Island Plant | Watertown, NY | 2.6 GWh | 10.4 mi |
Herrings | Carthage, NY | 23.0 GWh | 7.9 mi |
Kamargo | Black River, NY | 27.5 GWh | 8.4 mi |
Kings Falls Hydroelectric | Copenhagen, NY | 2.0 GWh | 3.2 mi |
Longfalls Facility | West Carthage, NY | 881.0 MWh | 6 mi |
Maple Ridge Wind Farm | Lowville, NY | 708.3 GWh | 10.8 mi |
Number Three Wind Project | Lowville, NY | 301.0 GWh | 8.2 mi |
NY 26 Carthage CSG | Carthage, NY | 2.5 GWh | 5 mi |
OYA Wayside Drive | Watertown, NY | 9.5 GWh | 13.2 mi |
Sewalls | Watertown, NY | 15.1 GWh | 10.7 mi |
St. Lawrence University - Sutton | Watertown, NY | 2.4 GWh | 8.7 mi |
Watertown | Watertown, NY | 28.0 GWh | 9.8 mi |
West End Dam Hydroelectric Project | Carthage, NY | 22.8 GWh | 6.2 mi |