Tenmile Creek
TBD, TBD, FL 32449Plant Summary Information
Tenmile Creek is ranked #33 out of 227 solar farms in Florida in terms of total annual net electricity generation.
Tenmile Creek generated 45.5 GWh during the 3-month period between April 2026 to July 2026.
| Plant Name | Tenmile Creek |
|---|---|
| Utility Name | Florida Power & Light Co |
| Location | Calhoun County, FL |
| Initial Operation Date | January 2025 |
| Last Update | Jul 2026 |
| Annual Generation | 171.4 GWh |
| Annual Consumption | 662.6 k MMBtu |
| Ranked #2,803 out of 13,285 Power Plants Nationwide | |
| Ranked #572 out of 7,198 Solar Power Plants Nationwide | |
| Ranked #109 out of 334 Florida Power Plants | |
| Ranked #33 out of 227 Florida Solar Power Plants | |
| Fuel Types | Solar |
Map of Tenmile Creek
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Tenmile Creek.
Monthly Net Generation for Tenmile Creek
Monthly Plant Fuel Consumption for Tenmile Creek
Tenmile Creek Details
| Summary Information | |
|---|---|
| Plant Name | Tenmile Creek (65886) |
| Plant Address | TBD, TBD, FL 32449 |
| Utility | Florida Power & Light Co (6452) |
| Latitude, Longitude | 30.50364, -85.16738 |
| Generation Dates on File | Jan 2025 to Jul 2026 |
| Initial Operation Date | January 2025 |
| Annual Generation | 171.4 GWh |
| Fuel Types | Solar |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Regulated |
| NERC Region | SERC |
| Balancing Authority | Florida Power & Light Company (FPL) |
| NAICS Code | Utilities (22) |
| Sector | Electric Utility (1) |
| Water Source | |
| Ash Impoundment | |
| Transmission / Distribution Owner | Florida Power & Light Co (6452) FL |
| Grid Voltage | 230.00 kV |
| Energy Storage | Yes |
Generator 1 Details Operating January 2025
| Technology | Solar Photovoltaic |
|---|---|
| Prime Mover | Photovoltaic |
| Ownership | Single Owner |
| Nameplate Capacity | 74.5 MW |
| Nameplate Power Factor | 0.95 |
| Summer Capacity | 74.5 MW |
| Winter Capacity | 74.5 MW |
| Uprate/Derate Completed | No |
|---|---|
| Status | Operating |
| First Operation Date | January 2025 |
| Sector Name | Electric Utility (1) |
| Energy Source | Solar |
| Multiple Fuels | No |
| Solar Details | |
| Single Axis Tracking | Yes |
|---|---|
| Bifacial | Yes |
| Azimuth Angle | 180 |
| Tilt Angle | 52 |
| DC Net Capacity | 108 MW |
| Crystalline Silicon | Yes |
| Net Metering Agreement | No |
| Virtual Net Metering Agreement | No |
Generator 2 Details Operating December 2025
| Technology | Batteries |
|---|---|
| Prime Mover | Battery |
| Ownership | Single Owner |
| Nameplate Capacity | 74.5 MW |
| Summer Capacity | 74.5 MW |
| Winter Capacity | 74.5 MW |
| Uprate/Derate Completed | No |
|---|---|
| Status | Operating |
| First Operation Date | December 2025 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Electricity used for energy storage |
| Energy Storage Details | |
| Nameplate Energy Capacity MWH | 223.5 |
|---|---|
| Maximum Charge Rate | 74.5 MW |
| Maximum Discharge Rate | 74.5 MW |
| Storage Technology | LIB |
| Nameplate Reactive Power Rating | 76 |
| Storage Enclosure Type | CS |
| Frequency Regulation | Yes |
| Co Located Renewable Firming | P |
| Voltage Or Reactive Power Support | Yes |
| Ac Coupled | Yes |
| Direct Support Of Another Unit | Yes |
| Direct Support Plant Id | 65886 |
| Direct Support Gen Id | 1 |
| Support T D Asset | Yes |
Tenmile Creek Plant Owners
| Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #562 | Georges Lake | TBD, FL | 178.8 GWh |
| #563 | Taylor Creek Solar | Orlando, FL | 178.7 GWh |
| #564 | Lone Star Solar | Cameron, SC | 175.9 GWh |
| #565 | Archtop Solar | Gibson City, IL | 178.0 GWh |
| #566 | FPL Saw Palmetto Solar Energy Center | Youngstown, FL | 177.8 GWh |
| #567 | Sundance Renewable Energy Center | Lee, FL | 177.6 GWh |
| #568 | Swallowtail | Defuniak Springs, FL | 177.5 GWh |
| #569 | Spring Grove Solar 2 | Spring Grove, VA | 177.4 GWh |
| #570 | Charlie Creek Solar Power Plant | Wauchula, FL | 177.2 GWh |
| #571 | Fourmile Creek | Altha, FL | 171.6 GWh |
| #573 | Snipesville | Denton, GA | 176.6 GWh |
| #574 | Hendry Isles | TBD, FL | 176.2 GWh |
| #575 | Hildreth Solar Power Plant | O'Brien, FL | 176.1 GWh |
| #576 | North Star Solar Project | North Branch, MN | 176.0 GWh |
| #577 | Swift Air Solar III | Odessa, TX | 175.8 GWh |
| #578 | Mitchell Creek | TBD, FL | 175.7 GWh |
| #579 | Hardeetown Solar Power Plant | Chiefland, FL | 175.7 GWh |
| #580 | Harmony Solar (FL) | St. Cloud, FL | 175.6 GWh |
| #581 | Sweetwater Solar | Green River, WY | 175.1 GWh |
| #582 | Grand View Solar Two | Grand View, ID | 175.0 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Tenmile Creek.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Apalachee | Marianna, FL | 146.4 GWh | 18.7 mi |
| Bay Ranch Solar Power Plant | Panama City, FL | 184.2 GWh | 30.4 mi |
| Big Brook | Clarksville, FL | 101.5 GWh | 7 mi |
| Blue Springs | Marianna, FL | 133.0 GWh | 20 mi |
| Cool Springs Solar (Hybrid) | Bainbridge, GA | 499.2 GWh | 33.5 mi |
| Fourmile Creek | Altha, FL | 171.6 GWh | 7.8 mi |
| FPL Chipola River Solar Energy Center | Altha, FL | 143.7 GWh | 7.4 mi |
| FPL Cypress Pond Solar | Vernon, FL | 173.2 GWh | 17.3 mi |
| FPL Flowers Creek Solar Energy Center | Altha, FL | 139.9 GWh | 8.8 mi |
| FPL Saw Palmetto Solar Energy Center | Youngstown, FL | 177.8 GWh | 17.3 mi |
| FPL Shirer Branch Solar Energy Center | Clarksville, FL | 167.1 GWh | 10 mi |
| Gadsden County Solar | Chattahoochee, FL | 186.0 GWh | 28.4 mi |
| Gulf Power Blue Indigo Energy | Cottondale, FL | 142.9 GWh | 29.3 mi |
| J Woodruff | Chattahoochee, FL | 228.5 GWh | 22.9 mi |
| Lansing Smith | Southport, FL | 3.8 TWh | 35.7 mi |
| Mule Creek Renewable Energy Center | Panama City, FL | 190.2 GWh | 30.4 mi |
| Sand Pine | Altha, FL | 60.4 GWh | 6.9 mi |
| Sandy Creek Solar Power Plant | Panama City, FL | 169.9 GWh | 31.2 mi |
| Springhill Gas Recovery Plant | Campbellton, FL | 32.4 GWh | 33.1 mi |
| Wild Azalea Solar Energy Center | Chattahoochee, FL | 170.7 GWh | 28 mi |