Chattahoochee Energy Facility
3461 Hollingswarth Ferry Rd, Franklin, GA 30217Plant Summary Information
Chattahoochee Energy Facility is ranked #9 out of 251 power plants in Georgia in terms of total annual net electricity generation.
Chattahoochee Energy Facility is comprised of 3 generators and generated 983.1 GWh during the 3-month period between November 2025 to February 2026.
| Plant Name | Chattahoochee Energy Facility |
|---|---|
| Utility Name | Oglethorpe Power Corporation |
| Location | Heard County, GA |
| Initial Operation Date | February 2003 |
| Last Update | Feb 2026 |
| Annual Generation | 3.9 TWh |
| Annual Consumption | 27.9 M MMBtu |
| Ranked #285 out of 12,637 Power Plants Nationwide | |
| Ranked #142 out of 2,243 Natural Gas Power Plants Nationwide | |
| Ranked #9 out of 251 Georgia Power Plants | |
| Ranked #5 out of 46 Georgia Natural Gas Power Plants | |
| Fuel Types | Natural Gas |
Map of Chattahoochee Energy Facility
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Chattahoochee Energy Facility.
Monthly Net Generation for Chattahoochee Energy Facility
Monthly Plant Fuel Consumption for Chattahoochee Energy Facility
Chattahoochee Energy Facility Details
| Summary Information | |
|---|---|
| Plant Name | Chattahoochee Energy Facility (7917) |
| Plant Address | 3461 Hollingswarth Ferry Rd, Franklin, GA 30217 |
| Utility | Oglethorpe Power Corporation (13994) |
| Latitude, Longitude | 33.4072, -85.0386 |
| Generation Dates on File | Feb 2003 to Feb 2026 |
| Initial Operation Date | February 2003 |
| Annual Generation | 3.9 TWh |
| Fuel Types | Natural Gas |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Regulated |
| NERC Region | SERC |
| Balancing Authority | Southern Company Services, Inc. - Trans (SOCO) |
| NAICS Code | Utilities (22) |
| Sector | Electric Utility (1) |
| Water Source | Chattahoochee River |
| Ash Impoundment | |
| Transmission / Distribution Owner | Georgia Transmission Corp (7197) GA |
| Grid Voltage | 230.00 kV |
| Energy Storage | No |
| Natural Gas Information | |
| Pipeline Name | TRANSCONTINENTAL GAS PIPELINE |
| Natural Gas Storage | No |
Generator 1 Details Operating February 2003
| Technology | Natural Gas Fired Combined Cycle |
|---|---|
| Prime Mover | Combined Cycle Combustion Turbine Part |
| Unit Code | 2224 |
| Ownership | Single Owner |
| Can Bypass Heat Recovery Steam Generator | No |
| Nameplate Capacity | 176 MW |
| Nameplate Power Factor | 0.85 |
| Summer Capacity | 145.5 MW |
| Winter Capacity | 169.5 MW |
| Minimum Load | 65 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | February 2003 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Natural Gas |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 12H |
| Multiple Fuels | No |
| Cofire Fuels | No |
Generator 2 Details Operating February 2003
| Technology | Natural Gas Fired Combined Cycle |
|---|---|
| Prime Mover | Combined Cycle Combustion Turbine Part |
| Unit Code | 2224 |
| Ownership | Single Owner |
| Can Bypass Heat Recovery Steam Generator | No |
| Nameplate Capacity | 176 MW |
| Nameplate Power Factor | 0.85 |
| Summer Capacity | 141.5 MW |
| Winter Capacity | 167.5 MW |
| Minimum Load | 130 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | February 2003 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Natural Gas |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 12H |
| Multiple Fuels | No |
| Cofire Fuels | No |
Generator 3 Details Operating February 2003
| Technology | Natural Gas Fired Combined Cycle |
|---|---|
| Prime Mover | Combined Cycle Steam Part |
| Unit Code | 2224 |
| Ownership | Single Owner |
| Duct Burners | Yes |
| Nameplate Capacity | 187.7 MW |
| Nameplate Power Factor | 0.85 |
| Summer Capacity | 179 MW |
| Winter Capacity | 189 MW |
| Minimum Load | 130 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | February 2003 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Natural Gas |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 12H |
| Multiple Fuels | No |
| Cofire Fuels | No |
Chattahoochee Energy Facility Plant Owners
| Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #132 | Ratcliffe | De Kalb, MS | 4.2 TWh |
| #133 | Dresden Energy Facility | Dresden, OH | 4.2 TWh |
| #134 | ExxonMobil Beaumont Refinery | Beaumont, TX | 4.3 TWh |
| #135 | Fort St Vrain | Platteville, CO | 4.2 TWh |
| #136 | Cane Island | Intercession City, FL | 4.1 TWh |
| #137 | Tracy | Sparks, NV | 4.1 TWh |
| #138 | Fremont Energy Center | Fremont, OH | 4.0 TWh |
| #139 | Choctaw County | French Camp, MS | 4.0 TWh |
| #140 | Northport | Northport, NY | 4.5 TWh |
| #141 | Liberty Electric Power Plant | Eddystone, PA | 4.0 TWh |
| #143 | Dearborn Industrial Generation | Dearborn, MI | 4.1 TWh |
| #144 | Dell Power Station | Dell, AR | 3.9 TWh |
| #145 | Dan River | Eden, NC | 3.9 TWh |
| #146 | Redbud Power Plant | Luther, OK | 3.9 TWh |
| #147 | Quantum Choctaw Power LLC | Ackerman, MS | 3.9 TWh |
| #148 | Ouachita | Sterlington, LA | 3.9 TWh |
| #149 | West Phoenix | Phoenix, AZ | 3.9 TWh |
| #150 | Buck | Salisbury, NC | 3.9 TWh |
| #151 | Woodbridge Energy Center | Keasbey, NJ | 3.9 TWh |
| #152 | Ontelaunee Energy Center | Reading, PA | 3.9 TWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Chattahoochee Energy Facility.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Atlanta Falcons Solar | Atlanta, GA | 1.1 GWh | 43.9 mi |
| Camp Solar Plant | Woodbury, GA | 3.9 GWh | 41.9 mi |
| Greenville | Greenville, GA | 1.4 GWh | 31.2 mi |
| Harris Dam | Lineville, AL | 115.6 GWh | 34.9 mi |
| Hawk Road Facility | Franklin, GA | 682.5 GWh | 4.3 mi |
| Jack McDonough | Smyrna, GA | 17.7 TWh | 43.3 mi |
| Kimberly-Clark Solar | LaGrange, GA | 3.8 GWh | 28.1 mi |
| LaFayette Solar Farm | LaFayette, AL | 164.3 GWh | 41.9 mi |
| MAS ASB Cogen Plant | Atlanta, GA | 38.0 GWh | 40.9 mi |
| Meriwether Jackson | Machester, GA | 6.3 GWh | 43.1 mi |
| Rockmart | Rockmart, GA | 5.4 GWh | 42 mi |
| Sewell Creek Energy | Cedartown, GA | 522.9 GWh | 39.8 mi |
| Tenaska Georgia Generation Facility | Franklin, GA | 109.2 GWh | 4.5 mi |
| Troup RC50 | Pine Mountain, GA | 1.5 GWh | 37 mi |
| Troup RC50 II | Pine Mountain, GA | 3.0 GWh | 36.1 mi |
| Turnipseed Solar, LLC | Douglasville, GA | 5.3 GWh | 28.9 mi |
| Wansley Combined Cycle | Franklin, GA | 7.5 TWh | 0.1 mi |
| Wansley Unit 9 | Franklin, GA | 2.2 TWh | 0.1 mi |
| West Point (GA) | West Point, GA | 181.0 GWh | 34.9 mi |
| Yates | Newnan, GA | 2.1 TWh | 8.9 mi |