Lowndes Tycor Farms
6734 GA-376, Lake Park, GA 31636Plant Summary Information
Lowndes Tycor Farms is ranked #97 out of 150 solar farms in Georgia in terms of total annual net electricity generation.
Lowndes Tycor Farms generated 938.0 MWh during the 3-month period between September 2024 to December 2024.
Plant Name | Lowndes Tycor Farms |
---|---|
Utility Name | Safari Energy, LLC |
Location | Lowndes County, GA |
Initial Operation Date | May 2020 |
Last Update | Dec 2024 |
Annual Generation | 4.6 GWh |
Annual Consumption | 16.5 k MMBtu |
Ranked #8,092 out of 12,288 Power Plants Nationwide | |
Ranked #3,205 out of 6,174 Solar Power Plants Nationwide | |
Ranked #178 out of 246 Georgia Power Plants | |
Ranked #97 out of 150 Georgia Solar Power Plants | |
Fuel Types | Solar |
Map of Lowndes Tycor Farms
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Lowndes Tycor Farms.
Monthly Net Generation for Lowndes Tycor Farms
Lowndes Tycor Farms Details
Summary Information | |
---|---|
Plant Name | Lowndes Tycor Farms (64279) |
Plant Address | 6734 GA-376, Lake Park, GA 31636 |
Utility | Safari Energy, LLC (63640) |
Latitude, Longitude | 30.68819, -83.16715 |
Generation Dates on File | May 2020 to Dec 2024 |
Initial Operation Date | May 2020 |
Annual Generation | 4.6 GWh |
Fuel Types | Solar |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | Yes |
FERC Small Power Producer Docket Number | QF20-494-000 |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | SERC |
Balancing Authority | Southern Company Services, Inc. - Trans (SOCO) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | No |
Transmission / Distribution Owner | Georgia Power Co (7140) GA |
Grid Voltage | 0.60 kV |
Energy Storage | No |
Generator LTF Details Operating May 2020
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Wholly Owned by Other Entity |
Nameplate Capacity | 2.3 MW |
Summer Capacity | 2.3 MW |
Winter Capacity | 2.3 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | May 2020 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Solar |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Solar Details | |
Single Axis Tracking | Yes |
---|---|
Azimuth Angle | 180 |
Tilt Angle | 55 |
DC Net Capacity | 3 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | No |
Lowndes Tycor Farms Plant Owners
Owner Name | Address | Ownership |
---|---|---|
Lowndes County GA S2, LLC | 1407 Broadway, 24th Floor, New York, NY 10018 | 100.00% |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#3195 | Woodlawn CSG | Crete, IL | 4.6 GWh |
#3196 | Monroe 009452 SCS Cozad, LLC | Cozad, NE | 4.6 GWh |
#3197 | Trenton Solar Farm (MO) | Trenton, MO | 4.6 GWh |
#3198 | Burlington Coat Factory Solar | Florence, NJ | 4.6 GWh |
#3199 | LPEA Sunnyside Solar 1 Facility | Durango, CO | 4.6 GWh |
#3200 | Galloway Landfill | Wall, NJ | 4.6 GWh |
#3201 | IL Sidney Project1 | Sidney, IL | 4.6 GWh |
#3202 | MilfordSolar OR | Forest Grove, OR | 4.6 GWh |
#3203 | Exeter Solar | Exeter, CA | 4.6 GWh |
#3204 | Chicopee Solar | Chicopee, MA | 4.6 GWh |
#3206 | USS Solar Brick | Standard City, IL | 4.6 GWh |
#3207 | Mount Dora Solar Farm F | Mount Dora, FL | 4.6 GWh |
#3208 | California City | California City, CA | 4.6 GWh |
#3209 | Sierra Pacific Chinese Camp | Chinese Camp, CA | 4.6 GWh |
#3210 | Round Grove 2 | Lyndon, IL | 4.6 GWh |
#3211 | Solar Las Vegas MB-1 | Las Vegas, NV | 4.6 GWh |
#3212 | CA-DGS-California Men's Colony | San Luis Obispo, CA | 4.6 GWh |
#3213 | Hinton | Hinton, OK | 4.5 GWh |
#3214 | Niagara Bottling - Bloomfield | Bloomfield, CT | 4.5 GWh |
#3215 | POM Beverage Solar | Del Rey, CA | 4.5 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Lowndes Tycor Farms.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Falmouth Renewable Energy Center | Live Oak, FL | 129.3 GWh | 23.8 mi |
Hamilton Solar Power Plant | Jasper, FL | 158.9 GWh | 16.9 mi |
Lakeland Solar Energy LLC | Lakeland, GA | 3.4 GWh | 24.3 mi |
Lowndes Cowart | Valdosta, GA | 6.8 GWh | 10.2 mi |
Lowndes IDA | Valdosta, GA | 3.1 GWh | 10.8 mi |
Moody Air Force Base Solar | Valdosta, GA | 76.1 GWh | 18.9 mi |
Norton Creek | TBD, FL | 52.4 GWh | 23.1 mi |
PCA-Valdosta Mill | Valdosta, GA | 322.6 GWh | 8.1 mi |
Pecan Row Landfill To Electric Facility | Valdosta, GA | 30.5 GWh | 14.5 mi |
Quitman II Solar | Quitman, GA | 307.1 GWh | 31.2 mi |
Quitman Solar | Quitman, GA | 324.5 GWh | 30.4 mi |
Suwannee River | Live Oak, FL | 76.0 GWh | 21.6 mi |
Suwannee Solar Facility | Live Oak, FL | 16.2 GWh | 21.6 mi |
Swift Creek Chemical Complex | White Springs, FL | 60.5 GWh | 24.3 mi |
Twin Rivers Solar Power Plant | Jasper, FL | 159.3 GWh | 19.3 mi |
Valdosta | Valdosta, GA | 1.4 GWh | 9.1 mi |
Valdosta Prison | Valdosta, GA | 1.7 GWh | 16.6 mi |
Valdosta Water Treatment Plant | Valdosta, GA | 52.0 MWh | 16.4 mi |
Vidalia Water Treatment Plant | Hahira, GA | 1.2 GWh | 28.4 mi |
Winquepin Renewable Energy Center | Lee, FL | 126.7 GWh | 29.1 mi |