Ceredo Generating Station

1662 Walker Branch Road, Huntington, WV 25704

Plant Summary Information

Ceredo Generating Station is ranked #9 out of 38 power plants in West Virginia in terms of total annual net electricity generation.

Ceredo Generating Station is comprised of 6 generators and generated 213.2 GWh during the 3-month period between June 2025 to September 2025.

Plant NameCeredo Generating Station
Utility NameAppalachian Power Co
LocationWayne County, WV
Initial Operation DateJune 2001
Last Update Sep 2025
Annual Generation 706.7 GWh
Annual Consumption 9.2 M MMBtu
Ranked #992 out of 12,539 Power Plants Nationwide
Ranked #500 out of 2,243 Natural Gas Power Plants Nationwide
Ranked #9 out of 38 West Virginia Power Plants
Ranked #2 out of 8 West Virginia Natural Gas Power Plants
Fuel Types Natural Gas

Map of Ceredo Generating Station

Full Screen Map

Register Now for Comprehensive Access

Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Ceredo Generating Station.

Create Your Account Today

Monthly Net Generation for Ceredo Generating Station

Ceredo Generating Station Details

Summary Information
Plant NameCeredo Generating Station (55276)
Plant Address1662 Walker Branch Road, Huntington, WV 25704
UtilityAppalachian Power Co (733)
Latitude, Longitude38.3681, -82.5339
Generation Dates on FileJul 2001 to Sep 2025
Initial Operation DateJune 2001
Annual Generation 706.7 GWh
Fuel Types Natural Gas
 
Federal Energy Regulatory Commission (FERC) Information
FERC Cogeneration StatusNo
FERC Small Power Producer StatusNo
FERC Exempt Wholesale Generator StatusNo
Regulatory Information
Regulatory StatusRegulated
NERC RegionRFC
Balancing AuthorityPJM Interconnection, LLC (PJM)
NAICS CodeUtilities (22)
Sector Electric Utility (1)
Water SourceCity of Kenova
Ash Impoundment No
Transmission / Distribution OwnerAppalachian Power Co (733) WV
Grid Voltage 138.00 kV
Energy StorageNo
 
Natural Gas Information
Pipeline Name COLUMBIA GAS TRANSMISSION CORP
Natural Gas StorageNo

Generator 01 Details Operating June 2001

TechnologyNatural Gas Fired Combustion Turbine
Prime MoverCombustion Turbine
OwnershipSingle Owner
Nameplate Capacity86.5 MW
Nameplate Power Factor0.85
Summer Capacity75 MW
Winter Capacity86 MW
Minimum Load64 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateJune 2001
Combined Heat & Power No
Sector NameElectric Utility (1)
Energy SourceNatural Gas
Solid Fuel Gasification No
Carbon Capture TechnologyNo
Time From Cold Shutdown To Full Load1H
Multiple FuelsNo
Cofire FuelsNo
Switch Between Oil And Natural GasNo

Generator 02 Details Operating June 2001

TechnologyNatural Gas Fired Combustion Turbine
Prime MoverCombustion Turbine
OwnershipSingle Owner
Nameplate Capacity86.5 MW
Nameplate Power Factor0.85
Summer Capacity75 MW
Winter Capacity86 MW
Minimum Load64 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateJune 2001
Combined Heat & Power No
Sector NameElectric Utility (1)
Energy SourceNatural Gas
Solid Fuel Gasification No
Carbon Capture TechnologyNo
Time From Cold Shutdown To Full Load1H
Multiple FuelsNo
Cofire FuelsNo
Switch Between Oil And Natural GasNo

Generator 03 Details Operating June 2001

TechnologyNatural Gas Fired Combustion Turbine
Prime MoverCombustion Turbine
OwnershipSingle Owner
Nameplate Capacity86.5 MW
Nameplate Power Factor0.85
Summer Capacity75 MW
Winter Capacity86 MW
Minimum Load64 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateJune 2001
Combined Heat & Power No
Sector NameElectric Utility (1)
Energy SourceNatural Gas
Solid Fuel Gasification No
Carbon Capture TechnologyNo
Time From Cold Shutdown To Full Load1H
Multiple FuelsNo
Cofire FuelsNo
Switch Between Oil And Natural GasNo

Generator 04 Details Operating June 2001

TechnologyNatural Gas Fired Combustion Turbine
Prime MoverCombustion Turbine
OwnershipSingle Owner
Nameplate Capacity86.5 MW
Nameplate Power Factor0.85
Summer Capacity75 MW
Winter Capacity86 MW
Minimum Load64 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateJune 2001
Combined Heat & Power No
Sector NameElectric Utility (1)
Energy SourceNatural Gas
Solid Fuel Gasification No
Carbon Capture TechnologyNo
Time From Cold Shutdown To Full Load1H
Multiple FuelsNo
Cofire FuelsNo
Switch Between Oil And Natural GasNo

Generator 05 Details Operating June 2001

TechnologyNatural Gas Fired Combustion Turbine
Prime MoverCombustion Turbine
OwnershipSingle Owner
Nameplate Capacity86.5 MW
Nameplate Power Factor0.85
Summer Capacity75 MW
Winter Capacity86 MW
Minimum Load64 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateJune 2001
Combined Heat & Power No
Sector NameElectric Utility (1)
Energy SourceNatural Gas
Solid Fuel Gasification No
Carbon Capture TechnologyNo
Time From Cold Shutdown To Full Load1H
Multiple FuelsNo
Cofire FuelsNo
Switch Between Oil And Natural GasNo

Generator 06 Details Operating June 2001

TechnologyNatural Gas Fired Combustion Turbine
Prime MoverCombustion Turbine
OwnershipSingle Owner
Nameplate Capacity86.5 MW
Nameplate Power Factor0.85
Summer Capacity75 MW
Winter Capacity86 MW
Minimum Load64 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateJune 2001
Combined Heat & Power No
Sector NameElectric Utility (1)
Energy SourceNatural Gas
Solid Fuel Gasification No
Carbon Capture TechnologyNo
Time From Cold Shutdown To Full Load1H
Multiple FuelsNo
Cofire FuelsNo
Switch Between Oil And Natural GasNo

Ceredo Generating Station Plant Owners

Owner NameAddressGeneratorOwnership
We couldn't locate any owners for this plant

Power Plants with Similar Net Generation

Power plants with a similar annual net generation from Natural Gas.

RankPlant NamePlant LocationAnnual Generation
#490Spindle Hill Energy CenterFort Lupton, CO752.2 GWh
#491Emporia Energy CenterEmporia, KS749.0 GWh
#492Donald Von Raesfeld Power PlantSanta Clara, CA741.2 GWh
#493Alliant Energy NeenahNeenah, WI739.9 GWh
#494Deerhaven Generating StationGainesville, FL750.0 GWh
#495Vermillion Energy FacilityCayuga, IN727.9 GWh
#496R D GreenRobards, KY713.6 GWh
#497EG178 FacilitySnyder, TX713.1 GWh
#498HF Sinclair Puget Sound RefiningAnacortes, WA989.9 GWh
#499Cleveland Cnty Generating FacilityKings Mountain, NC712.0 GWh
#501Orlando Cogen LPOrlando, FL704.8 GWh
#502New Castle PlantWest Pittsburg, PA695.9 GWh
#503Riverside Generating LLCCatlettsburg, KY694.0 GWh
#504Vandolah Power StationWauchula, FL717.7 GWh
#505Hawk Road FacilityFranklin, GA682.5 GWh
#506Sumas Power PlantSumas, WA675.8 GWh
#507Greenidge Generation LLCDresden, NY673.5 GWh
#508Lodi Energy CenterLodi, CA673.4 GWh
#509Garrison Energy Center LLCDover, DE687.8 GWh
#510Tennessee Eastman OperationsKingsport, TN1.1 TWh

Nearby Power Plants

Below are closest 20 power plants surrounding Ceredo Generating Station.

Plant NamePlant LocationAnnual GenerationDistance
Belleville DamBelleville, WV223.4 GWh67.3 mi
Big SandyLouisa, KY1.1 TWh14.4 mi
Big Sandy Peaker PlantKenona, WV285.3 GWh3.6 mi
Gavin Power, LLCCheshire, OH13.3 TWh45.2 mi
Green Valley LFGTEAshland, KY18.8 GWh15 mi
Greenup HydroFranklin Furnace, OH261.5 GWh26.1 mi
Hanging Rock Energy FacilityIronton, OH9.0 TWh19.6 mi
Haverhill North Cogeneration FacilityFranklin Furnace, OH325.4 GWh22.4 mi
John E AmosSt Albans, WV8.3 TWh39.1 mi
Kyger CreekCheshire, OH5.5 TWh43.6 mi
LondonHandley, WV72.9 GWh64.2 mi
MarmetMarmet, WV67.4 GWh52.9 mi
Martin County Solar Project, LLCPilgrim, KY182.2 GWh41.8 mi
Morehead Generating FacilityMorehead, KY6.3 GWh56.1 mi
MountaineerNew Haven, WV5.4 TWh53.2 mi
Pixelle Specialty Solutions LLC - ChilliChillicothe, OH272.9 GWh70.2 mi
RacineRacine, OH174.8 GWh50.7 mi
Riverside Generating LLCCatlettsburg, KY694.0 GWh12.8 mi
Rolling Hills GeneratingWilkesville, OH2.2 TWh50.6 mi
WinfieldWinfield, WV84.4 GWh35.3 mi