Chevelon Butte Phase 2
Arizona Highway 99, Winslow, AZ 86047Plant Summary Information
Chevelon Butte Phase 2 is ranked #39 out of 166 power plants in Arizona in terms of total annual net electricity generation.
Chevelon Butte Phase 2 generated 95.7 GWh during the 3-month period between December 2025 to March 2026.
| Plant Name | Chevelon Butte Phase 2 |
|---|---|
| Utility Name | AES Clean Energy |
| Location | Coconino County, AZ |
| Initial Operation Date | April 2024 |
| Last Update | Mar 2026 |
| Annual Generation | 466.1 GWh |
| Annual Consumption | 1.8 M MMBtu |
| Ranked #1,436 out of 12,332 Power Plants Nationwide | |
| Ranked #398 out of 1,358 Wind Power Plants Nationwide | |
| Ranked #39 out of 166 Arizona Power Plants | |
| Ranked #4 out of 9 Arizona Wind Power Plants | |
| Fuel Types | Wind |
Map of Chevelon Butte Phase 2
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Chevelon Butte Phase 2.
Monthly Net Generation for Chevelon Butte Phase 2
Monthly Plant Fuel Consumption for Chevelon Butte Phase 2
Chevelon Butte Phase 2 Details
| Summary Information | |
|---|---|
| Plant Name | Chevelon Butte Phase 2 (67176) |
| Plant Address | Arizona Highway 99, Winslow, AZ 86047 |
| Utility | AES Clean Energy (64904) |
| Latitude, Longitude | 34.6821, -110.803 |
| Generation Dates on File | May 2024 to Mar 2026 |
| Initial Operation Date | April 2024 |
| Annual Generation | 466.1 GWh |
| Fuel Types | Wind |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | Yes |
| FERC Exempt Wholesale Generator Docket Number | EG23-225-000 |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | WECC |
| Balancing Authority | Arizona Public Service Company (AZPS) |
| NAICS Code | Utilities (22) |
| Sector | IPP Non-CHP (2) |
| Water Source | NA |
| Ash Impoundment | No |
| Transmission / Distribution Owner | Arizona Public Service Co (803) AZ |
| Grid Voltage | 345.00 kV |
| Energy Storage | No |
Generator CHVB2 Details Operating April 2024
| Technology | Onshore Wind Turbine |
|---|---|
| Prime Mover | Wind Turbine, Onshore |
| Ownership | Single Owner |
| Nameplate Capacity | 216 MW |
| Summer Capacity | 216 MW |
| Winter Capacity | 216 MW |
| Uprate/Derate Completed | No |
|---|---|
| Status | Operating |
| First Operation Date | April 2024 |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Wind |
| Turbines/Hydrokinetic Buoys | 48 |
| Turbine Details | |
| Number Of Turbines | 48 |
|---|---|
| Predominant Turbine Manufacturer | Vestas |
| Predominant Turbine Model Number | V150-4.2 |
| Design Wind Speed | 14.8 MPH |
| Wind Quality Class | 3 - Low Wind |
| Turbine Hub Height Feet | 394 |
Chevelon Butte Phase 2 Plant Owners
| Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #388 | Frontier Windpower | Newkirk, OK | 476.0 GWh |
| #389 | Adams Wind | Lenox, IA | 474.5 GWh |
| #390 | Flat Ridge 3 | Zenda, KS | 474.4 GWh |
| #391 | Deerfield Wind Energy, LLC | Kinde, MI | 473.8 GWh |
| #392 | Hilltopper Wind Project | Mt. Pulaski, IL | 471.4 GWh |
| #393 | Bingham Wind | Bingham, ME | 471.3 GWh |
| #394 | Sweetwater Wind 3 LLC | Sweetwater, TX | 470.0 GWh |
| #395 | Mesquite Creek Wind | Lamesa, TX | 469.7 GWh |
| #396 | Wellsburg Wind Project | Wellsburg, IA | 468.7 GWh |
| #397 | Prairie Switch Wind LLC | El Campo, TX | 466.4 GWh |
| #399 | Ensign Wind LLC | Montezuma, KS | 464.2 GWh |
| #400 | Laurel Wind Farm | Laurel, IA | 463.1 GWh |
| #401 | Bobcat Bluff Wind Project LLC | Archer, TX | 462.3 GWh |
| #402 | Wildcat Creek Wind Farm LLC | Gainesville, TX | 462.0 GWh |
| #403 | Walleye Wind | Beaver Creek, MN | 461.3 GWh |
| #404 | Gunsight Mountain Wind Energy LLC | Big Spring, TX | 460.7 GWh |
| #405 | Buffalo Ridge II LLC | Elkton, SD | 459.4 GWh |
| #406 | Marble River Wind Farm | Churubusco, NY | 459.4 GWh |
| #407 | Pioneer Trail Wind Farm, LLC | Paxton, IL | 458.8 GWh |
| #408 | Ford County Wind Farm LLC | Ford County, IL | 456.7 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Chevelon Butte Phase 2.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Babbitt Ranch Energy Center | Flagstaff, AZ | 513.4 GWh | 88.8 mi |
| Chevelon Butte Wind Farm | Winslow, AZ | 559.0 GWh | 0.1 mi |
| Chino Valley Solar | Chino Valley, AZ | 41.0 GWh | 92.4 mi |
| Cholla | Joseph City, AZ | 1.3 TWh | 33.5 mi |
| Coronado | St Johns, AZ | 2.6 TWh | 87.4 mi |
| Dry Lake Wind LLC | Heber, AZ | 92.5 GWh | 29.5 mi |
| Horse Mesa | Apache Junction, AZ | 74.2 GWh | 81.5 mi |
| Jewish Community Center PV | Scottsdale, AZ | 1.8 GWh | 98.3 mi |
| Lake Pleasant WTP | Peoria, AZ | 12.9 GWh | 101.4 mi |
| Mormon Flat | Apache Junction, AZ | 39.3 GWh | 86.1 mi |
| Novo BioPower Plant | Snowflake, AZ | 168.1 GWh | 29.4 mi |
| Ocotillo | Tempe, AZ | 434.7 GWh | 107.7 mi |
| Paradise Valley H.S. PV | Phoenix, AZ | 2.1 GWh | 99.2 mi |
| Perrin Ranch Wind LLC | Williams, AZ | 167.6 GWh | 97.3 mi |
| Poseidon Wind, LLC | Herber, AZ | 95.4 GWh | 36.2 mi |
| Prescott Airport | Prescott, AZ | 2.5 GWh | 90.8 mi |
| Prescott Solar Plant | Prescott, AZ | 23.0 GWh | 92.3 mi |
| Roosevelt | Roosevelt, AZ | 101.8 GWh | 72.8 mi |
| Springerville | Springerville, AZ | 5.4 TWh | 96.7 mi |
| Stewart Mountain | Phoenix, AZ | 45.7 GWh | 87.8 mi |