Nine Canyon
92308 S. Nine Canyon Road, Kennewick, WA 99336Plant Summary Information
Nine Canyon is ranked #19 out of 23 wind farms in Washington in terms of total annual net electricity generation.
Nine Canyon generated 53.4 GWh during the 3-month period between September 2024 to December 2024.
Plant Name | Nine Canyon |
---|---|
Utility Name | Energy Northwest |
Location | Benton County, WA |
Initial Operation Date | September 2002 |
Last Update | Dec 2024 |
Annual Generation | 209.3 GWh |
Annual Consumption | 761.8 k MMBtu |
Ranked #2,315 out of 12,288 Power Plants Nationwide | |
Ranked #717 out of 1,353 Wind Power Plants Nationwide | |
Ranked #64 out of 131 Washington Power Plants | |
Ranked #19 out of 23 Washington Wind Power Plants | |
Fuel Types | Wind |
Map of Nine Canyon
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Nine Canyon.
Monthly Net Generation for Nine Canyon
Nine Canyon Details
Summary Information | |
---|---|
Plant Name | Nine Canyon (7936) |
Plant Address | 92308 S. Nine Canyon Road, Kennewick, WA 99336 |
Utility | Energy Northwest (20160) |
Latitude, Longitude | 46.0958, -119.0964 |
Generation Dates on File | Jun 2002 to Dec 2024 |
Initial Operation Date | September 2002 |
Annual Generation | 209.3 GWh |
Fuel Types | Wind |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Regulated |
NERC Region | WECC |
Balancing Authority | Bonneville Power Administration (BPAT) |
NAICS Code | Utilities (22) |
Sector | Electric Utility (1) |
Water Source | |
Ash Impoundment | No |
Transmission / Distribution Owner | PUD No 1 of Benton County (1579) WA |
Grid Voltage | 115.00 kV |
Energy Storage | No |
Generator 1 Details Operating September 2002
Technology | Onshore Wind Turbine |
---|---|
Prime Mover | Wind Turbine, Onshore |
Ownership | Single Owner |
Nameplate Capacity | 95.9 MW |
Summer Capacity | 95 MW |
Winter Capacity | 95 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | September 2002 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Wind |
Solid Fuel Gasification | No |
Turbines/Hydrokinetic Buoys | 63 |
Other Planned Modifications | No |
Multiple Fuels | No |
Turbine Details | |
Number Of Turbines | 63 |
---|---|
Predominant Turbine Manufacturer | Siemens |
Predominant Turbine Model Number | SWT-1.3-62 |
Design Wind Speed | 14 MPH |
Wind Quality Class | 4 - Very Low Wind |
Turbine Hub Height Feet | 200 |
Nine Canyon Plant Owners
Owner Name | Address | Ownership | |
---|---|---|---|
We couldn't locate any owners for this plant |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#707 | San Juan Mesa Wind Project LLC | Elida, NM | 218.5 GWh |
#708 | Star Point Wind Project LLC | Wasco, OR | 217.8 GWh |
#709 | Crescent Ridge | Tiskilwa, IL | 216.5 GWh |
#710 | Coachella Hills Wind | Palm Springs, CA | 215.9 GWh |
#711 | Flat Water Wind Farm LLC | Du Bois, NE | 215.6 GWh |
#712 | Foote Creek I | McFadden, WY | 215.5 GWh |
#713 | Fairbanks Wind Park | Garden, MI | 212.6 GWh |
#714 | Weaver Wind | Township 16, ME | 212.1 GWh |
#715 | Osceola Windpower II | Harris, IA | 211.3 GWh |
#716 | Barton Chapel Wind Farm | Jacksboro, TX | 210.9 GWh |
#718 | Steele Flats Wind Project LLC | Diller, NE | 209.0 GWh |
#719 | Cedar Springs Wind IV | Douglas, WY | 208.6 GWh |
#720 | Hoosier Wind Project LLC | Goodland, IN | 207.8 GWh |
#721 | Windthorst-2 | Archer, TX | 206.4 GWh |
#722 | Broken Bow Wind LLC | Broken Bow, NE | 205.7 GWh |
#723 | NWP Indian Mesa Wind Farm | Iraan, TX | 205.6 GWh |
#724 | Scurry County Wind LP | Snyder, TX | 205.4 GWh |
#725 | Elm Creek Wind II LLC | Trimont, MN | 205.4 GWh |
#726 | Cohocton Wind Project | Cohocton, NY | 203.5 GWh |
#727 | North Allegheny Windpower Project | Lilly, PA | 203.5 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Nine Canyon.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Butter Creek Power LLC | Echo, OR | 10.9 GWh | 31.4 mi |
Chandler | Benton City, WA | 31.4 GWh | 26.4 mi |
Columbia Generating Station | Richland, WA | 9.8 TWh | 28.3 mi |
Combine Hills I | Milton-Freewater, OR | 73.0 GWh | 26.4 mi |
Eltopia Branch Canal 4.6 | Pasco, WA | 8.0 GWh | 20.9 mi |
Eurus Combine Hills Turbine Ranch 2 | Milton Freewater, OR | 163.6 GWh | 26.4 mi |
Four Corners Windfarm LLC | Echo, OR | 20.7 GWh | 29.7 mi |
FPL Energy Vansycle LLC (OR) | Touchet, OR | 257.0 GWh | 14.6 mi |
FPL Energy Vansycle LLC (WA) | Touchet, WA | 370.3 GWh | 8.9 mi |
Hermiston Generating Plant | Hermiston, OR | 3.3 TWh | 24.1 mi |
Hermiston Power Partnership | Hermiston, OR | 4.4 TWh | 23.3 mi |
Horn Rapids Solar, Storage and Training | Richland, WA | 6.6 GWh | 20.8 mi |
Ice Harbor | Burbank, WA | 1.4 TWh | 14.9 mi |
McNary | Umatilla, OR | 3.7 TWh | 14.5 mi |
McNary Dam Fish Attraction Project | Plymouth, WA | 64.2 GWh | 14.5 mi |
NorWest Energy 9 LLC | Pendleton, OR | 10.7 GWh | 17.1 mi |
Oregon Trail Windfarm LLC | Echo, OR | 22.9 GWh | 30.4 mi |
Potholes East Canal 66.0 | Pasco, WA | 4.8 GWh | 20.9 mi |
Vansycle | Touchet, OR | 60.0 GWh | 23.7 mi |
Vansycle II Wind Energy Center | Athena, OR | 357.3 GWh | 27.8 mi |