Clear Spring Ranch PV Project
7383 Loren Lane, Fountain, CO 80817Plant Summary Information
Clear Spring Ranch PV Project is ranked #32 out of 178 solar farms in Colorado in terms of total annual net electricity generation.
Clear Spring Ranch PV Project generated 2.6 GWh during the 3-month period between September 2025 to December 2025.
| Plant Name | Clear Spring Ranch PV Project |
|---|---|
| Utility Name | Madison Energy Investments LLC |
| Location | El Paso County, CO |
| Initial Operation Date | October 2016 |
| Last Update | Dec 2025 |
| Annual Generation | 17.2 GWh |
| Annual Consumption | 61.7 k MMBtu |
| Ranked #5,594 out of 13,301 Power Plants Nationwide | |
| Ranked #1,684 out of 7,209 Solar Power Plants Nationwide | |
| Ranked #109 out of 299 Colorado Power Plants | |
| Ranked #32 out of 178 Colorado Solar Power Plants | |
| Fuel Types | Solar |
| Previous Operator |
DG Colorado Solar, LLC (2015 to 2024) Madison Energy Investments LLC (2025 to 2025) |
Map of Clear Spring Ranch PV Project
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Clear Spring Ranch PV Project.
Monthly Net Generation for Clear Spring Ranch PV Project
Monthly Plant Fuel Consumption for Clear Spring Ranch PV Project
Clear Spring Ranch PV Project Details
| Summary Information | |
|---|---|
| Plant Name | Clear Spring Ranch PV Project (60511) |
| Plant Address | 7383 Loren Lane, Fountain, CO 80817 |
| Utility | Madison Energy Investments LLC (65043) |
| Latitude, Longitude | 38.6021, -104.69469 |
| Generation Dates on File | Oct 2016 to Dec 2025 |
| Initial Operation Date | October 2016 |
| Annual Generation | 17.2 GWh |
| Fuel Types | Solar |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | WECC |
| Balancing Authority | Western Area Power Administration - Rocky Mountain Region (WACM) |
| NAICS Code | Utilities (22) |
| Sector | IPP Non-CHP (2) |
| Water Source | |
| Ash Impoundment | |
| Transmission / Distribution Owner | City of Colorado Springs - (CO) (3989) CO |
| Grid Voltage | 12.50 kV |
| Energy Storage | No |
Generator PV1 Details Operating October 2016
| Technology | Solar Photovoltaic |
|---|---|
| Prime Mover | Photovoltaic |
| Ownership | Single Owner |
| Nameplate Capacity | 10 MW |
| Summer Capacity | 10 MW |
| Winter Capacity | 10 MW |
| Uprate/Derate Completed | No |
|---|---|
| Status | Operating |
| First Operation Date | October 2016 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Solar |
| Solar Details | |
| Single Axis Tracking | Yes |
|---|---|
| Azimuth Angle | 180 |
| DC Net Capacity | 13.9 MW |
| Crystalline Silicon | Yes |
| Net Metering Agreement | No |
| Virtual Net Metering Agreement | No |
Clear Spring Ranch PV Project Plant Owners
| Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #1674 | Chisum | Blossom, TX | 17.6 GWh |
| #1675 | Turkey Creek PV1 | Kirby, NC | 17.6 GWh |
| #1676 | Otero Solar | La Luz, NM | 17.6 GWh |
| #1677 | Saltbranch 2 | Tulsa, OK | 17.6 GWh |
| #1678 | Oak Leaf Solar XVIII LLC | Denver, CO | 17.5 GWh |
| #1679 | Eagle Point Solar | Central Point, OR | 17.5 GWh |
| #1680 | Wheeler Gulch Solar, LLC | Parachute, CO | 17.5 GWh |
| #1681 | Gardy's Mill Solar | Kinsale, VA | 17.4 GWh |
| #1682 | Dane County Airport Solar | Madison, WI | 17.4 GWh |
| #1683 | Whitewright Solar | Whitewright, TX | 17.4 GWh |
| #1685 | Barrett PV | Oxford, MA | 17.2 GWh |
| #1686 | South 49th 013445 SCS Norfolk, LLC | Norfolk, NE | 17.2 GWh |
| #1687 | Mount Saint Mary's | Emmitsburg, MD | 17.2 GWh |
| #1688 | Peru 2 | Peru, IN | 17.2 GWh |
| #1689 | Mohave Electric Cooperative at Joy Lane | Fort Mohave, AZ | 17.1 GWh |
| #1690 | Wye Mills VNEM CSG | Queen Anne, MD | 17.1 GWh |
| #1691 | Washington White Post Solar LLC | Bath, NC | 17.1 GWh |
| #1692 | Suwannee Solar Facility | Live Oak, FL | 17.1 GWh |
| #1693 | Redstone Arsenal Hybrid | Huntsville, AL | 17.1 GWh |
| #1694 | Costen Solar | Pocomoke City, MD | 17.0 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Clear Spring Ranch PV Project.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| AFA Solar Farm | Colorado Springs, CO | 9.5 GWh | 25.3 mi |
| Bighorn Solar 1 | Pueblo, CO | 544.7 GWh | 27.8 mi |
| Carson Solar I | Colorado Springs, CO | 3.1 GWh | 9.6 mi |
| CEC Solar #1117, LLC | Pueblo, CO | 3.7 GWh | 23.8 mi |
| Comanche (CO) | Pueblo, CO | 1.8 TWh | 28 mi |
| CSU Pueblo | Pueblo, CO | 1.7 GWh | 21.4 mi |
| Fountain Valley Power Facility | Fountain, CO | 93.5 GWh | 3.1 mi |
| Front Range Power Plant | Fountain, CO | 2.4 TWh | 1.9 mi |
| George Birdsall | Colorado Springs, CO | 42.5 GWh | 20.4 mi |
| Manitou Springs | Manitou Spring, CO | 2.0 GWh | 21.7 mi |
| Neptune Energy Center Hybrid | Boone, CO | 620.7 GWh | 24.1 mi |
| Palmer Solar | Fountain, CO | 140.7 GWh | 3 mi |
| Pike Solar Hybrid | Fountain, CO | 442.2 GWh | 6.3 mi |
| Pikes Peak Solar Garden 1 LLC CSG | Colorado Springs, CO | 4.2 GWh | 12.2 mi |
| Pueblo Airport Generating Station | Pueblo, CO | 1.4 TWh | 21.5 mi |
| Ray D Nixon | Fountain, CO | 1.3 TWh | 2.2 mi |
| Ruxton Park | Manitou Spring, CO | 1.0 GWh | 22.4 mi |