Mid-Georgia Cogeneration Facility
200 Oaky Woods Road, Kathleen, GA 31047Plant Summary Information
Mid-Georgia Cogeneration Facility is ranked #19 out of 46 natural gas power plants in Georgia in terms of total annual net electricity generation.
Mid-Georgia Cogeneration Facility is comprised of 3 generators and generated 6.9 GWh during the 3-month period between February 2026 to May 2026.
| Plant Name | Mid-Georgia Cogeneration Facility |
|---|---|
| Utility Name | SEPG MGA, LLC |
| Location | Houston County, GA |
| Initial Operation Date | October 1997 |
| Last Update | May 2026 |
| Annual Generation | 154.1 GWh |
| Annual Consumption | 1.4 M MMBtu |
| Ranked #2,923 out of 13,081 Power Plants Nationwide | |
| Ranked #827 out of 2,206 Natural Gas Power Plants Nationwide | |
| Ranked #70 out of 247 Georgia Power Plants | |
| Ranked #19 out of 46 Georgia Natural Gas Power Plants | |
| Fuel Types | Natural Gas : 92.9% Distillate Fuel Oil : 7.1% |
| Previous Operators |
Mid-Georgia Cogen LP (2013 to 2014) SEPG Operating Services, LLC MGC (2015 to 2020) SEPG MGA, LLC (2021 to 2025) |
Map of Mid-Georgia Cogeneration Facility
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Mid-Georgia Cogeneration Facility.
Monthly Net Generation for Mid-Georgia Cogeneration Facility
Monthly Plant Fuel Consumption for Mid-Georgia Cogeneration Facility
Mid-Georgia Cogeneration Facility Details
| Summary Information | |
|---|---|
| Plant Name | Mid-Georgia Cogeneration Facility (55040) |
| Plant Address | 200 Oaky Woods Road, Kathleen, GA 31047 |
| Utility | SEPG MGA, LLC (12564) |
| Latitude, Longitude | 32.4856, -83.6039 |
| Generation Dates on File | Jan 2001 to May 2026 |
| Initial Operation Date | October 1997 |
| Annual Generation | 154.1 GWh |
| Fuel Types | Natural Gas : 92.9% Distillate Fuel Oil : 7.1% |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | Yes |
| FERC Cogeneration Docket Number | 96-26-001 |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | Yes |
| FERC Exempt Wholesale Generator Docket Number | 96-14-000 |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | SERC |
| Balancing Authority | Southern Company Services, Inc. - Trans (SOCO) |
| NAICS Code | Utilities (22) |
| Sector | IPP CHP (3) |
| Water Source | Municipality |
| Ash Impoundment | No |
| Transmission / Distribution Owner | Georgia Power Co (7140) GA |
| Grid Voltage | 230.00 kV |
| Energy Storage | No |
| Natural Gas Information | |
| Local Distribution Company (LDC) | Other - See pipeline notes. |
| Pipeline Name | Other - Please explain in pipeline notes below. |
| Natural Gas Storage | No |
Generator CT1 Details Operating October 1997
| Technology | Natural Gas Fired Combined Cycle |
|---|---|
| Prime Mover | Combined Cycle Combustion Turbine Part |
| Unit Code | CC01 |
| Ownership | Wholly Owned by Other Entity |
| Can Bypass Heat Recovery Steam Generator | No |
| Nameplate Capacity | 106.5 MW |
| Nameplate Power Factor | 0.9 |
| Summer Capacity | 101.5 MW |
| Winter Capacity | 115 MW |
| Minimum Load | 80 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | October 1997 |
|---|---|
| Combined Heat & Power | Yes |
| Sector Name | IPP CHP (3) |
| Topping Or Bottoming | T |
| Energy Source | Natural Gas / Distillate Fuel Oil |
| Startup Source | Natural Gas |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 12H |
| Multiple Fuels | Yes |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | Yes |
| Multifuel Details | |
| Switch When Operating | Yes |
|---|---|
| Net Summer Capacity With Natural Gas | 101.5 MW |
| Net Winter Capacity With Natural Gas | 125 MW |
| Net Summer Capacity With Oil | 101.5 MW |
| Net Winter Capacity With Oil | 120 MW |
| Time To Switch From Gas To Oil | 1H |
| Time To Switch From Oil To Gas | 1H |
| Factors That Limit Switching | Yes |
| Storage Limits | Yes |
Generator ST1 Details Operating December 1997
| Technology | Natural Gas Fired Combined Cycle |
|---|---|
| Prime Mover | Combined Cycle Steam Part |
| Unit Code | CC01 |
| Ownership | Wholly Owned by Other Entity |
| Duct Burners | No |
| Nameplate Capacity | 110 MW |
| Nameplate Power Factor | 0.9 |
| Summer Capacity | 100 MW |
| Winter Capacity | 100 MW |
| Minimum Load | 50 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | December 1997 |
|---|---|
| Combined Heat & Power | Yes |
| Sector Name | IPP CHP (3) |
| Topping Or Bottoming | T |
| Energy Source | Natural Gas |
| Startup Source | Natural Gas |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 12H |
| Multiple Fuels | No |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Generator CT2 Details Operating February 1998
| Technology | Natural Gas Fired Combined Cycle |
|---|---|
| Prime Mover | Combined Cycle Combustion Turbine Part |
| Unit Code | CC01 |
| Ownership | Wholly Owned by Other Entity |
| Can Bypass Heat Recovery Steam Generator | No |
| Nameplate Capacity | 106.5 MW |
| Nameplate Power Factor | 0.9 |
| Summer Capacity | 101.5 MW |
| Winter Capacity | 115 MW |
| Minimum Load | 80 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | February 1998 |
|---|---|
| Combined Heat & Power | Yes |
| Sector Name | IPP CHP (3) |
| Topping Or Bottoming | T |
| Energy Source | Natural Gas / Distillate Fuel Oil |
| Startup Source | Natural Gas |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 12H |
| Multiple Fuels | Yes |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | Yes |
| Multifuel Details | |
| Switch When Operating | Yes |
|---|---|
| Net Summer Capacity With Natural Gas | 101.5 MW |
| Net Winter Capacity With Natural Gas | 125 MW |
| Net Summer Capacity With Oil | 101.5 MW |
| Net Winter Capacity With Oil | 120 MW |
| Time To Switch From Gas To Oil | 1H |
| Time To Switch From Oil To Gas | 1H |
| Factors That Limit Switching | Yes |
| Storage Limits | Yes |
Mid-Georgia Cogeneration Facility Plant Owners
| Owner Name | Address | Generator | Ownership |
|---|---|---|---|
| Mid-Georgia Cogen, LP | 200 Oakley Woods Rd, Kathleen, GA 31047 | Generator CT1 | 100.00% |
| Mid-Georgia Cogen, LP | 200 Oakley Woods Rd, Kathleen, GA 31047 | Generator CT2 | 100.00% |
| Mid-Georgia Cogen, LP | 200 Oakley Woods Rd, Kathleen, GA 31047 | Generator ST1 | 100.00% |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #817 | Eight Flags Energy | Fernandina Beach, FL | 147.2 GWh |
| #818 | Valencia Energy Facility | Belen, NM | 147.1 GWh |
| #819 | Limon Generating Station | Limon, CO | 147.8 GWh |
| #820 | Gans | Gans, PA | 145.5 GWh |
| #821 | South Plant (CO) | Colorado Springs, CO | 145.7 GWh |
| #822 | Delray | Detroit, MI | 145.1 GWh |
| #823 | Millcreek Power Generation | St. George, UT | 145.0 GWh |
| #824 | Weston RICE | Kronenwetter, WI | 144.5 GWh |
| #825 | Lange Generating Station | Rapid City, SD | 144.5 GWh |
| #826 | Castleton Energy Center | Castleton, NY | 144.5 GWh |
| #828 | Escanaba Mill | Escanaba, MI | 452.4 GWh |
| #829 | Hamlet Generating Facility | Hamlet, NC | 144.9 GWh |
| #830 | Solway CT | Solway, MN | 142.9 GWh |
| #831 | 491 E 48th Street | Holland, MI | 142.2 GWh |
| #832 | Elk River | Elk River, MN | 155.5 GWh |
| #833 | Lederle Laboratories | Pearl River, NY | 142.0 GWh |
| #834 | Central Utility Plant - Texas A&M | College Station, TX | 140.1 GWh |
| #835 | Georgia-Pacific Palatka Operations | Palatka, FL | 331.4 GWh |
| #836 | Calcasieu | Sulphur, LA | 138.8 GWh |
| #837 | Berry Cogen Tanne Hills 18 | Maricopa, CA | 138.7 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Mid-Georgia Cogeneration Facility.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| ADS Renewable Energy-Wolf Creek LLC | Dry Branch, GA | 11.8 GWh | 22.3 mi |
| Arnold Cochran | Cochran, GA | 3.5 GWh | 16.3 mi |
| Bibb Williams | Macob, GA | 4.8 GWh | 25.8 mi |
| CG PS Portfolio 1, LLC | Kathleen, GA | 6.5 GWh | 6.3 mi |
| Coody Cochran | Cochran, GA | 5.6 GWh | 15.7 mi |
| CPV Stagecoach Solar | Andersonville, GA | 168.2 GWh | 33.7 mi |
| Flint River Operations | Oglethorpe, GA | 440.4 GWh | 31.4 mi |
| Fort Valley State University Solar | Fort Valley, GA | 20.7 GWh | 16.3 mi |
| Freeman Avenue | Andersonville, GA | 2.9 GWh | 38 mi |
| Graphic Packaging Intl Macon Mill | Macon, GA | 382.2 GWh | 19.8 mi |
| Pineview Solar, LLC | Pitts, GA | 8.4 GWh | 34.1 mi |
| Richland Solar Center | Jeffersonville, GA | 37.1 GWh | 16.8 mi |
| Robins | Robins AFB, GA | 4.6 GWh | 6.6 mi |
| Robins Air Force Base Solar | Macon, GA | 200.8 GWh | 13.5 mi |
| Smarr Energy Center | Forsyth, GA | 149.1 GWh | 37.2 mi |
| SR Perry | Perry, GA | 153.5 GWh | 11.1 mi |
| Twiggs Solar | Dry Branch, GA | 371.9 GWh | 10.5 mi |
| White Pine Solar, LLC | Butler, GA | 187.9 GWh | 38.1 mi |
| Wilkinson DeFore (Safari Energy) | Gordon, GA | 6.6 GWh | 32.5 mi |
| Wilkinson DeFore (Westbound) | Gordon, GA | 4.3 GWh | 31.8 mi |